Thursday, July 14, 2016, 13:25, Anders Mjos, Conditioning Station, Repair, , , VFD21 OL1 fault on Chiller
|
Anders Mjos wrote:
Plant Services group (Tony) will contact a service tech on Monday. |
Monday, July 18, 2016, 14:14, David Wang, Conditioning Station, Repair, TM3, , TM3 leak checked at TCS
|
Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good. Helium pressure test on TM3 water lines(except
GE, HS, and Window) were done. Leak detector has no response at 0.0xE-9 atm.cc/sec. They are leak free. |
Tuesday, July 19, 2016, 14:35, Aurelia Laxdal, Conditioning Station, Repair, TM3, , TM3 leak checked at TCS
|
David Wang wrote:
Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good. Helium pressure |
Friday, July 22, 2016, 10:57, David Wang, Conditioning Station, Repair, TM3, , TM3 has been moved and connected at TCS
|
I started vacuum system.
I started TCS water system. The chiller does not work properly still. But, It will not affect the TM3 HV conditioning. HV cover is installed
on TM3 in TH. The module is ready for HV conditioning. |
Monday, July 25, 2016, 08:15, Anders Mjos, Conditioning Station, Repair, TM3, , HV Test
|
Monday, July 25, 2016, 08:14: Enabled staging for chiller
Monday, July 25, 2016, 08:33: Disabled staging. Fault 2. Staging does not work at this point.
Monday, July 25, 2016, 08:34: Running CP1 manually to cool down water. |
Tuesday, July 26, 2016, 11:22, chad fisher, South Hot-Cell, Maintenance, , , Soth Hot Cell Waste Storage Vault Tunnel
|
The two 45 gal (m) drums of waste removed from the south hot cell in December 2015 and January 2016 were transferred from the north hot cell to the shaft
of the east vault tunnel on Monday, July 25th 2016 and subsequently to the east tunnel bunker in the vault tunnel on Tuesday, July 26th, 2016.The first
drum (removed from the hot cell in December) containing both activated and contaminated metals was measured at 900 uSv/hr @ .5 m and the second drum (removed |
Friday, July 29, 2016, 14:27, Isaac Earle, North Hot-Cell, Development, , , North Hot Cell Measurements & Cleanup
|
The North Hot Cell was accessed today via the Ante Room for inspection, measurements,
and clean-up. There were no modules in the SHC or TCS, and no spent targets in the SHC. Under these conditions the maximum field in the NHC
was approximately 2μSv/hr. The inside of the cell was cleaned and swept, followed |
Wednesday, August 03, 2016, 09:15, chad fisher, South Hot-Cell, Repair, , , Manipulator
|
East manipulator on the south hot cell is showing signs of eminent wrist/tong cable failure. Some slight slippage was noted yesterday and confirmed by
a snapping sound and more slippage tomorrow. |
Wednesday, August 03, 2016, 09:49, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 is ready for conditioing at TCS.
|
I started TCS water system and installed HV cover onto TM4. The TM4 containment box is supplied with water also. TM4 is ready for conditioning
at TCS. |
Wednesday, August 03, 2016, 09:56, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)
|
Update schedule weekly. See attachments 1,2 |
Friday, August 05, 2016, 13:50, chad fisher, South Hot-Cell, Maintenance, , , Anteroom clean out
|
Some items have been removed from the anteroom in preparation for painting. Items have been placed on plastic in the south hot cell service area. No
contamination found so far. |
Friday, August 05, 2016, 14:13, Isaac Earle, North Hot-Cell, Development, , , Preparations for NHC Ventilation Test
|
A hole was drilled in the NHC exhaust duct in the east end of the target hall above the hatch to the Ante Room. This will be used for measuring
NHC exhaust flow rate with a thermal anemometer. The hole was tapped and plugged with an NPT tap.
Flow was measured in the existing hole in the SHC exhaust duct in approximately the same location. Flow velocity was measured to be 1415 |
Monday, August 08, 2016, 11:24, chad fisher, South Hot-Cell, Maintenance, , , Anteroom Clean-up - Waveguide
|
The wave guide from TM3 has been surveyed, swiped and removed from the anteroom and transported to rad waste for disposal. The wave guide has been stored
in the anteroom since its removal. |
Tuesday, August 09, 2016, 11:36, Anders Mjos, Conditioning Station, Maintenance, , , RGA and CG1S moved
|
The locations (ports) for the RGA and CG1S was swapped today by Anders and Isaac to provide clearance for the North Hot Cell ventilation. Attached
photos show old and new locations. |
Wednesday, August 10, 2016, 12:18, chad fisher, South Hot-Cell, Maintenance, , , Anteroom clearing
|
Black "radio active" materials cabinet has been emptied, items bagged and removed from the anteroom. Cabinet itself has been swiped inside
and out and also been removed from the anteroom. Most items have been removed from the anteroom now save some cardboard, rolls of plastic etc. |
Wednesday, August 10, 2016, 14:38, Isaac Earle, North Hot-Cell, Development, , , North Hot Cell Ventilation Test Results
|
Testing was performed on August 9th on the ISAC nuclear ventilation system to determine if the existing ventilation system can achieve the required cell
depressions for both SHC and NHC under all expected configurations and if a proposed modification to the DDC control system can provide acceptable stability
and response time for the system. The proposed control system observes the lower of the SHC depression or the NHC depression + 10% (to avoid stability |
Thursday, August 11, 2016, 10:37, David Wang, Conditioning Station, Repair, TM3, , TM3 service tray cover plate ITA2108 has been removed.
|
Requested by Aurelia, and approved by Friedhelm, TM3 service tray cover plate ITA2108 has been remove out of the module. The plated is checked for active
and contamination after removal. Then,It is double bagged, sealed , tagged, and placed downstairs in TH between south wall and green block . The
ram contact reading on the plate is about 10 usv/hr. We will do anther TM3 HV test at TCS without this cover plate. |
Friday, August 12, 2016, 09:58, chad fisher, South Hot-Cell, Maintenance, , , Manipulator Maitenance
|
Disassembled the master side of the right manipulator this morning to check the wrist cable. The cable on the master side shows no sign of wear or fraying
suggesting that the slave side cable may be the item that is wearing. during disassembly of the master I did notice some loose parts that could have been
the source of the audible concern but should not have contributed to the slippage felt in the gripper. I will try and schedule Tuesday for entry into the |
Friday, August 12, 2016, 10:59, Anders Mjos, Conditioning Station, Development, TM3, , HV Test with Service Chase Panel removed
|
Water cooling is performed manually with CP1. RGA is ON since yesterday. EE is not connected and in conditioning mode.
Friday, August 12, 2016, 10:43: BIAS at 10 kV, EL at 0.5 kV. IG1 at 1.8E-6 T
Friday, August 12, 2016, 11:04: BIAS at 20 kV |
Monday, August 15, 2016, 10:15, David Wang, Conditioning Station, Standard Operation, TM4, , Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)
|
Weekly update target hall schedule. Everything on schedule are finished on time. See attachment. |
|