Entry  Wednesday, March 16, 2016, 17:19, Ron Kuramoto, Primary Beamlines, Development, 4VQ3 Removal IMG_1893.JPGIMG_1893.JPGIMG_1899.JPGIMG_1902.JPGIMG_1907.JPG
 On 8March2016, under W/P C2016-03-08-2, 4VQ3 was lifted out of BL4V with the vault orbit crane where it was first weighed then lifted onto the
RH flat deck rail dolly.  It was then moved into the RH basement where it was surveyed before lifting it up onto the Red wagon cart in the RH loading
bay.  It was then pulled to the Meson Hall loading bay by fork lift where and then over the Cycloton vault to the top of the E-Hall roof beams under
Entry  Wednesday, March 16, 2016, 17:57, Ron Kuramoto, Primary Beamlines, Development, 4VQ1&Q2 Removal 13x
 On 14March2016, 4VQ1&Q2 were removed from BL4V and lowered into the Vault basement B3 level where they were stored in the south west corner
on their respective wood pallets.  The hot ends of both magnets were place against the west wall.  4VQ2 was lifted out first and moved temporarily
downstream where it was separated from its magnet stand. Q2 was then craned into the basement where it was tipped 45o to lay on the flat side
Entry  Tuesday, April 16, 2019, 11:19, Ron Kuramoto, Primary Beamlines, Repair, 1AQ14 B/L Flange Broken Thermocouple 1AQ14_FlgTC1_7Mar2019.jpeg1AQ14_FlgTC2__7Mar2019.jpeg1AQ14_FlgTC3_7Mar2019.jpeg
On March 7,2019 the Thermocouple (TC) cable which monitors the temperature of the 1AQ14 B/L vacuum joint was broken when the iron shield block (Triumf Dwg
D-3237 aka M8 Tongue block) was restored on the east of the T2 Monolyth. See attached photos.  This TC (Omega #KTSS-116U-144) is attached to the 1AQ14
Indium ring seal (Triumf Ref Dwg TBP0372D) and should be replaced the next time this B/L joint is serviced.
The Controls Group has noted on the CCSC2,
Entry  Tuesday, February 14, 2012, 16:29, Keith C Ng, M20, Repair, m20 q1 q2 repair P1010986.JPG
Warm cell reconfigured for water leak repair at coil termination. Radiation surveys done. M20 Q1 ready for  removal of insulators.
Attached photo of warm cell as of Tuesday morning.
Entry  Thursday, February 16, 2012, 08:08, Keith C Ng, M20, Repair, m20 q1 q2 repair P1020003.JPGP1020001.JPG
Insulators # 6,7,8 removed from Q1 headers late afternoon by C Ballard. Ready for removal and re-brazing of #7 joint some time today.
Entry  Thursday, February 16, 2012, 16:22, Keith C Ng, M20, Repair, m20 q1 q2 repair IMG_2545.JPGP1020013.JPGP1020028.JPG
Old #7 coil fitting removed, replaced and re-brazed today by M Good. Insulators ready to go back on to magnet coils to be pressure checked.
Image    P1020013.JPG shows #7 coil fitting before removal. Heat shielding in the form of small aluminum sheets were installed to protect the magnet
and electrical wiring. 
Entry  Friday, February 17, 2012, 15:35, Keith C Ng, M20, Repair, m20 q1 q2 repair P1020033.JPGP1020037.JPGP1020038.JPGP1020035.JPGP1020031.JPG
Reinstalled ceramic insulators #6 7 8 to Q1 magnet by C Ballard. #6 and 8 went on with no issues. The copper tubing on insulator #7 had to be bent to
match the new position of the re-brazed #7 fitting. This may have been due to the removal of the inner and outer conductors (the two copper plates that
clamp the two coils together) during yesterdays repair which shifted the position of the coil. See photos.
Entry  Thursday, March 01, 2012, 16:01, Keith C Ng, Primary Beamlines, Repair, 2C Rad Hard Valve Replacement 
4" indium flanges at the 2C rad hard valve were cleaned of the remaining indium by C. Ballard. Both upstream and down stream flanges were done,
ready for installation of new valve.
Entry  Thursday, October 11, 2012, 16:40, Keith C Ng, M9, Repair, m9 t2 joint repair 20121011_RH1_01_0357.JPG20121011_RH1_02_0367.JPG20121011_RH1_02_0362.JPG20121011_RH1_02_0363.JPG
Today:
Bridge setup complete; Noticed 12 x 3 x 3 block when placed on top of several other blocks rocked when placed down.
Took initial photos of joint: west side approximately 0.05" to 0.06" gap, east side 0.20" to 0.220" gap. Joint appears to be
Entry  Friday, October 12, 2012, 15:12, Keith C Ng, M9, Repair, M9 T2 Joint Repair cont. 20121012_RH2_01_0002.JPG20121012_RH2_01_0004.JPG
Joint repair continues.
 
Leak Check:
Entry  Monday, October 15, 2012, 17:03, Keith C Ng, M9, Repair, M9 T2 joint repair cont. 
Today:
- Removed pins and removed indium through ring. Joint fully open at 14.5 to 15 turns of retraction mechanism.
- Did initial video inspection of T2 and Q1 flanges, some residual indium on knife surfaces, did initial scraping of T2 flange. (see videos on
Entry  Thursday, October 18, 2012, 08:26, Keith C Ng, M9, Repair, M9 T2 joint repair cont. 
Yesterday:
Installed indium blank off at M9 T2 joint and pumped down at 15:20 to 15:45 overnight. 1ACG7 (T2 vacuum pressure) reads between 6.0E-3mT and 2.0E-2
mT as of 8:15 today.
Entry  Thursday, October 18, 2012, 16:28, Keith C Ng, M9, Repair, M9 T2 joint repair cont. T2_Remote_Leak_Check.PDF20121018_m9q2_waterleak.jpg
Today:
Completed leak check of M9 T2 area: joint(s) are He leak tight. Remote He lines checked as well, see attached.
 
Entry  Friday, October 19, 2012, 16:48, Keith C Ng, M9, Repair, M9 T2 Joint Repair cont. 20121019_RH1_01_0081.JPG20121019_RH1_01_0082.JPG20121019_RH2_02_0004.JPG
Today:
Cleaned up work site and removed extraneous poles and tooling. Radioactive parts stored in lead flask now located on TNF.
- Two pins, an RH bullet bolt and indium ring (tb22148) were put into lead flask for storage, flask now located on TNF.
Entry  Monday, October 22, 2012, 15:48, Keith C Ng, M9, Repair, M9 T2 clean up and shield restoration 20121022_RH1_02_0092.JPG20121022_RH1_02_0081.JPG20121022_RH1_02_0082.JPG
Today;
Restoring shielding at M9 T2 area and cleaning up RH setup.
 
Entry  Wednesday, October 24, 2012, 11:53, Keith C Ng, M9, Repair, M9 T2 blank off complete 201211_m9t2repair.xlsx
Shielding around m9 t2 restored as of 11:45, vacuum levels still the same since 19 October.
- Work permit returned.
- A dose record of the job is attached as a spread sheet. Total dose for all workers is 1.89 mSv for the job.
Entry  Friday, January 11, 2013, 15:44, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement 
Assisted vacuum group with removing 1AVA8:
- uncovered valve area and set up remote handling bridge over valve.
- shut off pneumatic supply to valve to render valve in mid position (shut off valve in 1A tunnel). disconnected electrical services and air supply
Entry  Monday, January 14, 2013, 16:36, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement 
continued with o ring replacement, replaced all relevant o ring seals on valve (valve body seal and actuator arm dynamic seals).
- valve re installed and services reconnected.
- valve cycled and checked; valve, limit switches ok.
Entry  Tuesday, January 15, 2013, 16:37, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement 
Job completed today and shielding block over valve restored.
- He leak checked valve and accessible up stream joints, no leaks found.
- J McKinnon checked power supplies for nearby steering magnets before and after covering valve. supplies working ok.
Entry  Wednesday, January 16, 2013, 17:03, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair 
Moved 18' blocks away from triplet area in preparation for uncovering triplet. Plastic laid down up stream of t2 target station for short term storage
of 6' layered blocks.