Friday, September 21, 2012, 08:27, Anders Mjos, , , , , , , Problems/Solutions, Backing pressure TSG:CG1A/B fluctuating
|
Backing pressures TSG:CG1A/B are fluctuating between 0.02 and 0.05 since Sept 17th at ~17h. Expected values <0.01. |
Monday, September 24, 2012, 10:31, Anders Mjos, , , , , , , Problems/Solutions, EPICS whiteout
|
Test stand was off this morning and EPICS controls in "white-out". Controls is looking into it.
Update 13:51:
Controls have reestablished contact with the PLC. |
Monday, September 24, 2012, 13:52, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 will not start without blowing the fuse
|
See e-fault 6329
Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow. |
Monday, September 24, 2012, 15:25, Anders Mjos, , , , , , , Done, TMS RP and TP started
|
|
Tuesday, September 25, 2012, 13:05, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 will not start without blowing the fuse
|
Anders Mjos wrote:
See e-fault 6329 |
Tuesday, September 25, 2012, 13:25, Anders Mjos, , , , , , , Done, Started turbos after replaced roughing pump
|
|
Tuesday, September 25, 2012, 16:10, Aurelia Laxdal, , , , , , , , Conditioning - SiC-HP-FEBIAD for operator training
|
Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A |
Thursday, September 27, 2012, 12:27, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training
|
The source was used yesterday for operator training.
Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source. |
Friday, September 28, 2012, 09:59, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training - Source Off
|
Checked with ISAC Ops this morning and they are not available for FEBIAD training. Turned off the source until next week. |
Monday, October 01, 2012, 10:41, Aurelia Laxdal, , HP-FEBIAD, , , , , In progress, SiC-HP-FEBIAD for operator training - Source ON
|
Turned the source back ON. Heaters are ramping up. |
Wednesday, October 03, 2012, 13:50, Aurelia Laxdal, , HP-FEBIAD, , , , , In progress, Training updates
|
On Monday October 1, the HP-FEBIAD source was turned ON again, to complete the operator training. The last session was yesterday and for the time being
the ISAC operators can play with the source when time allows, and from the ISAC Control room. For this purpose the source will be kept on this week and
also over the week-end. |
Wednesday, October 10, 2012, 10:47, Friedhelm Ames, , , , , , , Failed, found teststand tripped off
|
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown. |
Wednesday, October 10, 2012, 17:35, Aurelia Laxdal, , , , , , , Failed, found teststand tripped off
|
Friedhelm Ames wrote:
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown. |
Thursday, October 25, 2012, 11:13, Anders Mjos, Test, HP-FEBIAD, , , , , In progress, Venting chamber for installation of TiC#3
|
Thursday, October 25, 2012, 11:11: Vacuum at 1.3E-7 T
Thursday, October 25, 2012, 11:12: Turbos off
Thursday, October 25, 2012, 11:50: Venting |
Thursday, October 25, 2012, 13:02, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , In progress, Pumping down
|
Thursday, October 25, 2012, 13:00: Roughing
Thursday, October 25, 2012, 13:19 : Turbos on
Thursday, October 25, 2012, 13:28 : Turbos at speed |
Friday, October 26, 2012, 08:29, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , Done, Target ready for conditioning
|
Anders Mjos wrote:
Thursday, October 25, 2012, 13:00: Roughing |
Thursday, November 01, 2012, 11:16, Aurelia Laxdal, TiC#3, LP-SIS, ITW, TM1, , , , TiC#3-LP-SIS Startup
|
Did the HV conditioning for the TiC#3 up to 30kV.
Heaters ramp up in progress. |
Thursday, November 01, 2012, 14:57, Aurelia Laxdal, TiC#3, LP-SIS, ITW, TM1, , , , TSH:TGHT readback stopped at 264.5A (for a higher setpoint)
|
The TSH:TGHT stopped at 263.7A, but the setpoint is still ramping (now at 421A). The voltage is set correctly: have 6.238V setpoint and 4.386V readback.
The reading on the Power Supply shows 418A. Through the window the target assembly looks at high temperature. The readback on Epics seems stuck.
Normal
0
|
Friday, November 02, 2012, 14:20, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , , Mass scan done
|
Normal
0
false
false
false
EN-US
X-NONE
X-NONE
|
Friday, November 02, 2012, 15:40, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , Done, SiC#3 cooldown started
|
Started the cooldown for SiC#3. |
|