ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  1268   Monday, June 27, 2016, 13:45 David WangITEStandard Operation  5 Shielding blocks have been transferred from ITW to ITE.ITE is configured to take proton beam.   
  1270   Thursday, June 30, 2016, 13:33 Dan McDonaldSpent Target VaultMaintenance  F308'sThe five spent target F308  flasks
where gone through in accordance with Nordion
guidelines, the sixth spare is remains in
  
  1271   Wednesday, July 06, 2016, 07:03 David WangITWStandard OperationTM2 TM2 was connected in ITW.TM2 was disconnected in ITW and moved to
SHC.
  
  1272   Wednesday, July 06, 2016, 07:06 David WangConditioning StationStandard Operation  venting TCS with argon.I switched off the vacuum pumps and vented
TCS with argon. The TCS will be ready to
accept TM2 this afternoon.
  
  1276   Wednesday, July 06, 2016, 14:25 David WangConditioning StationStandard OperationTM2 TCS and TM2 turbo-pumps have been started.The TCS and TM2 are pumping down.   
  1278   Friday, July 08, 2016, 08:20 David WangConditioning StationStandard OperationTM2 TM2 has been connected at TCSI connected TM2 to TCS and started water
system.
  
  1279   Friday, July 08, 2016, 16:56 Anders MjosConditioning StationRepair  VFD21 OL1 fault on ChillerPlant Services group (Tony) will contact
a service tech on Monday.
Water system will be switched off
  
  1282   Tuesday, July 12, 2016, 12:40 David WangITWStandard OperationTM2 TM2 has been connected in ITWAll turbo-pumps are started. Everything
is good so far.
  
  1283   Tuesday, July 12, 2016, 12:42 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Update schedule weekly.Attachment 1,2  Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1285   Thursday, July 14, 2016, 10:54 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update TH schedule 130 according to mini-shut
down change.See attachment 1,2,3,4
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep_2016.pdfTarget_Hall_shedule_129_Sep_to_Dec.xlsx 
  1286   Thursday, July 14, 2016, 13:25 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

    

       
            
  
  1288   Monday, July 18, 2016, 14:14 David WangConditioning StationRepairTM3 TM3 leak checked at TCSLast Friday July-15, TM3 was leak checked
at TCS. All air to vacuum seals on service
cap are good.  Helium pressure test
  
  1289   Tuesday, July 19, 2016, 14:35 Aurelia LaxdalConditioning StationRepairTM3 TM3 leak checked at TCS

    

       
            
  
  1290   Friday, July 22, 2016, 10:57 David WangConditioning StationRepairTM3 TM3 has been moved and connected at TCSI started vacuum system.
I started TCS water system. The chiller
does not work properly still. But, It will
  
  1291   Monday, July 25, 2016, 08:15 Anders MjosConditioning StationRepairTM3 HV Test Monday, July 25, 2016, 08:14: Enabled
staging for chiller
Monday, July 25, 2016, 08:33: Disabled
 TM3_HV_conditioning_2016-07-25.docxTCS-2016-07-25_TM3_no_target.rgaTCS-2016-07-26_TM3_no_target.rga 
  1292   Tuesday, July 26, 2016, 11:22 chad fisherSouth Hot-CellMaintenance  Soth Hot Cell Waste Storage Vault TunnelThe two 45 gal (m) drums of waste removed
from the south hot cell in December 2015
and January 2016 were transferred from the
  
  1294   Friday, July 29, 2016, 14:27 Isaac EarleNorth Hot-CellDevelopment  North Hot Cell Measurements & Cleanup The North
Hot Cell was accessed today via the Ante
  
  1300   Wednesday, August 03, 2016, 09:15 chad fisherSouth Hot-CellRepair  ManipulatorEast manipulator on the south hot cell
is showing signs of eminent wrist/tong cable
failure. Some slight slippage was noted yesterday
  
  1302   Wednesday, August 03, 2016, 09:49 David WangConditioning StationStandard OperationTM4 TM4 is ready for conditioing at TCS.I started TCS water system and installed
HV cover onto TM4.  The TM4 containment
box is supplied with water also. TM4 is ready
  
  1303   Wednesday, August 03, 2016, 09:56 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update schedule weekly. See attachments
1,2
 Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 