209
|
Friday, September 21, 2012, 08:27 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A/B fluctuating | Backing pressures TSG:CG1A/B are fluctuating
between 0.02 and 0.05 since Sept 17th at
~17h. Expected values <0.01. |
|
|
210
|
Monday, September 24, 2012, 10:31 |
Anders Mjos | | | | | | | Problems/Solutions | EPICS whiteout | Test stand was off this morning and
EPICS controls in "white-out".
Controls is looking into it. |
|
|
211
|
Monday, September 24, 2012, 13:52 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 will not start without blowing the fuse | See e-fault 6329
Tried to start the pump from another
power outlet with Edi. No luck. Pump will |
|
|
212
|
Monday, September 24, 2012, 15:25 |
Anders Mjos | | | | | | | Done | TMS RP and TP started | |
|
|
213
|
Tuesday, September 25, 2012, 13:05 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 will not start without blowing the fuse |
|
|
|
214
|
Tuesday, September 25, 2012, 13:25 |
Anders Mjos | | | | | | | Done | Started turbos after replaced roughing pump | |
|
|
215
|
Tuesday, September 25, 2012, 16:10 |
Aurelia Laxdal | | | | | | | | Conditioning - SiC-HP-FEBIAD for operator training | Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A |
|
|
216
|
Thursday, September 27, 2012, 12:27 |
Aurelia Laxdal | | | | | | | In progress | SiC-HP-FEBIAD for operator training | The source was used yesterday for operator
training.
Today, I found the source off: the |
|
|
217
|
Friday, September 28, 2012, 09:59 |
Aurelia Laxdal | | | | | | | In progress | SiC-HP-FEBIAD for operator training - Source Off | Checked with ISAC Ops this morning and
they are not available for FEBIAD training.
Turned off the source until next week. |
|
|
218
|
Monday, October 01, 2012, 10:41 |
Aurelia Laxdal | | HP-FEBIAD | | | | | In progress | SiC-HP-FEBIAD for operator training - Source ON | Turned the source back ON. Heaters are
ramping up. |
|
|
219
|
Wednesday, October 03, 2012, 13:50 |
Aurelia Laxdal | | HP-FEBIAD | | | | | In progress | Training updates | On Monday October 1, the HP-FEBIAD source
was turned ON again, to complete the operator
training. The last session was yesterday |
|
|
220
|
Wednesday, October 10, 2012, 10:47 |
Friedhelm Ames | | | | | | | Failed | found teststand tripped off | turbo pumps in source section and all ion
gauges off all optics and heaters tripped.
Reason unknown. |
|
|
221
|
Wednesday, October 10, 2012, 17:35 |
Aurelia Laxdal | | | | | | | Failed | found teststand tripped off |
|
|
|
222
|
Thursday, October 25, 2012, 11:13 |
Anders Mjos | Test | HP-FEBIAD | | | | | In progress | Venting chamber for installation of TiC#3 | Thursday, October 25, 2012, 11:11: Vacuum
at 1.3E-7 T
Thursday, October 25, 2012, 11:12: |
|
|
223
|
Thursday, October 25, 2012, 13:02 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | In progress | Pumping down | Thursday, October 25, 2012, 13:00: Roughing
Thursday, October 25, 2012, 13:19
: Turbos on |
|
|
224
|
Friday, October 26, 2012, 08:29 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | Done | Target ready for conditioning |
|
|
|
225
|
Thursday, November 01, 2012, 11:16 |
Aurelia Laxdal | TiC#3 | LP-SIS | ITW | TM1 | | | | TiC#3-LP-SIS Startup | Did the HV conditioning for the TiC#3 up
to 30kV.
Heaters ramp up in progress. |
|
|
226
|
Thursday, November 01, 2012, 14:57 |
Aurelia Laxdal | TiC#3 | LP-SIS | ITW | TM1 | | | | TSH:TGHT readback stopped at 264.5A (for a higher setpoint) | The TSH:TGHT stopped at 263.7A, but the
setpoint is still ramping (now at 421A).
The voltage is set correctly: have 6.238V |
|
|
227
|
Friday, November 02, 2012, 14:20 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | | Mass scan done |
Normal
0
false
false
false
|
|
|
228
|
Friday, November 02, 2012, 15:40 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | SiC#3 cooldown started | Started the cooldown for SiC#3. |
|