199
|
Tuesday, September 11, 2012, 19:48 |
Friedhelm Ames | NB#7 | HP-SIS | | | | | Done | cool down finished, all source power supplies off. | |
|
200
|
Wednesday, September 12, 2012, 08:02 |
Anders Mjos | Nb#7 | LP-SIS | ITW | TM1 | | | In progress | Venting | Wednesday, September 12, 2012, 08:01: Turbos
off
Wednesday, September 12, 2012, 13:35: |
|
201
|
Wednesday, September 12, 2012, 17:04 |
Anders Mjos | Nb#7 | LP-SIS | ITW | TM1 | | | In progress | Pumping down - w/replaced insulators | Replaced swollen insulator and added Ta
heat shield on insulator.
|
|
202
|
Thursday, September 13, 2012, 08:24 |
Anders Mjos | Nb#7 | LP-SIS | ITW | TM1 | | | In progress | Water on | Thursday, September 13, 2012, 08:16: Opened
up cooling water. Vacuum (IG1) increased
from 5.9E-7 to 6.2E-7 before returning to |
|
203
|
Thursday, September 13, 2012, 13:05 |
Friedhelm Ames | Nb#7 | LP-SIS | | | | | | heater ramping up started | |
|
204
|
Friday, September 14, 2012, 15:27 |
Anders Mjos | Nb#7 | LP-SIS | ITW | TM1 | | | Done | Venting | Target cooled down. Power supplies off.
Friday, September 14, 2012, 15:27:
Turbos off. |
|
205
|
Friday, September 14, 2012, 16:33 |
Anders Mjos | | | | | | | In progress | Pumping down empty chamber | Friday, September 14, 2012, 16:33: Roughing
Friday, September 14, 2012, 16:57:
Starting turbos |
|
206
|
Thursday, September 20, 2012, 14:24 |
Anders Mjos | | | | | | | In progress | Venting - installation of FEBIAD test target for operator training | Thursday, September 20, 2012, 14:24: Turbos
off
Thursday, September 20, 2012, 15:20: |
|
207
|
Thursday, September 20, 2012, 15:52 |
Anders Mjos | TEST SiC | HP-FEBIAD | | | | | In progress | Installilng SiC-HP-FEBIAD target for operator training | Thursday, September 20, 2012, 15:50: Roughing
Thursday, September 20, 2012, 15:54:
Aborting. VCR for gas line not connected. |
|
208
|
Friday, September 21, 2012, 08:20 |
Anders Mjos | TEST SiC | HP-FEBIAD | | | | | In progress | Installilng SiC-HP-FEBIAD target for operator training |
|
|
209
|
Friday, September 21, 2012, 08:27 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A/B fluctuating | Backing pressures TSG:CG1A/B are fluctuating
between 0.02 and 0.05 since Sept 17th at
~17h. Expected values <0.01. |
|
210
|
Monday, September 24, 2012, 10:31 |
Anders Mjos | | | | | | | Problems/Solutions | EPICS whiteout | Test stand was off this morning and
EPICS controls in "white-out".
Controls is looking into it. |
|
211
|
Monday, September 24, 2012, 13:52 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 will not start without blowing the fuse | See e-fault 6329
Tried to start the pump from another
power outlet with Edi. No luck. Pump will |
|
212
|
Monday, September 24, 2012, 15:25 |
Anders Mjos | | | | | | | Done | TMS RP and TP started | |
|
213
|
Tuesday, September 25, 2012, 13:05 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 will not start without blowing the fuse |
|
|
214
|
Tuesday, September 25, 2012, 13:25 |
Anders Mjos | | | | | | | Done | Started turbos after replaced roughing pump | |
|
215
|
Tuesday, September 25, 2012, 16:10 |
Aurelia Laxdal | | | | | | | | Conditioning - SiC-HP-FEBIAD for operator training | Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A |
|
216
|
Thursday, September 27, 2012, 12:27 |
Aurelia Laxdal | | | | | | | In progress | SiC-HP-FEBIAD for operator training | The source was used yesterday for operator
training.
Today, I found the source off: the |
|
217
|
Friday, September 28, 2012, 09:59 |
Aurelia Laxdal | | | | | | | In progress | SiC-HP-FEBIAD for operator training - Source Off | Checked with ISAC Ops this morning and
they are not available for FEBIAD training.
Turned off the source until next week. |
|
218
|
Monday, October 01, 2012, 10:41 |
Aurelia Laxdal | | HP-FEBIAD | | | | | In progress | SiC-HP-FEBIAD for operator training - Source ON | Turned the source back ON. Heaters are
ramping up. |
|