11
|
Monday, December 22, 2014, 14:21 |
Isaac Earle | 100KW Beam Dump | Development | Water System Leak Checked | This morning Bill Richert pressurized the
beam dump water cooling system with 30psi
air and held for 2 hours. He reported |
|
|
6
|
Wednesday, December 03, 2014, 10:36 |
Isaac Earle | 100KW Beam Dump | Development | Upper half of BD water blocks installed; Bypass loops installed | On December 2 the upper half of the RH
water blocks were installed (4 total) using
a 0.030" thick 6061-T6 Al shim torqued |
|
|
9
|
Tuesday, December 16, 2014, 16:36 |
Isaac Earle | 100KW Beam Dump | Development | Upper Pb Shield and Water Hoses Installed | The upper lead shield was installed
this morning. Also the water hoses
for lower lead shield, beam dump, and upper |
|
|
1
|
Tuesday, November 04, 2014, 16:58 |
John Wong | 100KW Beam Dump | Maintenance | Testing Elog | Tuesday, November 04, 2014, 16:58
This is a test.
|
|
|
40
|
Wednesday, March 13, 2019, 16:14 |
Isaac Earle | 100KW Beam Dump | Development | Testing EHD water leak detectors | The following work was completed today
on the EHD water leak sensors:
Mike Vogel installed a |
9x |
|
70
|
Thursday, October 17, 2024, 11:34 |
Albert Kong | Hot Cell 1 | Development | Tarping completed on hot cell roof | Two tarps were installed above the hot
cell roof to protect against concrete dust
while testing in the hot cell. |
|
|
65
|
Wednesday, April 24, 2024, 09:17 |
Adam Newsome | T-Hall Crane | Repair | Target Hall Crane: VFD DC bus undervoltage fault [root cause: encoder board failure on 900VFD] | On 2024-04-22 around 3:30 pm it was discovered
that the crane's main hoist was in a faulted
state. The operator (Adam Newsome) experienced |
|
|
64
|
Wednesday, February 14, 2024, 09:02 |
Adam Newsome | T-Hall Crane | Maintenance | Target Hall Crane: Trolley Encoder Homing | The main trolley's E/W motion was observed
to be slowed on 2024-02-13.
Upon investigation, the following |
|
|
38
|
Monday, July 17, 2017, 15:32 |
Jason Kapalka | T-Hall Crane | Repair | Target Hall Crane modifications and repairs | |
|
|
62
|
Wednesday, April 26, 2023, 16:06 |
Adam Newsome | T-Hall Crane | Maintenance | Target Hall Crane - Hoist Wire Wrapping | It was observed recently that the main
hoist's wires seemed skewed, and there was
occasionally some noise heard when raising |
|
|
12
|
Friday, February 06, 2015, 13:32 |
Isaac Earle | 100KW Beam Dump | Development | TEL5079 Hose Modification | When the EHDT shielding service stand shield
plug was installed in January it was found
that the Beam Dump Outlet Hose (TEL5079) |
|
|
68
|
Tuesday, September 10, 2024, 13:03 |
Adam Newsome | Hot Cell 1 | Development | Spacer flange installation | The spacer flanges were installed on both
turntables today.
See photos and information in the |
|
|
69
|
Thursday, October 10, 2024, 12:22 |
Adam Newsome | Hot Cell 1 | Standard Operation | Safety Walkaround Complete - Hot Cell area | A safety walkaround was completed for the
ARIEL Hot Cell area.
The resulting spreadsheet can be |
|
|
66
|
Wednesday, July 17, 2024, 15:07 |
Adam Newsome | Hot Cell 1 | Standard Operation | Safety Walkaround Complete - B2 Level | A safety walkaround for July 2024 was completed
for the B2 level by A. Newsome. No deficiencies
to report. |
|
|
53
|
Monday, May 30, 2022, 12:58 |
Adam Newsome | T-Hall Crane | Development | Reversion of South position limit to OEM value | The position limit modification described
in e-log 49 has been reverted. Currently
the South soft limit is set back to 0.36m. |
|
|
28
|
Thursday, April 07, 2016, 11:25 |
Isaac Earle | 100KW Beam Dump | Development | Result of VCR Gasket Corrosion Test | In August 2014 gasket corrosion tests
were prepared by placing a 1" Swagelok
VCR gasket in a 500mL beaker with de-ionized |
|
|
43
|
Thursday, February 13, 2020, 08:51 |
Adam Newsome | T-Hall Crane | Standard Operation | Remote mode door limit switch bypass | The non-existent safety limit switch for
the target hall door which prevents remote
motion has been bypassed in the crane PLC |
|
|
25
|
Wednesday, June 24, 2015, 15:19 |
Isaac Earle | 100KW Beam Dump | Development | Remainder of BD Shielding Installed | The location of the already installed blocks
including the TSH0392 protruding lift bails
were remeasured, and it was found that modification |
|
|
16
|
Thursday, May 07, 2015, 16:23 |
Isaac Earle | 100KW Beam Dump | Development | RH Clamp Installed with Used Seal | The remote handling 4" marman flange
clamp was reinstalled today with a used seal.
It is "Clamp B" as tested |
|
|
14
|
Friday, April 17, 2015, 14:37 |
Isaac Earle | 100KW Beam Dump | Development | RH Clamp Delivered to Beamlines Group | A 4" Remote Handling Marman
Flange Clamp was delivered to Doug Preddy
today to be used to clamp the EHDT beam pipe |
|