|
ID |
Date |
Author |
Category |
Type |
Subject |
Text |
|
|
70
|
Thursday, October 17, 2024, 11:34 |
Albert Kong | Hot Cell 1 | Development | Tarping completed on hot cell roof | Two tarps were installed above the hot
cell roof to protect against concrete dust
while testing in the hot cell. |
|
|
69
|
Thursday, October 10, 2024, 12:22 |
Adam Newsome | Hot Cell 1 | Standard Operation | Safety Walkaround Complete - Hot Cell area | A safety walkaround was completed for the
ARIEL Hot Cell area.
The resulting spreadsheet can be |
|
|
68
|
Tuesday, September 10, 2024, 13:03 |
Adam Newsome | Hot Cell 1 | Development | Spacer flange installation | The spacer flanges were installed on both
turntables today.
See photos and information in the |
|
|
67
|
Tuesday, September 10, 2024, 12:52 |
Adam Newsome | T-Hall Crane | Standard Operation | Drive not ready faults observed on power-up | Upon powering on the crane today and attempting
to use the main hoist, the following faults
were present: |
|
|
66
|
Wednesday, July 17, 2024, 15:07 |
Adam Newsome | Hot Cell 1 | Standard Operation | Safety Walkaround Complete - B2 Level | A safety walkaround for July 2024 was completed
for the B2 level by A. Newsome. No deficiencies
to report. |
|
|
65
|
Wednesday, April 24, 2024, 09:17 |
Adam Newsome | T-Hall Crane | Repair | Target Hall Crane: VFD DC bus undervoltage fault [root cause: encoder board failure on 900VFD] | On 2024-04-22 around 3:30 pm it was discovered
that the crane's main hoist was in a faulted
state. The operator (Adam Newsome) experienced |
|
|
64
|
Wednesday, February 14, 2024, 09:02 |
Adam Newsome | T-Hall Crane | Maintenance | Target Hall Crane: Trolley Encoder Homing | The main trolley's E/W motion was observed
to be slowed on 2024-02-13.
Upon investigation, the following |
|
|
63
|
Wednesday, August 02, 2023, 09:13 |
chad fisher | Hot Cell 1 | Repair | Leak Rate Testing | On August 1, 2023 HC1 was pumped down to
-1200 Pa (gauge) and then valved off to test
the leak rate after turntables had been sealed |
|
|
62
|
Wednesday, April 26, 2023, 16:06 |
Adam Newsome | T-Hall Crane | Maintenance | Target Hall Crane - Hoist Wire Wrapping | It was observed recently that the main
hoist's wires seemed skewed, and there was
occasionally some noise heard when raising |
|
|
61
|
Tuesday, April 25, 2023, 12:28 |
Adam Newsome | T-Hall Crane | Standard Operation | ARIEL Target Hall Crane - Drives Fault | Today while operating the crane with load,
the crane stopped moving. Upon investigating,
all safety signals appeared to be OK. Fault |
|
|
60
|
Tuesday, March 21, 2023, 10:47 |
Adam Newsome | Hot Cell 1 | Repair | Circuit breaker replacement - telemanipulators | There was an issue with a 20 A circuit
breaker used to control motor assist functions
for the telemanipulators (specifically, the |
|
|
59
|
Thursday, March 16, 2023, 14:41 |
Adam Newsome | T-Hall Crane | Development | ARIEL Target Hall Crane - Spare Pendant Procured, Tested | A spare pendant for the overhead crane
was procured from COH. The pendant's functionality
is the same as the original one's. The pendant |
|
|
58
|
Friday, January 20, 2023, 14:48 |
Adam Newsome | T-Hall Crane | Standard Operation | Pendant/Receiver Communication Issue (Repeated) | An issue was observed in which the pendant
did not work to control the crane. This
is the second time in recent memory this |
|
|
57
|
Friday, January 13, 2023, 13:57 |
Adam Newsome | T-Hall Crane | Repair | Crane light (west) not working | It was observed today that the crane's
west light was not functioning. |
|
|
56
|
Tuesday, December 20, 2022, 10:03 |
Adam Newsome | T-Hall Crane | Standard Operation | Overhead crane powered off for the holidays | [edit 2023-01-03] The crane was powered
back on this morning - there do not appear
to be any faults on the HMI and it seems |
|
|
55
|
Wednesday, August 24, 2022, 13:47 |
Adam Newsome | T-Hall Crane | Standard Operation | Pendant/Receiver Communication Issue | In preparing to troubleshoot the issue
described in e-log #54, the crane was power
cycled, and the pendant battery removed, |
|
|
54
|
Tuesday, August 23, 2022, 10:32 |
Adam Newsome | T-Hall Crane | Maintenance | North Aux Hoist - reverse motion axes on E/W | Update 2022-10-06: During routine
inspection of the crane, Tom Kauss investigated
the direction swap issue. It was determined |
|
|
53
|
Monday, May 30, 2022, 12:58 |
Adam Newsome | T-Hall Crane | Development | Reversion of South position limit to OEM value | The position limit modification described
in e-log 49 has been reverted. Currently
the South soft limit is set back to 0.36m. |
|
|
52
|
Tuesday, March 15, 2022, 10:03 |
Adam Newsome | T-Hall Crane | Repair | North Aux Hoist VFD Replaced | The North Aux Hoist VFD which had failed
(e-log 50) was replaced today by Tom Kauss
and Adam Newsome on Work Permit A2022-03-15-1. |
|
|
51
|
Friday, February 18, 2022, 09:26 |
Adam Newsome | T-Hall Crane | Maintenance | Potential grease leak observed | Naimat Khan noticed after using the crane
that some grease dropped onto a spreader
bar, and believes it is a leak from the main |
|