2600
|
Tuesday, May 28, 2024, 07:45 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx#45 | TCS was argon vented this morning between 6:00 and 7:30am. | TCS was argon vented this morning between
6:00 and 7:30am for TM4 moving to ITW. |
|
2603
|
Thursday, May 30, 2024, 11:08 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 was moved from silo to TCS yesterday morning. | TM2 was moved from silo to TCS yesterday
morning. The move is smooth.
TCS vacuum system was started after. TCS |
|
2605
|
Wednesday, June 05, 2024, 11:25 |
David Wang | Conditioning Station | Standard Operation | | | refilled TCS:TK2 to 27.4 inches. | refilled TCS:TK2 to 27.4 inches to compensate
water lost during THC filters change. |
|
2606
|
Wednesday, June 05, 2024, 11:32 |
David Wang | Conditioning Station | Standard Operation | | | TCS water system filters have been changed. | TCS water system five filters were
changed yesterday by plant group Dan.T. Service
labels on filters are updated. No water |
|
2608
|
Wednesday, June 12, 2024, 10:18 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 is moved from TCS to silo this morning | TM2 is moved from TCS to silo this morning.
The move is smooth. |
|
2609
|
Thursday, June 13, 2024, 11:44 |
David Wang | Conditioning Station | Repair | TM2 | | Replaced several o ring seals on TM2 service cap. | couple of E-8 to low E-7 atm.cc/sec
leak were found on TM2 service cap top air
to vacuum o rings. Replaced these |
|
2626
|
Wednesday, June 26, 2024, 13:49 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Tm2 has been moved from SW silo to TCS. | Tm2 has been successfully moved from SW
silo to TCS. |
|
2629
|
Wednesday, July 03, 2024, 14:01 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Tm2 has been moved from TCS to SW silo. | Tm2 has been moved from TCS to SW silo.
the move is smooth. |
|
2635
|
Monday, July 08, 2024, 10:40 |
David Wang | Conditioning Station | Standard Operation | TM4 | TiC#7 | TM4 has been moved from SHC to TCS. | TM4 has been moved from SHC to TCS. The
move is successfully. |
|
2665
|
Monday, August 19, 2024, 09:32 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#68 | TM4 has been moved from SHC to TCS. | TM4 has been moved from SHC to TCS. The
move is successful. |
|
2678
|
Wednesday, September 11, 2024, 07:59 |
David Wang | Conditioning Station | Standard Operation | TM4 | TiC#9 | TM4 has been moved from SHC to TCS. | TM4 has been moved from SHC to TCS. The
move is smooth. |
|
2694
|
Friday, September 27, 2024, 07:29 |
David Wang | Conditioning Station | Repair | | | TCS water system resistivity analyzer has been repaired. | TCS water system resistivity analyzer has
been repaired. Two diodes and one capacitor
on PS board were broken. They were replaced. |
|
2708
|
Thursday, October 24, 2024, 10:37 |
David Wang | Conditioning Station | Standard Operation | | | TCS water system functionnal test. | TCS water system has been started for functional
test. System parameters including pressure,
all temperature sensors, flow rate sensors, |
|
2722
|
Tuesday, November 26, 2024, 13:54 |
Adam Newsome | Conditioning Station | Standard Operation | TM3 | | TM3 move - SHC to TCS | TM3 was moved from SHC to TCS with UCx#47.
The move was smooth. |
|
2750
|
Thursday, January 16, 2025, 14:21 |
David Wang | Conditioning Station | Standard Operation | TM3 | No target | TM3 electrical check at TCS under good vacuum | A
complete TM3 electrical check at TCS under
good vacuum has been done. Pin 14 to 60KV |
 |
2755
|
Tuesday, January 28, 2025, 11:47 |
David Wang | Conditioning Station | Standard Operation | TM3 | No target | Tm3 has been moved from TCS to silo. | Tm3 has been moved from TCS to silo.
The move is successful. |
|
2770
|
Friday, February 14, 2025, 11:35 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 TP1/TP2 and TCS TP1S have been started at TCS. | TM2 TP1/TP2 and TCS:TP1S have been started
at TCS. The starting time and operation of
turbo pumps are ok. TM2 had been stored in |
|
2771
|
Tuesday, February 18, 2025, 10:41 |
David Wang | Conditioning Station | Standard Operation | TM3 | No target | TM2 at TCS annual electrical check and water lines helium pressure check . | TM2
has been moved to TCS and under good vacuum.
TP1/2 work fine. Electrical check: |
|
2774
|
Thursday, February 20, 2025, 11:10 |
David Wang | Conditioning Station | Standard Operation | TM2 | No target | TM2 has been moved from TCS to west-south silo. | TM2 has been moved from TCS to west-south
silo. Travis and I did the job. The move
is successful. |
|
2786
|
Thursday, March 20, 2025, 13:10 |
David Wang | Conditioning Station | Standard Operation | | | TCS water system filters annual replacement has been done. | TCS water system filters annual replacement
has been done. Plant group Dan Tower finished
the job and updated the inspection tags . |
|