Entry  Thursday, August 11, 2016, 10:37, David Wang, Conditioning Station, Repair, TM3, , TM3 service tray cover plate ITA2108 has been removed. 
Requested by Aurelia, and approved by Friedhelm, TM3 service tray cover plate ITA2108 has been remove out of the module. The plated is checked for active
and contamination after removal. Then,It is double bagged, sealed ,  tagged, and placed downstairs in TH between south wall and green block . The
ram contact reading on the plate is about 10 usv/hr.  We will do anther TM3 HV test at TCS without this cover plate.
Entry  Friday, August 12, 2016, 10:59, Anders Mjos, Conditioning Station, Development, TM3, , HV Test with Service Chase Panel removed TM3_HV_conditioning_2016-08-12.docxTCS-2016-08-11_TM3_Service_Chase_Panel_Removed.rga
Water cooling is performed manually with CP1. RGA is ON since yesterday. EE is not connected and in conditioning mode.

Friday, August 12, 2016, 10:43: BIAS at 10 kV, EL at 0.5 kV. IG1 at 1.8E-6 T
 Friday, August 12, 2016, 11:04: BIAS at 20 kV
Entry  Monday, August 15, 2016, 10:15, David Wang, Conditioning Station, Standard Operation, TM4, , Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp
Weekly update target hall schedule. Everything on schedule are finished  on time.   See attachment.  
Entry  Tuesday, August 16, 2016, 12:35, David Wang, Conditioning Station, Repair, TM3, , CS vacuum pumps have been stopped 
The TCS is venting now. The TM3 blue insulator replacement job will be started soon.
    Reply  Thursday, August 18, 2016, 10:35, Anders Mjos, Conditioning Station, Repair, , , VFD21 OL1 fault on Chiller 


    
        
            Anders Mjos wrote:
        
        
            
            
            
Entry  Thursday, August 18, 2016, 14:19, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 is now back in the the north east silo.
Entry  Wednesday, August 24, 2016, 10:45, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum system has been connected at TCS 
Start of roughing now.
Entry  Wednesday, August 24, 2016, 14:42, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#49, Conditioning TCS-2016-08-24_Ta#49.rgaTa#49.docx
Wednesday, August 24, 2016, 14:42: RGA on
Wednesday, August 24, 2016, 20:27: IG2 and IG1S on. Checked on water system.

Conditioning by ISAC operations. Water flow tripped power supplies after a few hours of conditioning at 580 / 230 A and 30 kV. See operations
Entry  Thursday, August 25, 2016, 08:36, David Wang, Conditioning Station, Standard Operation, TM2, , Helium pressure test on TM2 HS water lline  
I did a helium pressure test on TM2 HS water line at TCS. Leak detector base leak rate only could get to 1.8x e-8 atm.cc/sec at this moment. Applied
5 minutes 70psi helium on it. No leak has been found at this level. I connected water to this circuit after the test for weekend TM2 conditioning at TCS.
I will do another helium pressure test after the conditioning. The LD base leak rate should be 0.0Xe-9 atm.cc/sec at that time.
Entry  Thursday, August 25, 2016, 08:43, David Wang, Conditioning Station, Standard Operation, TM2, , All TM2 connections to TCS are done. 
The HV cover is installed. The Faraday cage at B2 level is locked also.The TCS and TM2 are still pumping down. Everything is good so far.
Entry  Thursday, August 25, 2016, 13:59, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 130 (Apr- Sep, 2016) Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp
Weekly update schedule.  See attachment 1,2.
Entry  Monday, August 29, 2016, 13:34, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been disconnected at TCS 
I stopped TCS water pumps and vacuum pumps also.   TM2 and TCS will be vented tomorrow morning.
Entry  Wednesday, September 07, 2016, 11:44, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 has been moved from the NE Silo to the conditioning station.
Entry  Thursday, September 08, 2016, 16:28, David Wang, Conditioning Station, Repair, TM3, , TM3 blue insulators have been replaced. 
All TM3 blue insulators except Gas,EL, and 60 KV common  on top of the module have been replaced with new designed insulators. The new blue insulator
for gas line need to be modified to fit for the bent on the gas  line.   EL, and 60KV common blue insulators were replaced during last time
TM3 refurbishment so they are relative new, and  not replaced this time. All seals related to the blue insulators are changed to new seals. The o-
Entry  Thursday, September 08, 2016, 16:30, David Wang, Conditioning Station, Repair, TM3, , TM3 vacuum system have been connected at TCS. 
start of roughing now.
 start of TCS and TM3 turbo-pumps. Everything is good so far.
Entry  Monday, September 12, 2016, 09:25, David Wang, Conditioning Station, Repair, TM3, , TM3 leak checked at TCS 
After blue insulators replacement, TM3 service cap are leak checked. LD base leak rate 0.0xe-9 atm.cc/sec. I sprayed lots helium on all blue insulator
seals. No leak has been found. Double checked them again, and got same result. All other seals on top of TM3 also have been checked. They are leak free.
OVEN, TUBE, MSP, COIL, and EE water lines are pressurized with 70 psi helium for 3minutes each. They are good also.
Entry  Tuesday, September 13, 2016, 13:52, Anders Mjos, Conditioning Station, Standard Operation, TM3, , HV Test with new insulators on Service Cap (vacuum to air) TM3_HV_conditioning_2016-09-13.docxTCS-2016-09-11_TM3_New_Blue_Insulators.rga
Tuesday, September 12, 2016, 10:00: RGA on

Tuesday, September 13, 2016, 13:52: Source on
Tuesday, September 13, 2016, 13:55: BIAS / EL at 10 / 5 kV
Entry  Wednesday, September 14, 2016, 11:54, David Wang, Conditioning Station, Repair, TM3, , TM3 is disconnected at TCS. 
 TM3 is disconnected at TCS and ready to be moved to silo.
Entry  Wednesday, September 14, 2016, 13:53, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, Module move 
TM#3, no target, has been moved from the conditioning station to the north east silo.
Entry  Monday, September 19, 2016, 08:28, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 131(Sep-Dec, 2016) Target_Hall_shedule_131__Sep_to_Dec_2016.pdfTarget_Hall_shedule_131__Sep_to_Dec_2016.xlsxTarget_Hall_shedule_131_Sep_to_Dec.mppTarget_Hall_shedule_131_Sep_to_Dec.pdf
Post new  target hall Excel sheet schedule for beam schedule 131. See attachment 1,2
Post new target hall  MS project schedule for beam schedule131. See attachment 3,4