  14   Wednesday, November 26, 2014, 14:01 Laura Lambert       
  17   Thursday, July 13, 2017, 15:12 Laura LambertUnder Process D.H.W leak in SEM lab Thursday, July 13, 2017, 14:53
Same pipe that had a leak in the
cold lab ~1 month ago now has leak in SEM
 IMG_1713.JPGIMG_1715.JPGIMG_1716.JPGIMG_1719.JPG 
  18   Tuesday, August 08, 2017, 14:55 Laura Lambert  Glove box Alarm Tuesday, August 08, 2017, 14:28
Alarm for glove box went off this
afternoon.
  
  19   Wednesday, December 20, 2017, 09:16 Laura Lambert  RETURN and SUPPLY valves CLOSED for xmas break for both evap1 and evap2 Wednesday, December 20, 2017, 09:02
Replaced Argon tank
  
  20   Tuesday, January 23, 2018, 11:58 Laura Lambert  All BeO removed from Labs! Tuesday, January 23, 2018, 11:55
Portable glove box with everything
inside, contaminated beakers, pellets and
  
  21   Wednesday, January 31, 2018, 13:35 Laura Lambert  New lab safety mirrors installed in hot lab Wednesday, January 31, 2018, 13:31
3 x lab safety mirrors have been
installed in the hot lab, now all locations
 IMG_0237.JPGIMG_0239.JPG 
  22   Monday, April 09, 2018, 15:59 Laura LambertFixed Glove box leak in hot lab Friday, April 06, 2018, 16:21
Over the long weekend ~1000psi was
used up, indicating a leak somewhere in the
 GetImage.jpgGetImage_(1).jpgGetImage_(2).jpgGetImage_(3).jpg 
  46   Tuesday, April 18, 2023, 17:40 Keyur ChauhanFixed1Actinide Mass Balance CalibrationISAC-1 B1 Hot Lab
actinide mass balance calibration was carried
out on April 18, 2023, at 10:40 a.m. with
 Actinide_Mass_Balance_-_18_Apr_2023.pdf 
  56   Wednesday, March 27, 2024, 13:42 Keyur Chauhan  Actinide Mass Balance Calibration ISAC-I B1 Hot Lab ISAC-1
B1 Hot Lab actinide mass balance calibration
 Actinide_Mass_Balance_-_27_Mar_2024.pdf 
  1   Wednesday, March 30, 2011, 16:47 John Wong  All Fumehood pumps in hot and cold labs tripped off due to MCC-X powered downAll the fumehood pumps in the ISAC-I hot
and cold labs got tripped off when the MCC-X
was powered down (See ISAC WP#2011-03-30-5).
  
  2   Tuesday, April 12, 2011, 12:03 John Wong  Hot Lab Glove Box Regeneration Tue Apr 12 12:00:52 2011:  The hot
lab glove box regeneration was started yesterday
(April 11, 2011).  "Before regeneration,
  
  3   Tuesday, April 12, 2011, 12:07 John Wong  All Fumehood pumps in hot and cold labs tripped off due to MCC-X powered down

    

       
            
  
  4   Wednesday, April 13, 2011, 13:54 John Wong  Cloth booties now avaiable for hotlabWed Apr 13 13:53:46 2011

I've setup a box of cloth booties
for entering the hotlab.  They are
washable
  
  5   Friday, May 13, 2011, 11:59 John WongFixed Uranium Waste Container Removed from HotlabFri May 13 11:55:37 2011:  The contain
in the uranium waste container was removed
and transferred into a beaker and sealed. 
  
  6   Tuesday, June 21, 2011, 16:38 John WongFixed Planetary Ball Mill Re-Commisioning Tue Jun 21 16:30:48 2011: 
Re-Cap:  On June 13, 2011, the
milling jar gasket seal partially came out
  
  7   Friday, June 24, 2011, 18:00 John WongUnder Process TIS New Users Hi All,
As requested by Pierrer Bricault,
 I have added the following users to
 elog_demo.png 
  8   Tuesday, July 19, 2011, 16:26 John WongFixed Planetary Ball Mill moved to Hotlab Tuesday, July 19, 2011, 16:22:  The
planetary ball mill was in the coldlab, and
now it has moved to the hot lab for the purpose
 Screen_shot_2011-07-19_at_4.21.04_PM.png 
  9   Friday, August 19, 2011, 10:04 John WongUnder Process1Evaporator#1 glovebox repairingThe evaporator#1 glovebox is leaking from
the gloves, around the ports, and the base
(possible more places).  It is evident
  
  12   Tuesday, February 28, 2012, 12:01 John Wong  TIS/RH UsersTuesday, February 28, 2012, 11:31
Hi All,
Hope you all find the TIS/RH elog
  
  34   Wednesday, August 05, 2020, 19:50 Darwin Ortiz RosalesFixed1Hot Lab Glove Box RegenerationWednesday, August 05, 2020, 19:34
On Friday July 31 a regeneration
of the glovebox was started.
  