Entry  Monday, January 05, 2015, 09:20, Anders Mjos, , , , , , , Problems/Solutions, IV4 did not get close signal before the Hollidays 
The valve closes physically, but does not receive the closed signal.
Cycled the valve multiple times before finally showing closed state.
Entry  Tuesday, January 20, 2015, 14:31, Anders Mjos, , , , , , , Problems/Solutions, Ne leak disconnected for recallibration 
SN 11-231 from VIC
Entry  Wednesday, January 28, 2015, 10:40, Anders Mjos, , , , , , , Problems/Solutions, Test Stand shut down for site wide power outage today 
Friday, January 30, 2015, 10:50: Optics section accidentally vented during work on the ER

Monday, February 02, 2015, 13:24: Roughing TMS section
Monday, February 02, 2015, 13:39: Starting turbos
Entry  Tuesday, February 03, 2015, 09:40, Anders Mjos, , , , , , , Problems/Solutions, RGA installation 2015-02-04-1340.png
Tuesday, February 03, 2015, 09:40: Venting
RGA installed on the 12" CF port below the Source Tray.

Wednesday, February 04, 2015, 13:45: RGA turned on and mass scan performed.
Entry  Tuesday, February 03, 2015, 16:10, Anders Mjos, , , , , , , Problems/Solutions, Current read back on TBHT has been corrected to 600 A 
 By controls group
Entry  Friday, February 13, 2015, 13:59, Anders Mjos, , , , , , , Problems/Solutions, PLC failure 
The PLC CPU came out of the socket around 11:50am today (Dave Morris). The CPU had not been properly attached. This resulted in full stop of all power
supplies and vacuum pumps.
Restarted vacuum pumps at 12:10pm (20 min later).
Entry  Wednesday, February 18, 2015, 13:32, Anders Mjos, , , , , , , Problems/Solutions, Switched off system in preparation for power outage 
Thursday, February 19, 2015, 12:14: Starting system again after the power outage
Thursday, February 19, 2015, 13:27: The performance of RP1 has degraded. Edi flushed some air through, which helped a bit. It now takes longer
to start up.
Entry  Thursday, April 09, 2015, 11:21, Anders Mjos, , , , , , , Problems/Solutions, No RGA communcations 
RGA stopped working. Likely after a spark yesterday.
Entry  Monday, April 13, 2015, 13:07, Anders Mjos, , , , , , , Problems/Solutions, ISAC Test Stand Optical elements power supply drop out 
 See e-fault 8027 
Monday, April 13, 2015
Kevin and Graham are working on it
Entry  Friday, April 24, 2015, 12:25, Anders Mjos, , , , , , , Problems/Solutions, Backing line pressure high 
TSG:RP1 backing line pressure is >200 mT. An e-fault has been submitted to have the roughing pump replaced.
Friday, April 24, 2015, 13:13: Pump replaced by vacuum group.
Entry  Monday, May 04, 2015, 09:51, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Coil power supply replaced 
 Power supply did not work after high voltage conditioning. On Friday May 1st John Chow replaced the power supply with a 12 V 100 A power supply temporary while the other supply is being repaired. EPICS controls have not been adjusted.
Entry  Friday, May 08, 2015, 09:07, Anders Mjos, , , , , , , Problems/Solutions, EPICS lost contact with the PLC 
Everything shut down, while EPICS showed everyhing to be on.
Controls group (Dave Morris) has reestablished contact. System is operations.
TSG section vented for Source Tray work
Entry  Tuesday, May 19, 2015, 19:10, Anders Mjos, , , , , , , Problems/Solutions, EPICS white out 
 Likely caused by the PLC. e-fault  8139

Wednesday, May 20, 2015
Dave Morris re-established contact with controls. (PLC IOC was down).
Entry  Thursday, May 21, 2015, 16:40, Anders Mjos, , , , , , , Problems/Solutions, Reconfigured service cap coil connections TestStandSourceTray.jpgTM2SourceTray.jpg
 The service cap has been reconfigured (colling and electric) to be compatible with the TM2 Source tray. Coil- is E & F , Coil+ is G & H.
Entry  Thursday, May 21, 2015, 17:38, Anders Mjos, , , , , , , Problems/Solutions, Installed equipment for measuring outgassing rate 
 A gauge and a valve was installed on the roughing line to the large turbo pump
Entry  Wednesday, June 03, 2015, 09:35, Anders Mjos, , , , , , , Problems/Solutions, PLC upgrade 
Wednesday, June 03, 2015, 09:35: TP6 and TP2 off
Wednesday, June 03, 2015, 10:15: Upgrade in progress.
Entry  Monday, June 15, 2015, 14:07, Anders Mjos, , , , , , , Problems/Solutions, Test Stand Source Tray installed Coils_configuration.jpg
Monday, June 15, 2015
Remaining items to do

    ANODE wire not yet attached
    FEBIAD COILS not yet reconfigured


Tuesday, June 16, 2015:
Entry  Monday, June 29, 2015, 16:51, Friedhelm Ames, , , , , , , Problems/Solutions, TSG:BV1B closed 
found TSG:TP1B tripped off. Closed TSG:BV1B as pressure at TSG:iG1 was rising. Pressure is coming down again.

Tuesday, June 30, 2015 by AM
Found the control cable not completely inserted. Inserted cable, which tripped TP1A. Started both turbo pumps again.
Entry  Monday, July 06, 2015, 09:29, Anders Mjos, , , , , , , Problems/Solutions, Replaced out gassing gauge on the backing line 
 
Entry  Tuesday, August 04, 2015, 13:37, Anders Mjos, , , , , , , Problems/Solutions, Equipment for outgassing measurements removed 
 