1944
|
Thursday, June 20, 2019, 15:09 |
Isaac Earle | Safe Module Parking | Development | | | SMP motor wiring inspected by electrician | The AC wiring for the SMP motor was inspected
by Randy Boehm (TRIUMF electrician) as recommended
by Franco Mammarella (TRIUMF electrical engineer). |
|
|
1946
|
Thursday, July 04, 2019, 08:57 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum system installed | July 3:
- Assembled exhaust line flexible
hose and fittings as per ISK0529 Rev D then |
|
|
1955
|
Friday, July 26, 2019, 15:43 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum control system completed | The SMP vacuum control system has
been wired and setup to be controlled from
EPICS. Backing valve control (SMP:BV1) |
|
|
1970
|
Friday, August 23, 2019, 14:27 |
Isaac Earle | Safe Module Parking | Development | | | SMP camera video cabling installed and tested | Installation of the video lines for
the SMP cameras was completed yesterday according
to IRH1670 Rev B. All four cameras |
|
|
1971
|
Tuesday, August 27, 2019, 13:12 |
Adam Newsome | Safe Module Parking | Development | | | SMP Remote Control Wiring Inspection | The wiring for the SMP remote control module
was inspected by Joel Semilla (TRIUMF electrician).
The module was plugged in to verify there |
|
|
1983
|
Tuesday, September 10, 2019, 14:04 |
David Wang | ITW | Standard Operation | | | ITW water interlock check. | ITW water interlock check is finished.
Everything is good. |
|
|
1987
|
Wednesday, September 18, 2019, 14:28 |
Travis Cave | Spent Target Vault | Standard Operation | | | Repacking of the targets. | Three of the five targets in the
mini storage have been repackaged into the
stronger pail. |
|
|
1988
|
Thursday, September 19, 2019, 10:11 |
Travis Cave | Spent Target Vault | Standard Operation | | | Repacking of the targets. | Another target in the mini storage
has been repackaged into the new pails. With
one remaining to do which will be done on |
|
|
1989
|
Monday, September 23, 2019, 13:21 |
Travis Cave | Spent Target Vault | Standard Operation | | | Repacking of the targets. | All targets in the mini vault have
been repackaged and are now ready to be loaded
into F-308s. All the target pails have new |
|
|
1990
|
Monday, September 30, 2019, 11:27 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum vessel modifications completed | The SMP vacuum vessel welds were reinforced
to match the specifications on IRH1710 Rev
D. In addition a tube stub was added |
|
|
1997
|
Wednesday, October 02, 2019, 08:25 |
chad fisher | South Hot-Cell | Standard Operation | | ZrC#8 | ZrC#8 PIE | Heat shield has been removed from ZrC#8. |
|
|
1998
|
Thursday, October 03, 2019, 10:25 |
Travis Cave | Spent Target Vault | Standard Operation | | ZrC#8 | Spent Target Move | The spent ZrC#8 was moved from the
south hot cell to the spent target vault.
It was placed in pail 217 and the pail was |
|
|
2005
|
Wednesday, October 09, 2019, 13:28 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#27 | Spent Target Move | The spent target in the south hot
cell has been moved to the spent target vault.
It was placed in spot 1B of the vault in |
|
|
2006
|
Thursday, October 10, 2019, 16:17 |
Adam Newsome | Safe Module Parking | Development | | | SMP Main Panel: Relay Addition for E-Stop Circut | An update was made for the E-stop and power
supply system in the SMP main panel. Upon
testing remote control, it was determined |
|
|
2007
|
Tuesday, October 15, 2019, 16:42 |
Isaac Earle | Safe Module Parking | Development | | | SMP flange alignment tested using shield plug | As a preliminary test in preparation
for SMP commissioning, one of the steel module
shield plugs was installed into the SMP to |
|
|
2008
|
Thursday, October 17, 2019, 11:49 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#31,32 and UC#19,20,21 | Loading F-308 | The targets in the mini storage have
been loaded into the F-308. |
|
|
2010
|
Tuesday, October 22, 2019, 16:26 |
Isaac Earle | Safe Module Parking | Development | | | SMP shield box grounding | A braided grounding strap was attached
to the aluminum gear box support on the SMP
shield box structure, and grounded by attaching |
|
|
2015
|
Monday, October 28, 2019, 11:50 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#28 | Spent Target Move | UC#28 has been moved from the south
hot cell to spent target storage. The target
was placed in pail number 219 and placed |
|
|
2016
|
Monday, October 28, 2019, 12:00 |
Isaac Earle | Safe Module Parking | Development | | | SMP shielding attenuation measured & compared to theoretical values | The attenuation of the SMP shielding was
measured as part of SMP commissioning (Document-170404,
R1, Section 4, Test #8) |
|
|
2017
|
Tuesday, October 29, 2019, 10:00 |
Adam Newsome | Safe Module Parking | Development | | | SMP Updates to E-stop circuit and feedback signals | The SMP main control panel and remote control
module were updated in order to implement
the following items which were deemed desirable |
|