OLIS Logbook General
  General, Page 14 of 26  Not logged in ELOG logo
Entry  Fri Feb 19 17:54:40 2010, Damien Gallop, , , OLIS Shutdown in progress DSCN7351.JPGDSCN7355.JPG
Partial disassembly of DB1 optics today. Shielding of insulators is definitely working and indicated for unshielded insulators. Discussion of possibilities
in progress. Wiring looks good, but one Kapton wire snapped at the connector upon disassembly (no force required).
Entry  Thu Mar 11 23:02:18 2010, Keerthi, , , OLIS status after shutdown 
Microwave source is up and running.
Supernanogan: grounding rod is stuck, RF generator does not clear the interlocks (controls?)
LEBT: FC3 air leak, in is out, out is in
Entry  Fri Mar 12 11:33:09 2010, Keerthi, , , IOS:IG! 
IOS:IG1 is faulty. Need to replac it during next earliest window.
Entry  Fri Mar 12 11:35:34 2010, Keerthi, , , Cusp water cooling 
Cusp source water cooling (#4)  interlick does not work.
Entry  Wed Mar 17 09:25:27 2010, Damien Gallop, , , 20Ne1+ at 40.8keV for accelerator commissioning Picture_2.pngPicture_3.pngPicture_4.png
20Ne1+ set up from the MWS and handed over to Sophia & Marco for accelerator recommissioning. Strip to 5+ at M:5. First day of beam. Happy St. Patrick's
Day.
Later... a Stripchart of beam today: baby-blue trace is FC6. Also, here are screenshots of the source.
Entry  Fri Mar 19 09:00:21 2010, Damien Gallop, , , 20Ne1+ at 40.8keV for accelerator commissioning Picture_5.png
MWS is running well. Tune save: 100319_0901.snapiosdragon with beam observed to Prague magnet. Stripchart of last 24h attached.
Entry  Wed Mar 24 11:42:32 2010, Damien Gallop, , , 20Ne1+ at 40.8keV for accelerator commissioning Picture_9.png
Beam is on standby. Target snapshot
in IOPS elog.  Over the last little while...
* IOS:IG1 repaired last evening. IOS vented to Ar, flowing for duration of repair. Standard Varian filament repair kit used with Dimo's instructions.
Entry  Thu Mar 25 12:43:16 2010, Damien Gallop, , , 20Ne1+ at 40.8keV for accelerator commissioning Picture_8.png
Beam stable as a rock overnight. Pity we have no-one using it at the moment! Stripchart attached.
Entry  Fri Mar 26 09:31:04 2010, Damien Gallop, , , 20Ne1+ at 40.8keV for accelerator commissioning Picture_10.png
Beam idling overnight. Yesterday ICR called me regarding an IOSIOC reboot and consequent fallout. In short, it turned off IOS:MB. Not good. While the
fix was easy enough, it took time to find it, which would translate to downtime during regular delivery. A lesson learned. I just noticed now that the
magnet stability program was out of range and obviously had been since the IOC reboot. I reset the power supply and field. This procedure will need to
Entry  Mon Mar 29 12:15:00 2010, Damien Gallop, , , 20Ne1+ at 40.8keV for accelerator commissioning 
OLIS sprung a water leak last night. Problem was sparking through a coiled  cooling line. I replaced the pair of cooling lines and rerouted them
somewhat. Source is up again now.
Entry  Tue Mar 30 10:27:09 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning Picture_12.png
16O1+ beam requested yesterday. Source switched over and beam ready by evening. Nice overnight Stripchart, attached. Sophia has the beam now.
Entry  Wed Mar 31 09:43:30 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning Picture_13.png
Beam set up for accelerator commissioning. Sophia took beam yesterday. Beam idle overnight. Stripchart of overnight performance attached.
Entry  Thu Apr 1 09:23:08 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning Picture_1.png
Beam idle overnight. Another night of super-stable beam. If no users today, then we may take it for MRO.
Later... Check out magstab program while we have quiet time. Test outcomes when serial link is opened. Purpose: Improve fault tolerance. Done.
Sophia will take the beam shortly.
Entry  Mon Apr 12 11:53:22 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning Picture_1.pngPicture_2.png
Beam was used last week for DRAGON commissioning. Successful run, completed yesterday, as reported by Colin this morning.
Milestone: First coasting beam through
new SCC on Thursday, 8-Apr-2010 at ~20:00, using 16O(1+)4+ at 1.5MeV/u from MWS.
Entry  Tue Apr 13 10:20:27 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning Picture_3.png
Accelerator commissioning has resumed for the day. Beam was nice and stable overnight. See attached Stripchart.
Entry  Wed Apr 14 17:28:32 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning 
Beam reserved for continuing accelerator development, but there are some ISAC-I RF phase troubles. However, maintenance was not permitted today... until
just now. Too late for today.
Entry  Thu Apr 15 09:39:11 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning 
Yesterday's RF troubles in ISAC-I are reportedly solved. Beam development is expected to resume this morning.
Entry  Fri Apr 16 09:26:01 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning grab.Ft9922.png
Beam development through accelerators continues today. Beam was rock-stable overnight.
Entry  Mon Apr 19 10:11:17 2010, Damien Gallop, , , 16O1+ at 32.64keV for accelerator commissioning Picture_1.pnggrab.a19570.png
Development on Friday; idle over the weekend. Stripchart attached.
Meanwhile, there was a power bump at around 09:30, and the source went out. Restarted OK.
Entry  Mon Apr 19 17:12:55 2010, Damien Gallop, , , OLIS Maintenance 
Just in: an active work permit for OLIS maintenance. Underway through tomorrow (Tuesday) evening.
Save: 100416_2339.snapiosvault
Later... done for today. Source is on for the night.