Entry  Tuesday, January 11, 2022, 11:51, David Wang, North Hot-Cell, Standard Operation, TM2, , TM2 has been moved from NHC to SMP. 
TM2( no target ) has been moved  from NHC to SMP.  The moving is smooth and successful. 
Entry  Wednesday, January 19, 2022, 13:26, David Wang, Crane, Standard Operation, , , Inpection of Target module lifting frames ITA0494-1997-01 and ITA0494-1997-02.  2022-01-19_170.jpg2022-01-19_173.jpg2022-01-19_175.jpg2022-01-19_176.jpg
Tom Gauss inspected  two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02.. He certified the use of these two frames. Inspection
tags have been issued and attached to frames. He has inspection record on them. See attachments.
Entry  Wednesday, January 19, 2022, 13:36, David Wang, Crane, Standard Operation, , , Targe hall crane below hook attachment pins and plates annual inspection.  2022-01-19_174.jpg2022-01-19_172.jpg
Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01. He certified the use of these pins and plates. The inspection
of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08.  After inspection,
The inspection tag  was issued and attached to pin. Tom has an inspection record on this job. See attachments.
Entry  Thursday, January 20, 2022, 08:18, David Wang, North Hot-Cell, Standard Operation, TM4, No target, TM4 was removed from NHC to S_W silo yesterday.  
TM4 was removed from NHC to S_W silo yesterday.  The remove is smooth and successful. 
Entry  Monday, January 24, 2022, 11:18, David Wang, ITE/ITW, Standard Operation, , , TH emergency exit hatch functional check 
TH emergency exit hatch which is located on TH west end roof is opened and closed for functional check. The hatch works fine. The limit switch on hatch
is in position. No obstacle on hatch way to the roof.  
Entry  Tuesday, January 25, 2022, 08:57, David Wang, ITE/ITW, Standard Operation, , , ITE/ITW have been cleaned with vacuum canister.  
ITE/ITW  are cleaned with vacuum canister. HV  cage inside and blue nylon insulators are wiped.  Garbage inside the pits are cleaned out.
Entry  Tuesday, January 25, 2022, 12:49, David Wang, ITE/ITW, Standard Operation, , , Target station vacuum system visual inspection.  
Two shielding blocks  above vacuum station at TH west end were opened for inspection. Checked ITH:MP1, MP2 lubricant color and level through sight
gauge on pumps. They are still ok.  Restored the shielding blocks.  Checked ITM:MP1 by decay tank (Mirror checked  sight gauge by north
wall). Added lubricant to ITM:MP1 to middle level on sight gauge.   
Entry  Wednesday, February 02, 2022, 11:05, David Wang, Crane, Standard Operation, , , Target hall overhand crane annual insepection.  
Tom Kauss finished target hall overhead crane annual inspection today. The crane works fine. He issued new inspection tag and e-logged the job. 
Entry  Thursday, February 10, 2022, 11:45, David Wang, Spent Target Vault, Standard Operation, , UCx#33., Spent target UCx #33 has been repacked with a new pail and lid in NHC.  
Spent target UCx #33 has been repacked with a new pail and lid in NHC. Old pail #255. New pail # 267. Location: Vault slot 1C.  it is an investigation
job for  a possible leak pail in vault.   
Entry  Thursday, February 10, 2022, 12:24, David Wang, ITW, Standard Operation, , , ITW HV test without mdoule.  
  Carla did the test. and reported the result as following: HV testing of ITW is complete. It was pretty well behaved up to 59.5kV,  and sat at
59kV for 30mins with no sparks (that EPICS caught). There was  some strange behaviour of the current between 51kV and 53kV - it was  jumping by 20uA or
more - but there didn't seem to be any voltage response, and it went away after 53kV (though it  returned on the way back down). The test was done in Feb
Entry  Thursday, February 10, 2022, 12:42, David Wang, ITE, Standard Operation, , , ITE HV test woithout mdoule was done. 
Carla did the test. That is what she wrote in Feb 04th:  "I am done with the HV testing  at ITE - the
results were the same as at ITW. It stayed at 59kV for 30  mins with no issues. Trying to go above 59.5kV is probably possible but a  bit more risky. ITE
also has a band, from 54-56kV, where the current jumps around like crazy". 
Entry  Thursday, February 17, 2022, 13:24, David Wang, Spent Target Vault, Maintenance, , UCx #34, Repackage of UCx #34in NHC. 
UCX34# in pail 258(Vault lot 7C) has been repacked today. It is an investigation to find a possible leak source of radioactive Iodine in vault. The new
pail  number is 268. It is back to vault 7c . I wrote down the information in  log book. The job is smooth today. I retrieved UCx 34 old pail and liner
 to TH. The liner from UCx#34 only has 3000 counts.  I bagged it. It  could be used later. However, the pail has 500K counts contamination on  bottom
Entry  Thursday, February 24, 2022, 13:23, David Wang, ITE/ITW, Maintenance, , , Polyurethane water cooling lines replacement in ITE and ITW.  
Polyurethane  water cooling lines in ITE and ITW  HV shroud are replaced.  Both stations Ta, Tu, MSP, HS, Coil , EE in HV shroud are new
lines. 
Entry  Tuesday, March 01, 2022, 11:51, David Wang, Spent Target Vault, Maintenance, , , UCx #32 has been repacked in NHC.  
UCx 32# P2N target in vault slot 1B is repacked is morning for Ferran to  take out his samples( in two small plastic containers) stored in pail  last
July when Chad did the spent target job. The job went well.  Old  pail # is 254# and new pail # is 233. It is put back to 1B in vault.
Entry  Wednesday, March 02, 2022, 10:51, David Wang, ITE/ITW, Standard Operation, , , Replaced old turbopump and 2A3M20 wire scanner are transferred to cyclotron tunnel.  
Replaced 9 old turbo pumps from ITE/ ITW and  one 2A3M20 wire scanner from ITE are transferred to cyclotron tunnel for storage. It is TH RAD waste
cleanup task in winter shut down. 
Entry  Thursday, April 28, 2022, 08:16, David Wang, ITW, Standard Operation, TM2, , Annual ITW water signal interlocks check . 
Annual ITW water signal interlocks check was done with TM2 in ITW.   Water signal interlocks on all water circuits related to TM and 2A beam
lines in ITW work fine.  
Entry  Wednesday, May 25, 2022, 13:23, David Wang, ITE, Standard Operation, TM4, , Annual ITE water signal interlocks. 
Annual ITE water signal interlocks check is done with Rob Shank. All ITE water signal  interlocks work fine. 
Entry  Wednesday, June 22, 2022, 09:03, David Wang, ITE, Standard Operation, TM4, UCX37# P2N, Remotely removed TM2 from ITE to NHC 
TM2 with UCx#37 P2N target  was removed from ITE to NHC yesterday morning. The move is good. 
Entry  Wednesday, June 22, 2022, 09:14, David Wang, South Hot-Cell, Standard Operation, TM2, SiC#42 and SiC#43. , Three of TM2 moves related to SiC#42 to SiC #43 target switching job.  
Monday morning June 20th: TM2 with SiC # 42 was moved from ITW to NHC.
Monday afternoon: TM2 with no target was moved from NHC to SHC due to 10 pin connector guide pin loose issue. The guide pin has to be moved out
in SHC due to NHC manipulator configuration limit .
Entry  Thursday, June 23, 2022, 13:04, David Wang, Conditioning Station, Standard Operation, TM4, Ta#64, helium pressure test on TM4 HS line.  
With Ta#64 installed , TM4 HS line was helium pressure tested at TCS. base leak rate is 0.0XE-9 atm.cc/sec. HS line tested leak rate is 3x E-7 atm.cc/sec
on 5 minutes 50 psi helium testing. Leak check result wasgood at NHC by helium spray method. We decided to apply water to HS and all other water lines
still. The vacuum status is closely being watched. So far, TCS pumping down trend is still good. HS line supply water valve was switched on and off couple