Tuesday, September 11, 2012, 19:48, Friedhelm Ames, NB#7, HP-SIS, , , , , Done, cool down finished, all source power supplies off.
|
|
Wednesday, September 12, 2012, 08:02, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Venting
|
Wednesday, September 12, 2012, 08:01: Turbos off
Wednesday, September 12, 2012, 13:35: Venting, water off and purged.
Wednesday, September 12, 2012, 13:55: Vented |
Wednesday, September 12, 2012, 17:04, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Pumping down - w/replaced insulators
|
Replaced swollen insulator and added Ta heat shield on insulator.
Wednesday, September 12, 2012, 17:03: Roughing
Wednesday, September 12, 2012, 17:23 : Starting turbos
Wednesday, September 12, 2012, 17:32 : Turbos at speed
Wednesday, September 12, 2012, 17:33 : Vacuum at 3.2E-5 |
Thursday, September 13, 2012, 08:24, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Water on
|
Thursday, September 13, 2012, 08:16: Opened up cooling water. Vacuum (IG1) increased from 5.9E-7 to 6.2E-7 before returning to 5.9E-7. Similar response on IG6 (valve closed). Response is however similar to previous (short time ~5 min) vacuum fluctuations. |
Thursday, September 13, 2012, 13:05, Friedhelm Ames, Nb#7, LP-SIS, , , , , , heater ramping up started
|
|
Friday, September 14, 2012, 15:27, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , Done, Venting
|
Target cooled down. Power supplies off.
Friday, September 14, 2012, 15:27: Turbos off.
Friday, September 14, 2012, 15:32: Water purged.
Friday, September 14, 2012, 16:00: Venting
Friday, September 14, 2012, 16:26: Vented |
Friday, September 14, 2012, 16:33, Anders Mjos, , , , , , , In progress, Pumping down empty chamber
|
Friday, September 14, 2012, 16:33: Roughing
Friday, September 14, 2012, 16:57: Starting turbos
Friday, September 14, 2012, 17:05 : Turbos at speed
Friday, September 14, 2012, 17:07: Vacuum at 8.7E-6
|
Thursday, September 20, 2012, 14:24, Anders Mjos, , , , , , , In progress, Venting - installation of FEBIAD test target for operator training
|
Thursday, September 20, 2012, 14:24: Turbos off
Thursday, September 20, 2012, 15:20: Venting |
Thursday, September 20, 2012, 15:52, Anders Mjos, TEST SiC, HP-FEBIAD, , , , , In progress, Installilng SiC-HP-FEBIAD target for operator training
|
Thursday, September 20, 2012, 15:50: Roughing
Thursday, September 20, 2012, 15:54: Aborting. VCR for gas line not connected.
Thursday, September 20, 2012, 16:09: Roughing
Thursday, September 20, 2012, 16:29: Starting turbos
Thursday, September 20, 2012, 16:38 : Turbos at speed
Thursday, September 20, 2012, 16:39 : Vacuum at 1.3E-5 torr
|
Friday, September 21, 2012, 08:20, Anders Mjos, TEST SiC, HP-FEBIAD, , , , , In progress, Installilng SiC-HP-FEBIAD target for operator training
|
Anders Mjos wrote: |
Thursday, September 20, 2012, 15:50: Roughing
Thursday, September 20, 2012, 15:54: Aborting. VCR for gas line not connected.
Thursday, September 20, 2012, 16:09: Roughing
Thursday, September 20, 2012, 16:29: Starting turbos
Thursday, September 20, 2012, 16:38 : Turbos at speed
Thursday, September 20, 2012, 16:39 : Vacuum at 1.3E-5 torr
|
Friday, September 21, 2012, 08:19: Cooling water on. Vacuum stable at 2.3E-7 torr. |
Friday, September 21, 2012, 08:27, Anders Mjos, , , , , , , Problems/Solutions, Backing pressure TSG:CG1A/B fluctuating
|
Backing pressures TSG:CG1A/B are fluctuating between 0.02 and 0.05 since Sept 17th at ~17h. Expected values <0.01. |
Monday, September 24, 2012, 10:31, Anders Mjos, , , , , , , Problems/Solutions, EPICS whiteout
|
Test stand was off this morning and EPICS controls in "white-out". Controls is looking into it.
Update 13:51:
Controls have reestablished contact with the PLC. |
Monday, September 24, 2012, 13:52, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 will not start without blowing the fuse
|
See e-fault 6329
Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow. |
Monday, September 24, 2012, 15:25, Anders Mjos, , , , , , , Done, TMS RP and TP started
|
|
Tuesday, September 25, 2012, 13:05, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 will not start without blowing the fuse
|
Anders Mjos wrote: |
See e-fault 6329
Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow.
|
Pump replaced by vacuum group |
Tuesday, September 25, 2012, 13:25, Anders Mjos, , , , , , , Done, Started turbos after replaced roughing pump
|
|
Tuesday, September 25, 2012, 16:10, Aurelia Laxdal, , , , , , , , Conditioning - SiC-HP-FEBIAD for operator training
|
Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A
for TSH:TBHT up to 230A |
Thursday, September 27, 2012, 12:27, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training
|
The source was used yesterday for operator training.
Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source. |
Friday, September 28, 2012, 09:59, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training - Source Off
|
Checked with ISAC Ops this morning and they are not available for FEBIAD training. Turned off the source until next week. |
Monday, October 01, 2012, 10:41, Aurelia Laxdal, , HP-FEBIAD, , , , , In progress, SiC-HP-FEBIAD for operator training - Source ON
|
Turned the source back ON. Heaters are ramping up. |
|