144
|
Tuesday, May 10, 2022, 11:31 |
Nadia Jorgenson | Cyclotron | Standard Operation | Vault Shield Door Closed |
The vault shield door has been closed and seal inflated. The operation was performed with no issue. |
153
|
Wednesday, April 26, 2023, 11:19 |
Adam Newsome | Cyclotron | Standard Operation | Vault Shield Door Closed |
The vault shield door has been closed and seal inflated. The operation was performed with no issue. |
147
|
Friday, January 27, 2023, 12:12 |
Adam Newsome | Infrastructure | Development | Vault crane - inspection, remote pendant installation |
The vault crane annual inspection was completed by Tom Kauss.
The wired pendant was replaced with a remote pendant by Tom Kauss. |
4
|
Friday, February 17, 2012, 15:07 |
Don Jackson | Trolley | Repair | Video Trolley Failed in Cyclotron Tank |
All control to the video trolley was lost during remote photographing of components in the cyclotron. The control system and cameras on the trolley were still operational leading to the suspicion that a power cable was broken either on the trolley or the bridge festooning. Two trips into the tank were made to evaluate the problem and attempt to push the trolley out of the tank. Pushing the trolley only managed to move the trolley a few feet before jamming. A lift mechanism was used to raise the drive wheel without any success. This device was modified and used successfully to remove trolley completely from the tank.
Three trips by two persons were required to remove the trolley. There was a total dose of 0.5 mSv was received by the two persons going into the tank. An additional 0.18mSv was receive by 3 persons outside of the tank.
The trolley will not be used in the cyclotron until the problem is diagnosed and repaired. This trolley is not critical to any upcoming remote handling operations. |
Attachment 1: Stuck_Video_Trolley_Feb_17_2012_005.jpg
|
|
Attachment 2: Stuck_Video_Trolley_Feb_17_2012_001.jpg
|
|
139
|
Monday, March 21, 2022, 13:14 |
Adam Newsome | Trolley | Repair | Video Trolley Mk 1 - Radial Limit Switch Replacement |
An issue was observed in which radial motion on the Video Trolley Mk 1 did not respond to commands. After troubleshooting, it was determined that this was due to the "OP LIMIT" interlock - the "OP LIMIT" pushbutton on the console was illuminated in red, and needed to be continuously held down in order to operate the radial in/out motion buttons.
It was determined that the root cause of the issue was a failed radial limit switch which was likely damaged during trolley transport. The limit switch was replaced, and functionality was restored. |
24
|
Monday, September 30, 2013, 14:02 |
Travis Cave | Service Bridge | Maintenance | new festooning |
The festooning and bearings for the festooning cars for both outriggers has been replaced and it is in working order. |
79
|
Friday, February 05, 2016, 14:57 |
Travis Cave | Service Bridge | Maintenance | outrigger problem |
outrigger 1 had a power failure, bridge was removed power restored and outrigger parked, outrigger will be looked at once the shield are done hopefully. |
78
|
Friday, February 05, 2016, 14:55 |
Travis Cave | Shielding | Standard Operation | shadow shields |
all 200, 400, 500, 600, and some 700 series of shield are in. |
80
|
Tuesday, February 09, 2016, 14:48 |
Travis Cave | Cyclotron | Standard Operation | shadow shields |
All shadow shields have been installed. Ladders, the pothole covers and the second rad survey will be done tomorrow. |
81
|
Wednesday, February 10, 2016, 14:53 |
Travis Cave | Cyclotron | Standard Operation | shadow shields |
All cyclotron in tank work is completed. |
33
|
Thursday, January 30, 2014, 13:47 |
Travis Cave | Cyclotron | Standard Operation | shields |
All shields, pothole covers, and ladders have been installed into the cyclotron. |
38
|
Tuesday, February 25, 2014, 15:00 |
Travis Cave | Shielding | Standard Operation | shields |
Started on the removal of shields. |
39
|
Wednesday, February 26, 2014, 14:55 |
Travis Cave | Shielding | Standard Operation | shields |
More shields have been removed from the cyclotron only 16 remain. I was also noted that the lift trolley is making an odd noise and will be looked at after the shutdown. |
40
|
Monday, March 03, 2014, 13:09 |
Travis Cave | Cyclotron | Standard Operation | shields |
all shields, porthole covers and ladder out and copper blockers in. Some conmination was found on the pads of the ladders (about a 1000 count or so) and was removed. |
31
|
Tuesday, January 28, 2014, 14:59 |
Travis Cave | Shielding | Standard Operation | shields |
200's, 400's, 500's, 600's, and a pallet of 700's have been installed |
30
|
Monday, January 27, 2014, 14:42 |
Travis Cave | Shielding | Standard Operation | shields and radiation survey |
The cyclotron radiation survey was aborted due to the orbit not working recording the numbers correctly. One shield has been in installed.
Jan 29th: uploaded meeting minutes from January 28th regarding the orbital counter problem. - Grant Minor
|
Attachment 1: Meeting_Orbital_Counter_Problem_Jan_2014.pdf
|
|