Entry  Tuesday, October 08, 2013, 13:11, Travis Cave, Spent Target Vault, Standard Operation, , SiC#29, Spent target move Vault_Storage_October_8_2013.pdf
SiC#29 has been moved to the spent target vault. The target was placed in Pail #109 and placed into slot 2B it was 24.7mS/hr upon removal from the south
hot cell. See attached PDF of the vault details.
Entry  Tuesday, October 08, 2013, 14:55, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
TM#4 with no target was to be moved today but the move was aborted when the crane failed to move in the East - West direction. The crane does not preform
this function in either remote or pendant operation.
Entry  Wednesday, October 16, 2013, 10:12, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
TM#4 with no target has been moved from the south west silo to the south hot cell.
Entry  Friday, October 18, 2013, 14:56, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, Electrical check TM#4_no_target_post_coilelectest.PDF
With the coil line removed an electrical check was done on TM#4 at the South Hot Cell see attached pdf.
Entry  Tuesday, October 22, 2013, 11:18, Travis Cave, ITW, Standard Operation, TM1, UC#7, module move 
TM#1 with UC#7 has been moved from the ITW to the south west silo.
Entry  Wednesday, October 23, 2013, 09:28, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#7, module move 
TM#1 with UC #7 has been moved from the south west silo to the south hot cell.
Entry  Wednesday, October 23, 2013, 12:07, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, module move 
TM#1 with no target has been moved back to the south west silo from the south hot cell.
Entry  Thursday, October 24, 2013, 11:31, Travis Cave, Spent Target Vault, Standard Operation, , UC#7, Spent target move Vault_Storage_October_24_2013.pdf
UC #7 has been moved from the south hot cell to the spent target vault, it was placed in pail #110 and put in slot 8B of the vault, it was 22.6mSv/hr
upon removal from the hot cell. See attached PDF for vault details.
Entry  Thursday, October 24, 2013, 11:32, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
TM#4 with no target has been moved from the conditioning station to the south hot cell.
Entry  Friday, October 25, 2013, 10:26, Travis Cave, ITW, Standard Operation, TM4, Ta#41, module move 
TM#4 with Ta#41 has been moved from the south hot cell to the west target station.
    Reply  Friday, October 25, 2013, 14:09, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#41, Target conductance TM#4_Ta#41_elec_test_SHC.PDF


    
        
            Anders Mjos wrote:
        
        
            
            The conductance check on the electrical check was found to be outside of accepted values for the TBHT
Entry  Friday, November 01, 2013, 09:08, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, module move 
TM#2 has been moved from the north west silo to the south hot cell. The module has a field of about 3.1mSv/hr when it was lowered into the hot cell.
Entry  Tuesday, November 19, 2013, 10:52, Travis Cave, South Hot-Cell, Standard Operation, TM3, NiO#2, module move 
TM#3 with NiO#2 moved from ITE to the south hot cell.
Entry  Wednesday, November 20, 2013, 09:52, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, module move 
TM#3 with no target has been moved from the south hot cell to the north east silo.
Entry  Friday, November 22, 2013, 10:29, Travis Cave, Spent Target Vault, Standard Operation, , NiO#2, Spent target move Vault_Storage_November_22_2013.pdf
NiO#2 has been moved from the south hot cell into spent target storage. It was placed in pail 111 in slot 3C of the storage vault. It was 76.4mSv/hr
upon removal from the south hot cell.
Entry  Monday, November 25, 2013, 11:48, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, module move 
TM#3 with no target has been moved from the north east silo to the south hot cell.
Entry  Tuesday, November 26, 2013, 14:10, Travis Cave, Crane, Maintenance, , , Thermal relay replaced 
The bad thermal motor protection relay for the crane has been replaced with a new unit. Crane was tested in pendant(local) operation and all drives worked.
Entry  Monday, December 02, 2013, 11:29, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, module move 
TM#3 with no target has been moved from the south hot cell to the northeast silo.
Entry  Tuesday, December 03, 2013, 10:35, Travis Cave, ITW, Standard Operation, , , fields above and in the target station with blocks off 
The blocks have been removed from the west target station. The fields at the top of the target pit at the railing at waist level is about 80uSv/hr, Turbo
pumps are about 805uSv/hr, backing lines for the turbos about a 1mSv/hr and the average field in the area of work down in the pit is about 600 to 750uSv/hr.
The proton beam went off at 10:45 on December 2nd, these measurements were done at 09:00 on December 3rd.
Entry  Wednesday, December 04, 2013, 10:44, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#41, module move 
TM#4 with Ta#41 has moved to the south hot cell, the move it self was uneventful but, the fields on the module are extremely high when lowering it down
into the south hot cell the module had a maximum field of about 392mSv/hr. The shield plug was also installed remotely as well due to the 12mSv/hr field
at the top of the west target station due to shine from the dump.