  2171   Monday, December 07, 2020, 12:20 Adam NewsomeConditioning StationDevelopmentTM3 TM3 Move

TM3 has been moved from the South Hot Cell to the Conditioning Station. No containment box.

  2175   Monday, January 04, 2021, 12:13 Adam NewsomeConditioning StationDevelopmentTM3 TM3 Move

TM3 was remotely moved from the South Hot Cell to the conditioning station. No containment box.

  2184   Wednesday, February 03, 2021, 09:14 David WangConditioning StationStandard OperationTM4 TM4 from TCS to SW silo.

TM4 is moved from TCS to SW silo. The moving is smooth.

 

 

 

 

 

 

 

 

 

 

 

  2193   Tuesday, March 02, 2021, 08:12 David WangConditioning StationStandard Operation   TCS leak check.

TCS leak check: TCS IG1S1.6 XE- 6 torr. LD  0.0XE-9atm.cc/sec.We used a long pole to spray helium to TCS vacuum seals on diagnostic box and vessel body. Lots helium have been sprayed around the check area.  no leak has been found.

  2195   Thursday, March 04, 2021, 13:54 David WangConditioning StationStandard OperationTM3 TM3 has been moved to NHC from silo

TM3 has been moved from silo to NHC. The move is successful. NHC ram stand and NHC protection railings are checked and installed. Everything works fine.

2021-03-05. TM3 has been moved from NHC to silo. The move is successful.

  2204   Thursday, March 25, 2021, 08:55 Anders MjosConditioning StationMaintenance  Filters inspected and cleaned on water circuit

By Curtis. See Work Permit I2021-03-24-1 for details.

  2218   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  Chiller maintenance

A contractor on site today for chiller maintenance. CP2 and CP3 circuit is leaking and shall not be used. CP1 can still be used. The contractor will contact Plant Group with a quote for repair and upgrades.

  2219   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  TK2 refilled

Tank refilled from 12 in to 25 in using the new valve.

  2228   Friday, June 11, 2021, 10:36 David WangConditioning StationStandard OperationTM2UCX33#TM2 leak check at TCS

Leak checked TM2 service cap at TCS. helium pressure checked containment box window and HS cooling lines.  No leak on service cap and waterlines.

  2232   Thursday, July 08, 2021, 11:36 David WangConditioning StationStandard OperationTM4Ta#62Remotely remove TM4(Ta#62) from SHC to TCS.

Remotely remove TM4 (ta# 62) from SHC to TCS.  The moving is smooth.

  2276   Wednesday, November 24, 2021, 09:08 Adam NewsomeConditioning StationStandard OperationTM4 Remotely moved TM4 from SHC to TCS

TM4 was moved from the South Hot Cell to the Conditioning Station.

  2277   Thursday, November 25, 2021, 10:33 David WangConditioning StationStandard OperationTM4Ta#63. helium pressure test on TM4 HS line at TCS.

Helium pressure test on TM4 HS line at TCS is done.  LD base leak rate 0.0 xE-9 atm.cc/sec. Helium pressure 70psi. HS line had been helium pressurized for 5 minutes during the test. No response on LD. HS line with Ta#63 is leak free.

  2313   Monday, April 04, 2022, 21:04 Carla BabcockConditioning StationDevelopmentTM2 HV testing of IGLIS wires in TM2

TM2 is in the TCS without containment box for HV testing following the installation of the IGLIS wiring.

Not great results so far - sat at 42.5kV for nearly 2 hours, current around 200uA and occasional sparks. I did not have time to go higher, will do this tomorrow. The sparks could be conditioning but it looks a bit suspicious to me. We will see if the ramp up tomorrow is very easy and how high we can go. I have data from HV testing of TM2 in December for comparison.

The EZL was reacting to all sparks, so I went into the target hall to see if it was sparking on the module top, but there was no sparking there.

 

Possible mitigations:

  1. Re-do the connections on top of the service cap to remove the extra length on the wires inside the service cap and inspect the routing carefully to make sure nothing is in the wron place.
  2. Inspect the wiring in the source tray to see if there is evidence of sparking in a certain area.

 

Second round of testing Tuesday April 5 2022:

Much better results, seems most of the sparking was conditioning. Went right up to 42.5kV with no issues. Spent quite a while getting up to 50kV, and didn't leave it there for more than a couple mins. May be running into the limitations of the HV cage at this point. Bias current was much lower, something like 140uA at 45kV.

 

Third round of testing Wednesday April 6 2022:

Ramped easily back to 45kV, a little more sparking above that. Sat at 47kV for ~30mins with no sparks. Won't try to go higher in case of issues with the cage. Will try to condition up to 50kV in the station. Other than the possible low megger value between B and C, all looks good.

  2340   Thursday, June 23, 2022, 13:04 David WangConditioning StationStandard OperationTM4Ta#64helium pressure test on TM4 HS line.

With Ta#64 installed , TM4 HS line was helium pressure tested at TCS. base leak rate is 0.0XE-9 atm.cc/sec. HS line tested leak rate is 3x E-7 atm.cc/sec on 5 minutes 50 psi helium testing. Leak check result wasgood at NHC by helium spray method. We decided to apply water to HS and all other water lines still. The vacuum status is closely being watched. So far, TCS pumping down trend is still good. HS line supply water valve was switched on and off couple of times at TCS IG1 1.15 XE-6 range, and no vacuum spike was observed. More information will be logged in during the TM4 and target conditioning stage at TCS. 

  2356   Thursday, August 11, 2022, 09:10 David WangConditioning StationStandard OperationTM4SiC #44HS line helium pressure test. Gas line fitting on module top and gas line leak check.

HS line helium pressure test is done at TCS. No leak. I also leak checked gasline adapter and fittings on TM4 top. No leak.  1/4 copper gas line between module and ITE was leak checked yesterday. It is good.

  2364   Thursday, September 08, 2022, 09:06 David WangConditioning StationStandard OperationTM2UCx#39HS line helium pressure test.

TM2 with UCX#39 HS line helium pressure test is done at TCS. 70 psi helium 3minutes. No leak @0.0XE-9 atm.cc/sec.

  2374   Wednesday, October 05, 2022, 09:31 David WangConditioning StationStandard OperationTM4C#4HS line helium pressure test. TM4 with C#4 at TCS.

TM4 HS line helium pressure test is done. 70psi helium pressure@ 3XE-8 atm.cc/sec . No leak.

  2380   Wednesday, October 19, 2022, 12:04 Carla BabcockConditioning StationRepair  TCS:TBHT taken as replacement for ITE:TBHT

During the last ITE run with the SiC#44 target, the ITE:TBHT controls card was fried twice. The first time we put in our spare, and the second time we just continued to run without controls readback. For the C#4 run starting Oct. 19, we used the conditioning station supply. As soon as one of the other supplies is fixed, we will install it in the conditioning station. The equipment list (https://triumfoffice365-my.sharepoint.com/:x:/g/personal/cbabcock_triumf_ca/EQPffP4p1P9JqEDWIHGRPfsBVDSQjMCv-M8ZNg4ngkyGHw?e=fnLVYe) tracks these movements.

  2385   Thursday, November 03, 2022, 13:15 David WangConditioning StationStandard OperationTM2UCx#40HS line helium pressure test. TM4 with UCx#40at TCS.

Helium 70 psi. tested 5minutes at base leak rate 0.9 xE09 atm.cc/sec on HS line.  No leak.

  2393   Wednesday, November 23, 2022, 12:10 Adam NewsomeConditioning StationStandard OperationTM4UCx#41TM4 Move - NHC to TCS

TM4 was moved from the North Hot Cell to the Target Conditioning Station with UCx#41.