Entry  Tuesday, April 09, 2024, 14:43, Darwin Ortiz Rosales, UO2, , LP TUBE, In progress, UCx240408 reduction 
Tuesday, April 09, 2024, 14:42
Cartridge #16 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, October 11, 2023, 10:06, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, TUCx-231005 reduction & conditioning 
Wednesday, October 11, 2023, 9:36
Cartridge #10 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, March 22, 2023, 22:29, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, 230316 Reduction 
Wednesday, March 22, 2023, 22:29
Cartridge #9 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Thursday, January 19, 2023, 10:02, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, C230105 Reduction 
Thursday, January 19, 2023, 09:57
Cartridge #8 loaded with 198 discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Monday, December 19, 2022, 10:45, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, C-221207 Reduction 
Monday, December 19, 2022, 10:38
Cartridge with 175 discs (including 5 analysis discs) loaded into a graphite cartridge. 
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields
Entry  Monday, November 28, 2022, 05:59, Darwin Ortiz Rosales, UO2/C, , LP-SIS, Done, C221125experiment Data_summary.png
Monday, November 28, 2022, 05:58
Left weekend to pump down
current IGPI= 7.23e-7 Torr
Entry  Wednesday, October 19, 2022, 12:28, Darwin Ortiz Rosales, UC2, 40253-5, LP TUBE, Done, C-220510 further conditioning 
Wednesday, October 19, 2022, 10:27
Cartridge-220510Cx was installed in the EVAP1 and pumped down yesterday.
Material will be further conditioned at 450A for 4 hours.
Entry  Friday, October 07, 2022, 08:14, Darwin Ortiz Rosales, UO2/C, , LP-SIS, Done, C-220928UCx conditioning experiments Cap_1_221011.pngCap_2.pngcap3.png
Friday, October 07, 2022, 07:55
Cartridge-220928UCx was installed in the EVAP1 and pumped down yesterday.
Material will be reduced in LP-SIS wrapped with 3 Ta foils.
Entry  Tuesday, June 07, 2022, 07:09, Darwin Ortiz Rosales, UO2/C, Target Boat, , Done, UO2 reduction ID C220510-1 
Tuesday, June 07, 2022, 07:05
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (previous
day)
Entry  Friday, June 03, 2022, 06:21, Darwin Ortiz Rosales, UO2/C, 42218-4, LP-IG-LIS, Done, UCx#39 reduction 

Friday, June 03, 2022, 06:24
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (previous
day)
Entry  Wednesday, June 01, 2022, 08:42, Darwin Ortiz Rosales, UO2/C, Target Boat, , Done, UO2 reduction Provisional ID C211209-1  
Wednesday, June 01, 2022, 08:39
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (previous
day)
Entry  Wednesday, May 04, 2022, 09:47, Luca Egoriti, UC2, , P2N-SIS, Done, P2N carbothermal reduction P2NC220408 
 Wednesday, May 04, 2022, 09:42
Yesterday, a second graphite cartridge was installed in EVAP1, it consists of the old, 3-body cartridge design, and was sanded on the outside to
be able to fit a P2N container. 
Entry  Wednesday, April 13, 2022, 10:55, Luca Egoriti, UC2, , P2N-SIS, Done, P2N carbothermal reduction P2Ncartridge-220323 
Wednesday, April 13, 2022, 10:50
P2NC-220323
Preparing the P2N-UCx for online operation on June 2022
Entry  Wednesday, November 24, 2021, 10:38, Luca Egoriti, Ta, , , In progress, IPF release tests 
Wednesday, November 24, 2021, 10:38
A first, short "FullTa1" target was loaded into the evap1. It consists of a short container (10 cm) with lateral thickness of ~0.2mm.
The ends of the target connect with the TGHT terminals through two copper adapters.
Entry  Friday, November 05, 2021, 13:38, Luca Egoriti, Ta, , LP-SIS, In progress, Full target release test 2 Ta-ReleaseTest-2_low-current.JPG
 Friday, November 05, 2021, 13:23
Full target loaded with ~500 non-active foils plus 4 active foils.  
Initial pressure when heating: 1.6E-5 T 
Entry  Friday, September 24, 2021, 15:40, Luca Egoriti, Ta, , LP-SIS, In progress, Full target release test 1 
 Friday, September 24, 2021, 15:38
Full target loaded with ~500 non-active foils plus 4 active foils.  
Initial pressure when heating: 6.6E-5 T 
Entry  Thursday, September 23, 2021, 07:03, Darwin Ortiz Rosales, UO2/C, , TARGET BOAT, Done, UCx#35 C reduction 
 Thursday, September 23, 2021, 06:55
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (Wednesday
September 22)
Entry  Wednesday, September 15, 2021, 07:19, Marla Cervantes, UC2, , TARGET BOAT, Done, Conditioning 2sc samples 
Wednesday, September 14, 2021, 21:14
Boat is wrapped with 2 layers of Ta-heat shield
The samples consists of 15 discs of UCx of 14mm diameter
Entry  Wednesday, July 07, 2021, 12:40, Darwin Ortiz Rosales, UO2/C, , TARGET BOAT, Done, UCx Provisional ID= 200229 conditioning 
 Wednesday, July 07, 2021, 14:39
Target Provisional ID = 200929 was installed in the EVAP1 and pumped down (Tuesday July 7, 2021).
Target is going to be thermally reduced for 8 hours and then conditioned for an additional 8
Entry  Wednesday, June 30, 2021, 13:35, Darwin Ortiz Rosales, UO2/C, , TARGET BOAT, Done, UCx#34 conditioning 
Target #34 was installed in the EVAP1 and pumped down (Tuesday June 29, 2021).
Target #34 is going to be conditioned on a Ta boat wrapped with 3 Ta foils.
IGP1 = 1.85e-6 Torr
ELOG V2.9.2-2455