1042
|
Tuesday, December 17, 2024, 16:09 |
Dave Neilson | | | | | | | Done | Anode,TGHT, TBHT power supply investigation. Resolved | Note, ground and HVC (high voltage
common) are used interchangeably here.
|
|
1043
|
Friday, December 20, 2024, 09:37 |
Dave Neilson | | | | | | | | Winter holiday shutdown | Friday, December 20, 2024, 09:37
turned off all 4 turbopumps. winding
down prior to evacuating. |
|
1044
|
Tuesday, January 07, 2025, 17:06 |
Dave Neilson | | LP-FEBIAD | | | 44692-4 | 42972-10 | In progress | FEBIAD development | Tuesday, January 07, 2025, 16:00
- Target assembly installed in test
stand. electrical connections assessed: |
|
1045
|
Thursday, January 23, 2025, 17:12 |
Dave Neilson | | | | | | | | CATHODE ANODE current leak testing | Recent tests have shown that CATHODE voltage
breaks down at ~130V, continually leaking
current and progressively dropping voltage, |
|
1046
|
Friday, February 28, 2025, 17:16 |
Dave Neilson | | LP-SIS | | | 45447-17 | 42972-2 | In progress | UCx heat shield conditioning | Friday, February 28, 2025, 15:54 : installed
target assembly in test stand
Friday, February 28, 2025, 15:54 |
|
1047
|
Tuesday, March 11, 2025, 14:36 |
Brady Borrmann | | | | | 44691-8 | 44378-2 | In progress | Mass Marker Test Target | Tuesday, March 11, 2025, 14:36 Roughing.
Target installed.
Tuesday, March 11, 2025, 15:06 TP1B |
|
|