  2308   Thursday, February 24, 2022, 13:23 David WangITE/ITWMaintenance  Polyurethane water cooling lines replacement in ITE and ITW.

Polyurethane  water cooling lines in ITE and ITW  HV shroud are replaced.  Both stations Ta, Tu, MSP, HS, Coil , EE in HV shroud are new lines.

  2307   Thursday, February 17, 2022, 13:24 David WangSpent Target VaultMaintenance UCx #34Repackage of UCx #34in NHC.

UCX34# in pail 258(Vault lot 7C) has been repacked today. It is an investigation to find a possible leak source of radioactive Iodine in vault. The new pail number is 268. It is back to vault 7c . I wrote down the information in log book. The job is smooth today. I retrieved UCx 34 old pail and liner to TH. The liner from UCx#34 only has 3000 counts.  I bagged it. It could be used later. However, the pail has 500K counts contamination on bottom outside rim. It may accidently be slided out of plastic bag and touched the NHC table during the repackage. I bagged it and store it in silo area. When we do drum clean up, I will throw it in the drum.

  2306   Wednesday, February 16, 2022, 15:19 Frank SongCoolingRepair  high active cooling water valves repaired/replaced

 A 3/8 inch drain valve on return cooling line was replaced in ITE. In the meantime two 1/2 inch valves labeled FEBIAD COIL and ENTRANCE COLLIMATOR RETURN at ITW were replaced . The 2 inches leaky supply/return water valves in ITW were repaired as well. Pls check pics

attached here for detail.

Attachment 1: RETURN_drain_valve_in_ITE.jpg
RETURN_drain_valve_in_ITE.jpg
Attachment 2: FEBIAD_COIL_in_ITW.jpg
FEBIAD_COIL_in_ITW.jpg
Attachment 3: ENTRANCE_COLLIMATOR_RETURN_in_ITW.jpg
ENTRANCE_COLLIMATOR_RETURN_in_ITW.jpg
Attachment 4: MAIN_S_and_R_VALVES_in_ITW.jpg
MAIN_S_and_R_VALVES_in_ITW.jpg
  2305   Tuesday, February 15, 2022, 11:18 Frank SongCoolingRepair  Replace 2 leak valves on high active water system

 The valves #V10 & V11 beside high active water pumps were replaced in Target Hall, pics attached.

 

Attachment 1: v10_v11.jpg
v10_v11.jpg
Attachment 2: v10.jpg
v10.jpg
Attachment 3: v11.jpg
v11.jpg
  2304   Thursday, February 10, 2022, 12:42 David WangITEStandard Operation  ITE HV test woithout mdoule was done.

Carla did the test. That is what she wrote in Feb 04th:  "I am done with the HV testing at ITE - the results were the same as at ITW. It stayed at 59kV for 30 mins with no issues. Trying to go above 59.5kV is probably possible but a bit more risky. ITE also has a band, from 54-56kV, where the current jumps around like crazy".

  2303   Thursday, February 10, 2022, 12:24 David WangITWStandard Operation  ITW HV test without mdoule.

  Carla did the test. and reported the result as following: HV testing of ITW is complete. It was pretty well behaved up to 59.5kV, and sat at 59kV for 30mins with no sparks (that EPICS caught). There was some strange behaviour of the current between 51kV and 53kV - it was jumping by 20uA or more - but there didn't seem to be any voltage response, and it went away after 53kV (though it returned on the way back down). The test was done in Feb 02.

  2302   Thursday, February 10, 2022, 11:45 David WangSpent Target VaultStandard Operation UCx#33.Spent target UCx #33 has been repacked with a new pail and lid in NHC.

Spent target UCx #33 has been repacked with a new pail and lid in NHC. Old pail #255. New pail # 267. Location: Vault slot 1C.  it is an investigation job for  a possible leak pail in vault.  

  2301   Wednesday, February 02, 2022, 11:05 David WangCraneStandard Operation  Target hall overhand crane annual insepection.

Tom Kauss finished target hall overhead crane annual inspection today. The crane works fine. He issued new inspection tag and e-logged the job. 

  2300   Tuesday, January 25, 2022, 12:49 David WangITE/ITWStandard Operation  Target station vacuum system visual inspection.

Two shielding blocks  above vacuum station at TH west end were opened for inspection. Checked ITH:MP1, MP2 lubricant color and level through sight gauge on pumps. They are still ok.  Restored the shielding blocks.  Checked ITM:MP1 by decay tank (Mirror checked  sight gauge by north wall). Added lubricant to ITM:MP1 to middle level on sight gauge.  

  2299   Tuesday, January 25, 2022, 08:57 David WangITE/ITWStandard Operation  ITE/ITW have been cleaned with vacuum canister.

ITE/ITW  are cleaned with vacuum canister. HV  cage inside and blue nylon insulators are wiped.  Garbage inside the pits are cleaned out.

  2298   Monday, January 24, 2022, 11:18 David WangITE/ITWStandard Operation  TH emergency exit hatch functional check

TH emergency exit hatch which is located on TH west end roof is opened and closed for functional check. The hatch works fine. The limit switch on hatch is in position. No obstacle on hatch way to the roof. 

  2297   Thursday, January 20, 2022, 11:09 Travis CaveSpent Target VaultStandard Operation Ta#63Spent Target Move
The spent Ta#63 has been moved from the north hot cell to the spent target vault. It was place in pail#266 and 
placed in spot #3B of the vault. see attached PDF for more details.
Attachment 1: Target_Index_2022-01-20.pdf
Target_Index_2022-01-20.pdf
  2296   Thursday, January 20, 2022, 08:18 David WangNorth Hot-CellStandard OperationTM4No targetTM4 was removed from NHC to S_W silo yesterday.

TM4 was removed from NHC to S_W silo yesterday.  The remove is smooth and successful.

  2295   Wednesday, January 19, 2022, 13:36 David WangCraneStandard Operation  Targe hall crane below hook attachment pins and plates annual inspection.

Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01. He certified the use of these pins and plates. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08.  After inspection, The inspection tag  was issued and attached to pin. Tom has an inspection record on this job. See attachments.

Attachment 1: 2022-01-19_174.jpg
2022-01-19_174.jpg
Attachment 2: 2022-01-19_172.jpg
2022-01-19_172.jpg
  2294   Wednesday, January 19, 2022, 13:26 David WangCraneStandard Operation  Inpection of Target module lifting frames ITA0494-1997-01 and ITA0494-1997-02.

Tom Gauss inspected  two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02.. He certified the use of these two frames. Inspection tags have been issued and attached to frames. He has inspection record on them. See attachments.

Attachment 1: 2022-01-19_170.jpg
2022-01-19_170.jpg
Attachment 2: 2022-01-19_173.jpg
2022-01-19_173.jpg
Attachment 3: 2022-01-19_175.jpg
2022-01-19_175.jpg
Attachment 4: 2022-01-19_176.jpg
2022-01-19_176.jpg
  2293   Wednesday, January 19, 2022, 09:00 Frank SongNorth Hot-CellStandard OperationTM4Ta #63Electrical check on TM4 at NHC without target

 David did electrical check after target removed from TM4 at NHC. see attachment pls.

Attachment 1: 20220119_080049.jpg
20220119_080049.jpg
  2292   Tuesday, January 18, 2022, 11:02 Frank SongNorth Hot-CellStandard OperationTM4Ta #63TM4 SIS with Target and No external Connections

 David made an electric check after TM4 been moved to NHC from ITE. The target is still on the module. Please find out attached pic for detail.

Attachment 1: tm4_with_Ta#63_on_NHC.jpg
tm4_with_Ta#63_on_NHC.jpg
  2291   Monday, January 17, 2022, 10:44 Frank SongSouth Hot-CellStandard OperationTM2UC#36 (the target removed)TM2 electrical check without Target.

 An electric check was done right after module moving from SMP to SHC. 

Attachment 1: TM2_without_UCx36_at_SHC_(2).jpg
TM2_without_UCx36_at_SHC_(2).jpg
  2290   Wednesday, January 12, 2022, 14:09 Travis CaveSpent Target VaultStandard Operation UC#36Spent Target Move

 The spent UC#36 target in the north hot cell has been removed and placed in the spent target vault. See attached PDF for detail note that the PDF does not show that spot 2B is occupied by the 2A3M20 pail.

Attachment 1: Target_Index_2022-01-12.pdf
Target_Index_2022-01-12.pdf
  2289   Tuesday, January 11, 2022, 11:51 David WangNorth Hot-CellStandard OperationTM2 TM2 has been moved from NHC to SMP.

TM2( no target ) has been moved  from NHC to SMP.  The moving is smooth and successful.