1701
|
Tuesday, April 17, 2018, 11:05 |
David Wang | ITW | Repair | | | Disconnect ITW entrance module | ITW entrance module has been disconnected.
All connections are labelled before or during
disconnection. The 24VDC electrical plug |
|
|
2192
|
Thursday, February 25, 2021, 10:09 |
Frank Song | ITE | Repair | | | Disconnect Entrance Module in ITE | David and I disconnected entrance
module in ITE by following the procedure
# 190510. And, the yoke was installed and |
|
|
787
|
Thursday, November 13, 2014, 14:05 |
David Wang | ITE | Repair | TM4 | | Dan and I replaced flow wheel on ITE HVC2 water flow sensor. | Dan and I replaced flow wheel on ITE HVC2
water flow sensor. The old wheel did rotate
smoothly inside its SST case. The new wheel |
|
|
582
|
Monday, January 20, 2014, 13:38 |
David Wang | ITE | Standard Operation | TM4 | | DISCONNECTED TM4 IN ITE. | I DISCONNECTED TM4 IN ITE. ALL WATER LINES
HAD BEEN PURGED OUT WITH PRESSURE AIR. |
|
|
2399
|
Friday, December 16, 2022, 16:39 |
Adam Newsome | Crane | Standard Operation | | | Crane powered off for holidays | [edit 2023-01-03] The crane was powered
back on this morning - there do not appear
to be any faults and it seems that the crane |
|
|
1668
|
Tuesday, December 19, 2017, 10:41 |
Anders Mjos | Crane | Maintenance | | | Crane powered down | The target hall crane has been powered
down by Don today in preparation for the
power shutdown over the Holidays. |
|
|
2188
|
Tuesday, February 16, 2021, 14:00 |
Adam Newsome | Crane | Development | | | Crane pendant upgrade | The crane pendant for the main hoist was
upgraded to a FLEX EX2 style pendant by Canco
Cranes. The installation work was performed |
|
|
1501
|
Monday, April 24, 2017, 16:06 |
David Wang | South Hot-Cell | Repair | TM2 | | Crane main hoist strane noise when lifting up TM2 | When lifting up TM2 (20000lbs) this
afternoon, TH crane has a strange noise on
main hoist. The module was lift up less than |
|
|
146
|
Friday, July 13, 2012, 16:33 |
Bevan Moss | Crane | Repair | | | Crane has stopped working | In the AM today David and I used the crane
to raise the ground plate sheet metal into
place. This afternoon when I attempted to |
|
|
147
|
Monday, July 16, 2012, 11:55 |
Bevan Moss | Crane | Repair | | | Crane has stopped working |
|
|
|
1476
|
Tuesday, April 04, 2017, 14:39 |
David Wang | Crane | Standard Operation | | | Crane check main hoist on jogging with shielding plug lifted. | Today, I checked TH crane main hoist
when shielding plug is installed into ITE
pit. I did some jogging actions on |
|
|
2173
|
Monday, December 21, 2020, 11:22 |
Adam Newsome | Crane | Standard Operation | | | Crane Shutdown for Power Outage | The Target Hall Crane has been shut down
in preparation for the power outage tomorrow
(Dec 22). Power will be restored on Dec 23. |
|
|
1667
|
Tuesday, December 19, 2017, 10:40 |
Don Jackson | Crane | Maintenance | | | Crane Power during winter break | The power to the crane and controls
were turned off using the power switch in
the Crane Control room. The main disconnect |
|
|
2272
|
Monday, November 22, 2021, 12:44 |
Adam Newsome | Crane | Repair | | | Crane PLC Fault: 0004h | An issue was observed in which the target
hall crane was not functioning: the N-E-S-W
and up/down motions did not work, however |
|
|
825
|
Monday, January 05, 2015, 12:47 |
Anders Mjos | Conditioning Station | Development | TM2 | | Cooling package started | by "enable staging" button.
MP3 has to be turned off-on to open WPV1 |
|
|
541
|
Tuesday, November 12, 2013, 14:33 |
Bevan Moss | Conditioning Station | Repair | | | Cooling manifold returned | The cooling manifold for the conditioning
station high power water cooled lines has
been returned. The cooling package can once |
|
|
363
|
Monday, May 27, 2013, 10:37 |
Bevan Moss | Conditioning Station | Maintenance | TM4 | | Cooling Systems topped off | Rob walker has flushed and refilled the
primary side of the system (note the water
still looks nasty). This morning the primary |
|
|
275
|
Monday, March 25, 2013, 09:35 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | CS Test Target #1 | Cooling Package and Vacuum Stopped | The cooling package and vacuum was
stopped today at 9:26 so the module can be
move. |
|
|
264
|
Thursday, March 14, 2013, 10:04 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | CS Test Target 1 | Cooling Package Started | The cooling package was started at
10:00 today. See attached picture. There
is another snap shot at 10:03. |
 |
|
266
|
Thursday, March 14, 2013, 11:56 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | CS Test Target 1 | Cooling Package Started |
|
|