981
|
Tuesday, July 07, 2015, 10:50 |
Anders Mjos | Conditioning Station | Development | | | EPICS migration update - archiver |
The archiver is now merged with
ISAC - data available under Utilities
- Archiver Retrieval
Old |
|
|
980
|
Friday, July 03, 2015, 13:29 |
chad fisher | South Hot-Cell | Repair | TM2 | | Hot Cell/ Module Fields | Field measured at block "R" through
tool port with pole monitor is 6.65 mSv/H.
There are three air hoods and two |
|
|
979
|
Friday, July 03, 2015, 11:33 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Coil Leak Progress | First thing this morning the hot cell was
"cleaned up" in preparation for
the return of TM2 for attempted verification |
|
|
978
|
Friday, July 03, 2015, 09:41 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - July 24 2015 | Updated the schedule before the weekend
2015-07-03. See attachment 1,2
Updated the schedule according to |
|
|
977
|
Friday, July 03, 2015, 09:27 |
Anders Mjos | Conditioning Station | Development | | | Controls working on access control in EPICS | Some reboots will be done. |
|
|
976
|
Friday, July 03, 2015, 09:11 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Module moved | TM#2 has been moved from the conditioning
station to the south hot cell. |
|
|
975
|
Thursday, July 02, 2015, 11:51 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#12 | Spent target moved | UC#12 has been moved from the south hot
cell and placed into storage. It is in pail
#125 and in spot 1C of the vault it had a |
|
|
974
|
Thursday, July 02, 2015, 11:49 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | Module moved | TM#1 has been moved from the south hot
cell to the south west silo. |
|
|
973
|
Thursday, July 02, 2015, 10:22 |
Anders Mjos | Conditioning Station | Maintenance | TM2 | | TP1S failed | See e-fault 8233. Edi assisted in
diagnosing the problem. The pump will have
to be replaced. |
|
|
972
|
Tuesday, June 30, 2015, 15:53 |
David Wang | Conditioning Station | Development | TM2 | | leak on TM2 at CS | I leak checked TM2 at CS this afternoon
which including air to vacuum check on service
cap and helium pressure test on water lines. |
|
|
971
|
Tuesday, June 30, 2015, 15:41 |
David Wang | ITW | Standard Operation | TM1 | | TM1 was disconnected in ITW this morning. | TM1 was disconnected in ITW this
morning. The ITW was vented with argon last
night. |
|
|
970
|
Tuesday, June 30, 2015, 12:37 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#12 | UCx #12 Removal | UCx#12 has been removed from TM1 and placed
in a pail with argon.
Right leg (B) of target is clearly |
|
|
969
|
Tuesday, June 30, 2015, 11:27 |
Travis Cave | ITW | Standard Operation | TM1 | UC#12 | Module moved | TM#1 with UC#12 has been moved from the
west station to the south hot cell. |
|
|
968
|
Tuesday, June 30, 2015, 09:47 |
chad fisher | South Hot-Cell | Repair | | | manipulator repair | The right hand manipulator has been repaired.
It took 43 minutes and I received ~ 0.56
mSv |
|
|
967
|
Monday, June 29, 2015, 10:51 |
David Wang | Conditioning Station | Repair | TM2 | | leak on TM2 side panel | There is an air to vacuum leak on TM2 service
cap side panel which we moved out during
the TM2 wiring job. The CS pumps are stopped |
|
|
966
|
Friday, June 26, 2015, 15:38 |
Anders Mjos | Conditioning Station | Development | TM2 | | Leak check and HV test | Roughing started by David.
Friday, June 26, 2015, 15:31: Started
TP1S |
|
|
965
|
Friday, June 26, 2015, 14:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 have been moved from SHC to CS | Bill and I mover TM2 from SHC to CS. The
move is smooth. I connected the CS vacuum
system after the move, and started the roughing. |
|
|
964
|
Friday, June 26, 2015, 09:45 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Status | Containment box window waterlines have
been connected and leak checked and new containment
box cover installed. |
|
|
963
|
Friday, June 26, 2015, 09:44 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Retrofit Status | On June 25th the following work was completed:
Optics tray was installed into TM2.
The lower fastener on the vertical cable |
|
|
962
|
Friday, June 26, 2015, 08:27 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - July 24 2015 | Update the Target hall Schedule after some
changes on TM2 refurbishment. See attachment
1,2 |
|