1294
|
Friday, July 29, 2016, 14:27 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Measurements & Cleanup | The North
Hot Cell was accessed today via the Ante |
|
1300
|
Wednesday, August 03, 2016, 09:15 |
chad fisher | South Hot-Cell | Repair | | | Manipulator | East manipulator on the south hot cell
is showing signs of eminent wrist/tong cable
failure. Some slight slippage was noted yesterday |
|
1303
|
Wednesday, August 03, 2016, 09:56 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) | Update schedule weekly. See attachments
1,2 |
 |
1305
|
Thursday, August 04, 2016, 08:56 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#16 | Spent Target move | The spent UC #16 have been moved from the
south hot cell to the storage vault see attached
PDF for details. |
|
1306
|
Friday, August 05, 2016, 13:50 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom clean out | Some items have been removed from the anteroom
in preparation for painting. Items have been
placed on plastic in the south hot cell service |
|
1307
|
Friday, August 05, 2016, 14:13 |
Isaac Earle | North Hot-Cell | Development | | | Preparations for NHC Ventilation Test | A hole was drilled in the NHC exhaust duct
in the east end of the target hall above
the hatch to the Ante Room. This will |
|
1308
|
Monday, August 08, 2016, 11:24 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom Clean-up - Waveguide | The wave guide from TM3 has been surveyed,
swiped and removed from the anteroom and
transported to rad waste for disposal. The |
|
1311
|
Tuesday, August 09, 2016, 11:36 |
Anders Mjos | Conditioning Station | Maintenance | | | RGA and CG1S moved | The locations (ports) for the RGA
and CG1S was swapped today by Anders and
Isaac to provide clearance for the North |
 |
1314
|
Wednesday, August 10, 2016, 12:18 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom clearing | Black "radio active" materials
cabinet has been emptied, items bagged and
removed from the anteroom. Cabinet itself |
|
1315
|
Wednesday, August 10, 2016, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Ventilation Test Results | Testing was performed on August 9th on
the ISAC nuclear ventilation system to determine
if the existing ventilation system can achieve |
|
1317
|
Friday, August 12, 2016, 09:58 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator Maitenance | Disassembled the master side of the right
manipulator this morning to check the wrist
cable. The cable on the master side shows |
|
1321
|
Tuesday, August 16, 2016, 11:27 |
chad fisher | South Hot-Cell | Maintenance | | | South Cell Field Readings | Field readings have been taken at the south
hot cell in preparation for entry into the
cell to fix manipulator. |
|
1323
|
Thursday, August 18, 2016, 10:35 |
Anders Mjos | Conditioning Station | Repair | | | VFD21 OL1 fault on Chiller |
|
|
1324
|
Thursday, August 18, 2016, 13:57 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator maitenance | South hot cell was entered to check to
replace cable if needed. Wrist cable showed
no signs of fraying or broken strands. |
|
1326
|
Tuesday, August 23, 2016, 08:05 |
chad fisher | South Hot-Cell | Maintenance | | | Post Hot Cell Entry Clean-up | Plastic has been removed from the floor
and any known active items in the hot cell
moved to the south east corner in an attempt |
|
1330
|
Wednesday, August 24, 2016, 09:19 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom Clean -up paint prep | Remaining items from anteroom have been
bagged and removed (save the boot boxes,
1 garbage can and 1 coverall garbage can). |
|
1335
|
Wednesday, August 24, 2016, 14:37 |
Anders Mjos | South Hot-Cell | Standard Operation | | SiC#33 | PIE | The target was inspected by Anders
and Chad. The target was in good condition
as can be seen on the photos on DocuShare. |
|
1339
|
Thursday, August 25, 2016, 13:59 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep, 2016) | Weekly update schedule. See attachment
1,2. |
 |
1340
|
Thursday, August 25, 2016, 14:25 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#33 | Spent Target move | SiC#33 was placed into pail #141 which
in turn was placed into slot 2B of the vault.
I was 295mS/hr upon removal from the south |
|
1345
|
Wednesday, September 07, 2016, 11:39 |
Isaac Earle | North Hot-Cell | Development | | | NHC North / South Wall Gap Measurements | Measurements were taken today of
the NHC north/south wall gap at the location
where the NHC/TCS partition wall will be |
|