Entry  Wednesday, July 05, 2017, 11:18, Anders Mjos, Conditioning Station, Maintenance, TM4, Ta#52, Changed electrical configuration to cathode bias 
 John Chow configured TCS to cathode bias mode (IRH1538). The anode P/S is in positive mode.
Entry  Monday, July 10, 2017, 10:19, David Wang, Conditioning Station, Standard Operation, TM4, , Turned off TCS water system 
Prepare for TM4 move tomorrow morning.
Entry  Tuesday, July 11, 2017, 10:20, Travis Cave, ITE, Standard Operation, TM4, Ta#52, Module move 
 TM#4 with Ta#52 has been moved from the conditioning station to the east target station.
Entry  Monday, August 28, 2017, 11:28, Travis Cave, ITE, Standard Operation, TM4, Ta#52, Module move 
 TM#4 with Ta#52 has been moved from the east station to the south hot cell.
Entry  Monday, August 28, 2017, 12:07, chad fisher, South Hot-Cell, Standard Operation, TM4, UCx#21, Ta#52 removed UCx#21 installed 
Ta#52 has been removed from TM$ and UCx#21 installed with new mounting and high current hardware. High current fasteners torqued to 130 in lbs.
Entry  Monday, August 28, 2017, 14:34, Travis Cave, Conditioning Station, Standard Operation, TM4, UC#21, Module move 
 TM#4 with UC#21 has been moved from the south hot cell to the conditioning station.
Entry  Monday, August 28, 2017, 14:40, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#21, Electrical Check TM4_UC21_elecchk_SHC.PDF
The results of the electrical check of TM#4 with UC#21 attached.
Entry  Tuesday, August 29, 2017, 08:59, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 HS line leak checks 
TM4 HS line leak checks are done, at SHC and TCS. SHC: Helium spray. TCS: Helium  pressurize 70psi.  LD base LR 0.0 X E-9 atm.cc/sec. 
No leak has been found on both leak checks. 
Entry  Tuesday, August 29, 2017, 09:01, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 has been connnected at TCS. 
TM4 has been connected at TCS. TCS water system has been started for TM4. TM4 and TCS vacuum pumping down is good so far.
Entry  Tuesday, September 05, 2017, 06:33, David Wang, Conditioning Station, Standard Operation, TM4, , Turned off TCS water system and vacuum system. 
Argon vent and disconnect TM4 at TCS.
Entry  Tuesday, September 05, 2017, 10:25, Travis Cave, ITE, Standard Operation, TM4, UC#21, Module move 
 TM#4 with UC#21 has been moved from the conditioning station to the east target station.
Entry  Tuesday, October 17, 2017, 10:56, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#21, Module move 
 TM#4 with UC#21 has been moved from the east target station to the south hot cell.
Entry  Wednesday, October 18, 2017, 10:45, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#37, Electrical Check TM4_SIC37_elec_chk_SHC.pdf
 The results of the electrical check of TM#4 with SiC#37, see attached PDF.
Entry  Wednesday, October 18, 2017, 10:46, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#37, Module move 
 TM#4 with SiC#37 has been moved from the south hot cell to the conditioning station.
Entry  Thursday, October 19, 2017, 10:11, David Wang, Conditioning Station, Standard Operation, TM4, , Leak check on TM4 HS line at SHC and TCS. 
Chad and I leak checked TM4 HS line after new target is installed yesterday. No leak has been found. Also, I helium pressurized the HS line at TCS this
morning. TM4 HS line is good on this test. The TM4 gas line configuration on TM4 top is leak check as well. No problem.
Entry  Thursday, October 19, 2017, 14:20, Anders Mjos, Conditioning Station, Standard Operation, TM4, SiC#37, SiC#37 Conditioning SiC#37_BIAS_current_vs_voltage.xlsxSiC#37.docx
Thursday, October 19, 2017, 14:20: EE configured for conditioning. HV cage locked up
Thursday, October 19, 2017, 16:46: BIAS / EL / EE at 45 / 22.5 / 0 kV
Thursday, October 19, 2017, 17:16: 30 min without sparking. Lowering to 0. Continue conditioning tomorrow.
Entry  Tuesday, October 24, 2017, 11:58, Travis Cave, ITE, Standard Operation, TM4, SiC#37, Module move 
 TM#4 with SiC#37 has been moved from the conditioning station to the east target station. A measurement was taken on TM#4 as it was being removed
from the conditioning station, the location was on the side of the service tray access panel approx one metre away and the cover fully exposed, the reading
was 750uSV/hr.
Entry  Thursday, October 26, 2017, 09:56, Anders Mjos, ITE, Repair, TM4, SiC#37, Leak on multi pin connector feedthrough 
On maintenance day Tuesday, the roughing of the target station could not go below 1.5 Torr. A brief troubleshooting on Tuesday was unsuccessful in determining
the cause. Leak checking continued on Wednesday by David and Anders. A leak was finally found on the multi pin connector feedthrough due to the seal between
the connector and flange on top of the nylon insulator. Upon re-tightening the connector, the leak could be stopped and the module pumped down to allow
Entry  Tuesday, January 02, 2018, 11:28, David Wang, ITE, Standard Operation, TM4, , ITE annual water interlock check. 
Eric and I finished ITE annual water interlock check. Everything works properly.
Entry  Tuesday, February 13, 2018, 13:54, Anders Mjos, ITE, Standard Operation, TM4, SiC#37, Target module disconnected 
TM disconnected by David and Yasmine Feb 8th