  Test-Stand, Page 8 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subjectdown Text Attachments
  485   Monday, January 11, 2016, 09:02 Anders Mjos       VentingMonday, January 11, 2016, 09:02: Turbos
stopped.
Monday, January 11, 2016, 12:58:
  
  492   Friday, January 22, 2016, 11:07 Anders Mjos      In progressVenting Friday, January 22, 2016, 11:07:
Stopped turbos
  
  105   Tuesday, June 26, 2012, 16:06 Anders Mjos      DoneVented

    

       
            
  
  137   Monday, July 09, 2012, 12:57 Anders Mjos      DoneVented    
  240   Tuesday, December 04, 2012, 11:05 Anders Mjos       VentedIn preparation for RFQ target and leak
troubleshooting.
Tuesday, December 04, 2012, 11:04:
  
  920   Wednesday, April 20, 2022, 13:42 Aaron Schmidt       Vent Beamline halfAurelia to do a visual test later.
Wednesday, April 20, 2022, 13:41:
IG6 Off. TP6 & TP2 off.
  
  24   Monday, October 17, 2011, 10:22 Anders MjosFEBIAD     Problems/SolutionsVariable leak valve replacedVariable leak valve with serial number
F3-592 has been replaced by F3-649 due
to regulating problems described previously
 F3-649.PDF 
  25   Monday, November 14, 2011, 15:40 Anders Mjos      Problems/SolutionsVariable leak valve repaired

    

       
            
 F3-VCR-43_Repair_F3-592.PDF 
  28   Tuesday, December 20, 2011, 16:09 Anders Mjos      Problems/SolutionsVariable leak valve repaired

    

       
            
  
  357   Wednesday, January 29, 2014, 14:42 Anders Mjos      Problems/SolutionsValved off water to TSG and TMS:MB1CuLCW will be shut off tomorrow. Valved
off water supply to MB1 and TSG to minimize
air into the system. Turbos are off.
  
  344   Tuesday, November 12, 2013, 12:38 Anders Mjos      Problems/SolutionsVacuumed desk, on and around the beam line    
  779   Thursday, January 23, 2020, 16:05 Anders Mjos      Problems/SolutionsVacuum tripped due to PLC/EPICS for for the new BIASThursday, January 23, 2020, 16:05: Restarting
vacuum and TPs
  
  601   Thursday, August 03, 2017, 17:00 Anders Mjos      Problems/SolutionsVacuum system tripped on power interruption Thursday, August 03, 2017, 17:00:
Restarted TPs
  
  791   Friday, March 27, 2020, 11:30 Aaron Schmidt       Vacuum loss / spike / ShutdownThe ISAC was left with the turbo pumps
and water supplies running. Just the power
supplies off. Monday, March, 23, 2020.
 Mar_27_-_2020_-_Vacuum_Trip.docx 
  792   Tuesday, April 07, 2020, 10:53 Anders Mjos       Vacuum loss / spike / Shutdown


   
        
            
  
  577   Monday, April 10, 2017, 15:12 Anders Mjos      Problems/SolutionsVacuum leak on front doorThe vacuum behaved erratic over night with
excursion up into the mid 10^-6 Torr range.
To investigate the chamber was vented. With
  
  697   Monday, November 19, 2018, 14:22 Aaron Schmidt      Problems/SolutionsVacuum issues.





Normal
0
  
  350   Thursday, December 12, 2013, 09:01 Anders Mjos      Problems/SolutionsVacuum excursion over nightMonday, December 16, 2013, 08:53
Some additional smaller magnitude
excursions have been observed since the fist
 VacuumExcursion-2013-12-12.pngVacuumExcursion-2013-12-16.png 
  570   Wednesday, February 15, 2017, 13:42 Aaron Schmidt    42218-1141751-6Problems/SolutionsVacuum Check (Water leak)*Vacuum from previous test still active,
minus turbo pumps. Same target, & heat
shield as well.*
  
  776   Friday, January 03, 2020, 11:56 Anders Mjos      Problems/SolutionsUpgrading BIAS Power SupplyA new power supply was installed today
by John Chow. Due to differences in pin configuration
of the controls, a change to the cabling
  