Entry  Monday, January 05, 2015, 09:20, Anders Mjos, , , , , , , Problems/Solutions, IV4 did not get close signal before the Hollidays 

The valve closes physically, but does not receive the closed signal.

Cycled the valve multiple times before finally showing closed state.

Entry  Tuesday, January 20, 2015, 14:31, Anders Mjos, , , , , , , Problems/Solutions, Ne leak disconnected for recallibration 

SN 11-231 from VIC

Entry  Wednesday, January 28, 2015, 10:40, Anders Mjos, , , , , , , Problems/Solutions, Test Stand shut down for site wide power outage today 

Friday, January 30, 2015, 10:50: Optics section accidentally vented during work on the ER


Monday, February 02, 2015, 13:24: Roughing TMS section

Monday, February 02, 2015, 13:39: Starting turbos

Monday, February 02, 2015, 13:45: Turbos at speed

Monday, February 02, 2015, 13:49: Vacuum at 5.7 E-5 T


Tuesday, February 03, 2015, 09:00: Vacuum low 1E-6 T. Backing pressure high ~ 75 mT. Caused by TP6.

Tuesday, February 03, 2015, 09:01: Turbos stopped to investigate vent screw on TP6.

Tuesday, February 03, 2015, 09:40: Venting through TP6

Gasket on the TP6 venting screw had fallen off. Re-installed.

Tuesday, February 03, 2015, 09:57: Roughing

Tuesday, February 03, 2015, 10:32: Started turbos

Tuesday, February 03, 2015, 10:45: Turbos at speed. Vacuum at 1.3E-5 T

Entry  Tuesday, February 03, 2015, 09:40, Anders Mjos, , , , , , , Problems/Solutions, RGA installation 2015-02-04-1340.png

Tuesday, February 03, 2015, 09:40: Venting

RGA installed on the 12" CF port below the Source Tray.


Wednesday, February 04, 2015, 13:45: RGA turned on and mass scan performed.

Entry  Tuesday, February 03, 2015, 16:10, Anders Mjos, , , , , , , Problems/Solutions, Current read back on TBHT has been corrected to 600 A 

 By controls group

Entry  Friday, February 13, 2015, 13:59, Anders Mjos, , , , , , , Problems/Solutions, PLC failure 

The PLC CPU came out of the socket around 11:50am today (Dave Morris). The CPU had not been properly attached. This resulted in full stop of all power supplies and vacuum pumps.

Restarted vacuum pumps at 12:10pm (20 min later).

Entry  Wednesday, February 18, 2015, 13:32, Anders Mjos, , , , , , , Problems/Solutions, Switched off system in preparation for power outage 

Thursday, February 19, 2015, 12:14: Starting system again after the power outage

Thursday, February 19, 2015, 13:27: The performance of RP1 has degraded. Edi flushed some air through, which helped a bit. It now takes longer to start up.

Thursday, February 19, 2015, 13:33: Vacuum recovered.

Entry  Thursday, April 09, 2015, 11:21, Anders Mjos, , , , , , , Problems/Solutions, No RGA communcations 

RGA stopped working. Likely after a spark yesterday.

Entry  Monday, April 13, 2015, 13:07, Anders Mjos, , , , , , , Problems/Solutions, ISAC Test Stand Optical elements power supply drop out 

 See e-fault 8027 

Monday, April 13, 2015
Kevin and Graham are working on it

 

 

 

 

Entry  Friday, April 24, 2015, 12:25, Anders Mjos, , , , , , , Problems/Solutions, Backing line pressure high 

TSG:RP1 backing line pressure is >200 mT. An e-fault has been submitted to have the roughing pump replaced.

Friday, April 24, 2015, 13:13: Pump replaced by vacuum group.

Entry  Monday, May 04, 2015, 09:51, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Coil power supply replaced 

 Power supply did not work after high voltage conditioning. On Friday May 1st John Chow replaced the power supply with a 12 V 100 A power supply temporary while the other supply is being repaired. EPICS controls have not been adjusted.

Entry  Friday, May 08, 2015, 09:07, Anders Mjos, , , , , , , Problems/Solutions, EPICS lost contact with the PLC 

Everything shut down, while EPICS showed everyhing to be on.

Controls group (Dave Morris) has reestablished contact. System is operations.

TSG section vented for Source Tray work

Friday, May 08, 2015, 09:13: TMS turbos at speed. Vacuum at 1.2E-5 T

Entry  Tuesday, May 19, 2015, 19:10, Anders Mjos, , , , , , , Problems/Solutions, EPICS white out 

 Likely caused by the PLC. e-fault  8139


Wednesday, May 20, 2015

Dave Morris re-established contact with controls. (PLC IOC was down).

Entry  Thursday, May 21, 2015, 16:40, Anders Mjos, , , , , , , Problems/Solutions, Reconfigured service cap coil connections TestStandSourceTray.jpgTM2SourceTray.jpg

 The service cap has been reconfigured (colling and electric) to be compatible with the TM2 Source tray. Coil- is E & F , Coil+ is G & H.

Entry  Thursday, May 21, 2015, 17:38, Anders Mjos, , , , , , , Problems/Solutions, Installed equipment for measuring outgassing rate 

 A gauge and a valve was installed on the roughing line to the large turbo pump

Entry  Wednesday, June 03, 2015, 09:35, Anders Mjos, , , , , , , Problems/Solutions, PLC upgrade 

Wednesday, June 03, 2015, 09:35: TP6 and TP2 off

Wednesday, June 03, 2015, 10:15: Upgrade in progress.

Entry  Monday, June 15, 2015, 14:07, Anders Mjos, , , , , , , Problems/Solutions, Test Stand Source Tray installed Coils_configuration.jpg

Monday, June 15, 2015

Remaining items to do

  • ANODE wire not yet attached
  • FEBIAD COILS not yet reconfigured

Tuesday, June 16, 2015:

Coils reconfigured. See attached photo.

 

Entry  Monday, June 29, 2015, 16:51, Friedhelm Ames, , , , , , , Problems/Solutions, TSG:BV1B closed 

found TSG:TP1B tripped off. Closed TSG:BV1B as pressure at TSG:iG1 was rising. Pressure is coming down again.


Tuesday, June 30, 2015 by AM

Found the control cable not completely inserted. Inserted cable, which tripped TP1A. Started both turbo pumps again.

Tuesday, June 30, 2015, 09:54: Both turbos at speed.

Tuesday, June 30, 2015, 09:56: Stopped turobs. BV1B does not close when TP1B is switched off. Requested Dave Morris to look into it. All remaining BVs close when TP is swithced off in TMS and TSG sections.

Entry  Monday, July 06, 2015, 09:29, Anders Mjos, , , , , , , Problems/Solutions, Replaced out gassing gauge on the backing line 
 
Entry  Tuesday, August 04, 2015, 13:37, Anders Mjos, , , , , , , Problems/Solutions, Equipment for outgassing measurements removed 
 