  424   Tuesday, February 03, 2015, 09:40 Anders Mjos      Problems/SolutionsRGA installationTuesday, February 03, 2015, 09:40: Venting
RGA installed on the 12" CF
port below the Source Tray.
 2015-02-04-1340.png 
  423   Wednesday, January 28, 2015, 10:40 Anders Mjos      Problems/SolutionsTest Stand shut down for site wide power outage todayFriday, January 30, 2015, 10:50: Optics
section accidentally vented during work on
the ER
  
  422   Wednesday, January 21, 2015, 13:40 Anders Mjos      In progressHV BIAS TestWednesday, January 21, 2015, 13:34: Opened
water flow.
Wednesday, January 21, 2015, 13:42:
  
  421   Tuesday, January 20, 2015, 14:31 Anders Mjos      Problems/SolutionsNe leak disconnected for recallibrationSN 11-231 from VIC   
  420   Monday, January 05, 2015, 09:20 Anders Mjos      Problems/SolutionsIV4 did not get close signal before the HollidaysThe valve closes physically, but does not
receive the closed signal.
Cycled the valve multiple times before
  
  419   Monday, January 05, 2015, 09:06 Anders Mjos      Problems/SolutionsTSG:TP1A found to be timed out after the HollidaysVacuum at 1.7E-7 T
Corrected title from off to timed
out . It seems the controller lost contact
  
  418   Tuesday, December 23, 2014, 09:08 Anders Mjos       Water closed for ChristmasShutting of water supply to the source
box. Water not needed.
  
  417   Monday, December 22, 2014, 11:06 Anders Mjos      Problems/SolutionsCopper rod removedA copper rod - not used was removed from
one of the cooling lines.
  
  416   Thursday, December 18, 2014, 16:38 Anders Mjos      Problems/SolutionsLeak found on service cap F/T Q 9 pin connectorLargest response on the bottom of the insulator.
Thursday, December 18, 2014, 16:39:
Closing pumping valves. Will allow system
 Spark_marks_on_insulator.jpgSpark_marks_on_insulator2.jpg 
  415   Thursday, December 18, 2014, 14:34 Anders Mjos      Problems/SolutionsGE cooling water lines disconnected In preparation for leak check
Thursday, December 18, 2014, 16:37:
Reconnected after leak check
  
  414   Tuesday, December 16, 2014, 10:18 Anders Mjos      Problems/SolutionsTP1B and TP6 stopped/faultpossibly due to HV spark
Tuesday, December 16, 2014, 10:24:
Starting TP1B and TP6
  
  413   Friday, December 12, 2014, 14:09 Anders Mjos LP-FEBIAD  Tube only In progressHV BIAS TestBIAS current limit pot changed from 2.40
to 0.25
EZL current limit pot changed from
 2014-12-17_60_kV_3h.png60_kV_Test.docx 
  412   Friday, December 12, 2014, 13:11 Anders Mjos      Problems/SolutionsHV inspection and cleaningby Ray D and Anders in preparation for
60kV test. Rack insulators and f/t insulators
cleaned with windex
  
  411   Friday, December 12, 2014, 13:11 Anders Mjos      Problems/SolutionsHV inspection and cleaningby Ray D and Anders in preparation for
60kV test. Rack insulators and f/t insulators
cleaned with windex
  
  410   Monday, November 24, 2014, 08:41 Anders Mjos      Problems/SolutionsTSG:RP1 replaced by Edi on Friday Nov 11th   
  409   Monday, November 03, 2014, 14:50 Anders Mjos      Problems/SolutionsIV4 did not close until 4th attemptIndicated with red valve on the EPICS vacuum
page
  
  408   Friday, October 31, 2014, 14:57 Anders Mjos LP-FEBIAD  Tube only38307-9In progressTestFriday, October 31, 2014, 14:47: Starting
turbos
Friday, October 31, 2014, 14:57:
 test20141103.pngtest20141103-2.png 
  407   Monday, October 27, 2014, 09:26 Anders Mjos      Problems/SolutionsTSG:TP1B noisye-fault 7748
Monday, October 27, 2014, 09:21:
Switched off turbos
  
  406   Monday, October 20, 2014, 09:17 Anders Mjos      Problems/SolutionsPower bump this weekend tripped off all turbo pumps Monday, October 20, 2014, 09:17:
Roughing
Monday, October 20, 2014, 09:18 :
  
  405   Tuesday, October 07, 2014, 09:32 Anders Mjos      In progressPumping down empty chamberTuesday, October 07, 2014, 09:30: Roughing
Tuesday, October 07, 2014, 10:24:
Starting turbos
  