Wednesday, August 17, 2016, 17:30
Container coated with TaC using 'flushing technique', cleaned ionizer tube with acetone, so no coating inside ionizer tube
Wrapped with 3 x Ta heat shields, incl center block
Currently pumping down in evap2
Thursday, August 18, 2016, 10:14
HS water valves opened...leak detected see attachment for photo from archives
Vented and opened up.
Anders performed leak check, nothing found.
Replaced all seals with blue seals.
Pumping down now
Thursday, August 18, 2016, 16:12
HS water valves opened...leak detected again see attachment for photo of striptool
Vented and opened up.
working with Anders on finding leak...
Monday, August 22, 2016, 10:38
leaks FIXED!
HS water valves opened, NO leaks detected!
Tapped up manually to 70A
Vacuum stable, IGP1 = 2.5e-6 Torr
Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 350A
Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A
Once max setpoints achieved, will tap up manually to final desired temperature of 1900C
Monday, August 22, 2016, 14:58
TGHT = 115A, 1.3V
TBHT = 89A, 0.97V
IGP1 = 4.1e-7 Torr.
Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.
Monday, August 22, 2016, 16:01
IGP1 = 1.25e-6 torr
TGHT = 174A, 2.2V
TBHT = 118A, 1.4V
Lowering ramping rate to 0.2A/min and 0.1A/min for the TGHT and TBHT respectively for overnight ramping.
|