ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1294   Friday, July 29, 2016, 14:27 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Measurements & Cleanup The North
Hot Cell was accessed today via the Ante
  
  1300   Wednesday, August 03, 2016, 09:15 chad fisherSouth Hot-CellRepair  ManipulatorEast manipulator on the south hot cell
is showing signs of eminent wrist/tong cable
failure. Some slight slippage was noted yesterday
  
  1303   Wednesday, August 03, 2016, 09:56 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update schedule weekly. See attachments
1,2
 Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1305   Thursday, August 04, 2016, 08:56 Travis CaveSpent Target VaultStandard Operation UC#16Spent Target moveThe spent UC #16 have been moved from the
south hot cell to the storage vault see attached
PDF for details.
 Vault_Storage_August_3_2016.pdf 
  1306   Friday, August 05, 2016, 13:50 chad fisherSouth Hot-CellMaintenance  Anteroom clean outSome items have been removed from the anteroom
in preparation for painting. Items have been
placed on plastic in the south hot cell service
  
  1307   Friday, August 05, 2016, 14:13 Isaac EarleNorth Hot-CellDevelopment  Preparations for NHC Ventilation TestA hole was drilled in the NHC exhaust duct
in the east end of the target hall above
the hatch to the Ante Room.  This will
  
  1308   Monday, August 08, 2016, 11:24 chad fisherSouth Hot-CellMaintenance  Anteroom Clean-up - WaveguideThe wave guide from TM3 has been surveyed,
swiped and removed from the anteroom and
transported to rad waste for disposal. The
  
  1311   Tuesday, August 09, 2016, 11:36 Anders MjosConditioning StationMaintenance  RGA and CG1S moved The locations (ports) for the RGA
and CG1S was swapped today by Anders and
Isaac to provide clearance for the North
 Old.JPGNew.JPG 
  1314   Wednesday, August 10, 2016, 12:18 chad fisherSouth Hot-CellMaintenance  Anteroom clearingBlack "radio active" materials
cabinet has been emptied, items bagged and
removed from the anteroom. Cabinet itself
  
  1315   Wednesday, August 10, 2016, 14:38 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Ventilation Test ResultsTesting was performed on August 9th on
the ISAC nuclear ventilation system to determine
if the existing ventilation system can achieve
  
  1317   Friday, August 12, 2016, 09:58 chad fisherSouth Hot-CellMaintenance  Manipulator MaitenanceDisassembled the master side of the right
manipulator this morning to check the wrist
cable. The cable on the master side shows
  
  1321   Tuesday, August 16, 2016, 11:27 chad fisherSouth Hot-CellMaintenance  South Cell Field ReadingsField readings have been taken at the south
hot cell in preparation for entry into the
cell to fix manipulator.
  
  1323   Thursday, August 18, 2016, 10:35 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

    

       
            
  
  1324   Thursday, August 18, 2016, 13:57 chad fisherSouth Hot-CellMaintenance  Manipulator maitenanceSouth hot cell was entered to check to
replace cable if needed. Wrist cable showed
no signs of fraying or broken strands.
  
  1326   Tuesday, August 23, 2016, 08:05 chad fisherSouth Hot-CellMaintenance  Post Hot Cell Entry Clean-upPlastic has been removed from the floor
and any known active items in the hot cell
moved to the south east corner in an attempt
  
  1330   Wednesday, August 24, 2016, 09:19 chad fisherSouth Hot-CellMaintenance  Anteroom Clean -up paint prepRemaining items from anteroom have been
bagged and removed (save the boot boxes,
1 garbage can and 1 coverall garbage can).
  
  1335   Wednesday, August 24, 2016, 14:37 Anders MjosSouth Hot-CellStandard Operation SiC#33PIE The target was inspected by Anders
and Chad. The target was in good condition
as can be seen on the photos on DocuShare.
  
  1339   Thursday, August 25, 2016, 13:59 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep, 2016)Weekly update schedule.  See attachment
1,2.
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1340   Thursday, August 25, 2016, 14:25 Travis CaveSpent Target VaultStandard Operation SiC#33Spent Target moveSiC#33 was placed into pail #141 which
in turn was placed into slot 2B of the vault.
I was 295mS/hr upon removal from the south
 Vault_Storage_August_25_2016.pdf 
  1345   Wednesday, September 07, 2016, 11:39 Isaac EarleNorth Hot-CellDevelopment  NHC North / South Wall Gap Measurements Measurements were taken today of
the NHC north/south wall gap at the location
where the NHC/TCS partition wall will be
  