122
|
Tuesday, September 24, 2019, 14:37 |
Keith C Ng | Primary Beamlines | Standard Operation | lead pig radiation survey |
Surveyed contents of storage flask located at TNF. The lid was lifted off roughly 12" up and a pole monitor was swept over the opening. The fields of the combined items in the flask were 9.84 mSv/h at 12-24". Extrapolated, the field is approximately 3.7 mSv/h at 1/2 m.
The flask contains an indium blank off plate, ISAC beam window and some miscellaneous used water fittings. The ISAC window is probably the largest contributor to the field.
A list of the contents and the dates the were placed into the flask are attached to the top of the flask lid. |
123
|
Thursday, October 24, 2019, 14:41 |
Keith C Ng | Primary Beamlines | Maintenance | annotated drawing of 1A Q15 cooling headers |
Annotated drawing of TBP0425D attempting to capture the repairs of 1A Q15 triplet magnet ceramic insulator/coils over the years.
Note that the file contains embedded comments visible only if opening the file in adobe acrobat reader. |
Attachment 1: tbp0425d_revB_acad-magnetinsulatortopheaderassembly_w-repairannotations.pdf
|
|
124
|
Monday, February 24, 2020, 15:13 |
Keith C Ng | M9 | Repair | m9 q1q2 repair laser tracker shoot |
Beamlines shot the position of the M9 T2 port and B1 flange for setting the M9 test stand flanges today. We removed the target jigs after this was done. |
Attachment 1: 20200224_m9project_P1040686.JPG
|
|
Attachment 2: 20200224_m9project_P1040688.JPG
|
|
125
|
Friday, March 06, 2020, 13:36 |
Keith C Ng | M9 | Repair | M9 B1 moved to warm cell |
The M9 B1 was removed from the M9 channel surveyed and moved to the remote handling warm cell for refurbishment.
The warm cell is currently locked. Remote Handling should be contacted if access is needed to B1.
A field map of B1 is attached as a pdf file. |
Attachment 1: 2020_M9_B1_field_survey_out_of_channel.pdf
|
|
126
|
Thursday, March 19, 2020, 15:42 |
Keith C Ng | Primary Beamlines | Development | Vault beamline beam position monitor |
The Beam Position Monitor between 1VB1 and 1VM3 has been installed. The indium joints are leak tight, however the V flanges are leaking slightly. The leak is small enough to still be able to run beam.
The Pin drive at the BPM and 1VB1 joint was replaced with a new one. The pin drive that was originally there had a bent screw drive so it was retired. The clamping collars at both joints were reused. |
127
|
Friday, August 07, 2020, 16:18 |
Keith C Ng | M9 | Maintenance | T2 M9 exit port and B1 flange cleaning |
Today we attempted to scrape remnant indium from T2 M9 exit port and clean B1 knife flange for the new magnet. Report of todays activities attached to the elog. |
Attachment 1: Cleaning_the_flanges.pdf
|
|
128
|
Monday, August 10, 2020, 16:08 |
Keith C Ng | M9 | Development | M9 Q1Q2 magnet assembly installed in pit |
The M9 Q1Q2 magnet assembly was installed in the M9 beam line today.
Attached to elog is an inspection report of the indium ring that will be used in the M9 T2 Q1 joint. |
Attachment 1: RHB_9237.JPG
|
|
Attachment 2: 20200810_indiumringinspectionreport.pdf
|
|
129
|
Friday, March 18, 2022, 12:12 |
Keith C Ng | Primary Beamlines | Repair | q15 repair |
beamlines replaced leaking insulator on q15, circuit #4. See updated pdf for replacement part and location. |
Attachment 1: tbp0425d_revB_acad-magnetinsulatortopheaderassembly_w-2022_repairannotations.pdf
|
|
Attachment 2: InkedRH1_0044_LI.jpg
|
|
Attachment 3: RH1_0046.jpg
|
|
Attachment 4: RH1_0050.jpg
|
|
Attachment 5: RH1_0049.jpg
|
|
130
|
Friday, May 06, 2022, 11:27 |
Keith C Ng | Primary Beamlines | Standard Operation | 4V CM1 RH joint install |
2022 Apr 28 to 29:
Installed a new remote handling 4" indium joint for new beamline 4 north section. Issues were encountered in clearance between the downstream steering magnet and the compression collar of the joint. Joint installation itself went smoothly.
The drive screw is a 17mm hex instead of a 5/8". This was noted in the install of the blank off plate in 2016.
See attached pdf report for photos and more description. |
Attachment 1: 2022_4v_cm1_rh_joint_install.pdf
|
|