ID Date Author Category Type Subject Text Attachments
  42   Tuesday, November 19, 2019, 10:31 Adam NewsomeT-Hall CraneRepair900VFD Encoder Board ReplacementAn issue arose in which the ARIEL crane hoist
could not be moved. It was determined that
the East and West drums were out of synchronization
 IMG_20191106_140016.jpgIMG_20191106_153311.jpgIMG_20191112_114042.jpgHoist_Sync_3.jpgHoist_Sync_5.jpg 
  41   Tuesday, August 13, 2019, 11:43 Jason KapalkaT-Hall CraneDevelopmentInstalled surge protectorBackground: On 2019-06-25 a Pri VelFdbk Loss
fault was discovered on the Main Hoist East
Drum South Motor of the ARIEL Target Hall
 908355.pdf 
  40   Wednesday, March 13, 2019, 16:14 Isaac Earle100KW Beam DumpDevelopmentTesting EHD water leak detectorsThe following work was completed today
on the EHD water leak sensors:

    Mike Vogel installed a
 9x 
  39   Friday, December 22, 2017, 12:42 Jason KapalkaT-Hall CraneStandard OperationPowered down ARIEL Target Hall Crane Powered down ARIEL Target Hall Crane
today by switching off main power switch
on B1 level in preparation for site-wide
  
  38   Monday, July 17, 2017, 15:32 Jason KapalkaT-Hall CraneRepairTarget Hall Crane modifications and repairs    
  37   Wednesday, June 28, 2017, 17:37 Isaac EarleBL4NDevelopmentBL4N 35-deg bender "No. 1" installed on magnet stand BL4N 35-deg bender magnet "No.
1" has been installed onto the magnet
stand with "stand leg" configuration
 IMG_0259.JPGIMG_0260.JPGIMG_0258.JPG 
  36   Monday, June 05, 2017, 16:16 Isaac EarleBL4NDevelopmentBL4N 35-deg bender stand assembly completeAssembly
of two complete bender stands was completed
 14x 
  35   Thursday, June 01, 2017, 15:25 Isaac EarleBL4NDevelopmentBL4N 35-deg bender adjustment blocks modified to fit magnetAdjustment blocks were installed on the
second dipole bender today (labeled "No.
03" "C15-III-57/15").  The
 Stress_analysis_on_TBP1808_and_1809_for_modification_to_fit_magnet_-_June_1_2017.pdfTBP1809.JPGTBP1808.JPG 
  34   Tuesday, May 16, 2017, 17:30 Jason KapalkaT-Hall CraneDevelopmentARIEL Target Hall Overhead Crane MeasurementsOn May 5, 2017 the Beamlines and Remote Handling
groups recorded distances in the ARIEL Target
Hall from the Target Pit floor and B1 Target
 ARIEL_Target_Hall_Overhead_Crane_Measurements_(20170505).pdfEmail_-_Michael_Vogel_-_ARIEL_B1_&_Target_Pit_floor_heights_(20170519).pdf 
  33   Tuesday, May 02, 2017, 16:52 Isaac EarleBL4NDevelopmentBL4N 35-deg bender stand hardened parts tested Hardness testing was performed on
1 sample each of parts TBP1822 and TBP1823
(part of the 35-deg magnet stand assembly
  
  32   Tuesday, April 18, 2017, 19:28 Jason KapalkaT-Hall CraneDevelopmentATH overhead crane fault investigationOn April 18, 2017, an investigation was initiated
to determine the cause of the ARIEL Target
Hall overhead crane faults that occurred
 8x 
  31   Wednesday, April 12, 2017, 10:52 Jason KapalkaT-Hall CraneRepairARIEL Target Hall crane oil leaks & inspection planOn March 29, 2017, a 9 tonne load was transferred
in the ARIEL Target Hall with the overhead
crane (TRIUMF crane #44). On April 3, 2017,
 IMG_3111.JPGIMG_3112.JPGIMG_3113.JPGIMG_3114.JPGIMG_3115.JPG 
  30   Friday, March 31, 2017, 19:39 Jason KapalkaT-Hall CraneDevelopmentARIEL Target Hall overhead crane faults (Test Mode)On March 29, 2017, a 9 tonne steel shield
block was transferred from the ARIEL Target
Pit and placed into a 
 history_201703311454.csvDataLogging_201703311520_Table.csvphoto_1.JPGphoto_2.JPG 
  29   Wednesday, February 15, 2017, 11:57 chad fisherT-Hall CraneDevelopmentJason's Remote Crane Test BoxesOn Tuesday, February 14th I finished modifying
Jason's boxes for the remote crane tests
by adding shelves to mount cameras... Apart
  
  28   Thursday, April 07, 2016, 11:25 Isaac Earle100KW Beam DumpDevelopmentResult of VCR Gasket Corrosion Test In August 2014 gasket corrosion tests
were prepared by placing a 1" Swagelok
VCR gasket in a 500mL beaker with de-ionized
 IMG_7003.JPGIMG_7004.JPGIMG_7005.JPGIMG_7006.JPGIMG_7007.JPG 
  27   Monday, January 25, 2016, 13:20 Allon MessenbergT-Hall CraneMaintenancePossible oil leakTwo small (approx. 5 cm across) puddles
of green fluid were discovered on the floor,
directly below the crane trolley.  The
 20160122_161849.jpg20160122_161830.jpg20160125_100929.jpg 
  26   Tuesday, November 03, 2015, 13:15 Isaac Earle100KW Beam DumpDevelopmentInitial tests of beam dump water system controlsDuring the maintenance period today the
E-Hall tunnel was accessed to begin controls
tests on the beam dump water system and initial
  
  25   Wednesday, June 24, 2015, 15:19 Isaac Earle100KW Beam DumpDevelopmentRemainder of BD Shielding InstalledThe location of the already installed blocks
including the TSH0392 protruding lift bails
were remeasured, and it was found that modification
  
  24   Monday, June 15, 2015, 17:08 Isaac Earle100KW Beam DumpDevelopmentE-Dump Shielding Installation- The hoist rings were removed from the
upper lead shield
- Two standard lock-blocks were installed
  
  23   Friday, June 12, 2015, 10:16 Isaac Earle100KW Beam DumpDevelopmentBeam Dump Vac Seal Vent & Test- Vacuum has been pumping steadily on the
EHDT section since June 8, reaching 3.2E-8
Torr at 8am today (June 12)
  