ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
|
228
|
Tuesday, January 08, 2013, 14:18 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | Electrical check | TM#1 was electrically check with out a
target see attached PDF for results. |
|
|
230
|
Monday, January 14, 2013, 14:09 |
Travis Cave | ITW | Standard Operation | TM1 | no target | module move | TM#1 has been moved from the south hot
hell to the west target station, move went
well. |
|
|
231
|
Tuesday, January 15, 2013, 10:49 |
David Wang | ITW | Standard Operation | TM1 | no target | TM1 vacuum system connection in ITW | I connected TM 1 vacuum system in ITW.
The TM1 and ITW will be pumped out for shut
down routine leak check. |
|
|
283
|
Wednesday, April 03, 2013, 10:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module move | TM#1 has been moved from the south west
silo to the south hot cell, move went well. |
|
|
298
|
Tuesday, April 16, 2013, 11:10 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 has been moved from the NE Silo to
the south hot cell, move went well. |
|
|
301
|
Wednesday, April 17, 2013, 09:26 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | Electrical check | Electrical check was performed on TM#3
with no target nothing was wrong was found,
but our megger does not go above 1000 volts |
|
|
303
|
Wednesday, April 17, 2013, 10:59 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the south hot cell to the conditioning station.
Move went well. The fields around the module |
|
|
319
|
Wednesday, April 24, 2013, 10:14 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 has been moved from the conditioning
station to the south hot cell, move went
well. |
|
|
337
|
Friday, May 10, 2013, 11:02 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
has been moved from the south hot cell to
the conditioning station. |
|
|
338
|
Friday, May 10, 2013, 11:11 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | Electrical check | TM#3 electrical check with no target and
no source tray, see pdf. |
|
|
395
|
Wednesday, July 03, 2013, 10:43 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
was moved from the north east silo to the
south hot cell the move went well. |
|
|
403
|
Thursday, July 18, 2013, 10:08 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
has been moved from the conditioning station
to the north east silo, move went well. |
|
|
431
|
Tuesday, August 27, 2013, 17:18 |
Grant Minor | Conditioning Station | Repair | TM3 | no target | TM3 Rev 3 source tray - prelminary leak check results at CS | David Wang started a helium leak check
on TM3 at the CS this morning.
David will create an e-log once his |
|
|
433
|
Wednesday, August 28, 2013, 14:25 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the conditioning station to the south hot
cell. The fields observed around the containment |
|
|
437
|
Thursday, August 29, 2013, 12:03 |
Grant Minor | South Hot-Cell | Repair | TM3 | no target | Heat Shield Circuit Leak |
|
|
|
448
|
Wednesday, September 11, 2013, 11:31 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved to the
conditioning station from the south hot cell. |
|
|
456
|
Thursday, September 19, 2013, 09:08 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | wiring harness | The wiring harness for TM#3 was made and
a continuity and megger test was done on
it and it passed, it has since been installed |
|
|
457
|
Thursday, September 19, 2013, 11:09 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | no target | Electrical check | Electrical check of TM#3 with no target
was performed and it failed. |
|
|
461
|
Tuesday, September 24, 2013, 08:15 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | Electrical check | Electrical check was done on TM#3 yesterday
and again the coil lines to the 60kV common
and the coil line to each other failed, as |
|
|
487
|
Wednesday, October 02, 2013, 14:47 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | Electrical check | Electrical check done on TM#4 with no target,
see PDF. |
|