Entry  Tuesday, June 09, 2015, 10:44, Laura Lambert, Empty, 41177-2, LP-SIS, In progress, Sintering TaC coating container for ZrC back-up 
    Reply  Wednesday, June 10, 2015, 16:35, John Wong, Empty, 41177-2, LP-SIS, In progress, Sintering TaC coating container for ZrC back-up 
       Reply  Thursday, June 11, 2015, 16:10, Laura Lambert, Empty, 41177-2, LP-SIS, In progress, Sintering TaC coating container for ZrC back-up 
          Reply  Monday, June 15, 2015, 15:30, John Wong, Empty, 41177-2, LP-SIS, Done, Re-Sintering TaC coating container for ZrC back-up 
Message ID: 210     Entry time: Tuesday, June 09, 2015, 10:44     Reply to this: 212
Author: Laura Lambert 
Target Material: Empty 
Target Oven W.O#: 41177-2 
Source: LP-SIS 
Status: In progress 
Subject: Sintering TaC coating container for ZrC back-up 

 Tuesday, June 09, 2015, 9:16

Target container is coated with TaC. No Ta-heat shields are used.

TGHT will be ramped up to 580A at 0.2A/min.

TBHT will be ramped up to 230A at 01A/min.

Chamber is currently being pumped down.


 Tuesday, June 09, 2015, 15:37

HS water valves were opened. no leaks detected.

Tapped up manually to 35A.

Once vacuum stabilized after ~45min, initiated auto-ramp.


 Wednesday, June 10, 2015, 08:02

IGP1 = 5.3e-7 Torr.

TGHT = 250A and TBHT = 140A.

Increasing auto ramp to 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.


 