ID Date Author Target/No.# Source Station Module Target Oven W.O#down Heat Shield W.O# Status Subject
  209   Friday, September 21, 2012, 08:27 Anders Mjos      Problems/SolutionsBacking pressure TSG:CG1A/B fluctuating

Backing pressures TSG:CG1A/B are fluctuating between 0.02 and 0.05 since Sept 17th at ~17h. Expected values <0.01.

  210   Monday, September 24, 2012, 10:31 Anders Mjos      Problems/SolutionsEPICS whiteout

 Test stand was off this morning and EPICS controls in "white-out". Controls is looking into it.

Update  13:51:

Controls have reestablished contact with the PLC.

  211   Monday, September 24, 2012, 13:52 Anders Mjos      Problems/SolutionsTSG:RP1 will not start without blowing the fuse

See e-fault 6329

Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow.

  212   Monday, September 24, 2012, 15:25 Anders Mjos      DoneTMS RP and TP started
  213   Tuesday, September 25, 2012, 13:05 Anders Mjos      Problems/SolutionsTSG:RP1 will not start without blowing the fuse

Anders Mjos wrote:

See e-fault 6329

Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow.

 Pump replaced by vacuum group

  214   Tuesday, September 25, 2012, 13:25 Anders Mjos      DoneStarted turbos after replaced roughing pump
  215   Tuesday, September 25, 2012, 16:10 Aurelia Laxdal       Conditioning - SiC-HP-FEBIAD for operator training

Did the HV conditioning up to 30kV.

Started the heaters conditioning:

for TSH:TGHT up to 580A

for TSH:TBHT up to 230A

  216   Thursday, September 27, 2012, 12:27 Aurelia Laxdal      In progressSiC-HP-FEBIAD for operator training

The source was used yesterday for operator training.

Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source.

  217   Friday, September 28, 2012, 09:59 Aurelia Laxdal      In progressSiC-HP-FEBIAD for operator training - Source Off

Checked with ISAC Ops this morning and they are not available for FEBIAD training. Turned off the source until next week.

  218   Monday, October 01, 2012, 10:41 Aurelia Laxdal HP-FEBIAD    In progressSiC-HP-FEBIAD for operator training - Source ON

Turned the source back ON. Heaters are ramping up.

  219   Wednesday, October 03, 2012, 13:50 Aurelia Laxdal HP-FEBIAD    In progressTraining updates

On Monday October 1, the HP-FEBIAD source was turned ON again, to complete the operator training. The last session was yesterday and for the time being the ISAC operators can play with the source when time allows, and from the ISAC Control room. For this purpose the source will be kept on this week and also over the week-end.

  220   Wednesday, October 10, 2012, 10:47 Friedhelm Ames      Failedfound teststand tripped off

turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.

  221   Wednesday, October 10, 2012, 17:35 Aurelia Laxdal      Failedfound teststand tripped off

Friedhelm Ames wrote:

turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.

 Checked the Archiver and the striptool: TSG:TP1A & TP1B tripped on Oct. 10, at 7:53am. Both pumps showed timeout, but the AC breakers were not tripped. Also, checked with MCR: they were no power bumps or cooling water problems around that time. 

Discussed it with Kazuya Negishi from Controls: there were no PLC problems. Kazuya and I would monitor the trips. 

  222   Thursday, October 25, 2012, 11:13 Anders MjosTestHP-FEBIAD    In progressVenting chamber for installation of TiC#3

Thursday, October 25, 2012, 11:11: Vacuum at 1.3E-7 T

Thursday, October 25, 2012, 11:12: Turbos off

Thursday, October 25, 2012, 11:50: Venting

  223   Thursday, October 25, 2012, 13:02 Anders MjosTiC#3LP-SISITWTM1  In progressPumping down

Thursday, October 25, 2012, 13:00: Roughing

Thursday, October 25, 2012, 13:19 : Turbos on

Thursday, October 25, 2012, 13:28 : Turbos at speed

Thursday, October 25, 2012, 13:29 : Vacuum at 1.6E-5 T

  224   Friday, October 26, 2012, 08:29 Anders MjosTiC#3LP-SISITWTM1  DoneTarget ready for conditioning

Anders Mjos wrote:

Thursday, October 25, 2012, 13:00: Roughing

Thursday, October 25, 2012, 13:19 : Turbos on

Thursday, October 25, 2012, 13:28 : Turbos at speed

Thursday, October 25, 2012, 13:29 : Vacuum at 1.6E-5 T

 Friday, October 26, 2012, 08:29: Opened water. Vacuum stable at 1.8E-7 T

  225   Thursday, November 01, 2012, 11:16 Aurelia LaxdalTiC#3LP-SISITWTM1   TiC#3-LP-SIS Startup

Did the HV conditioning for the TiC#3 up to 30kV.

Heaters ramp up in progress.

  226   Thursday, November 01, 2012, 14:57 Aurelia LaxdalTiC#3LP-SISITWTM1   TSH:TGHT readback stopped at 264.5A (for a higher setpoint)

The TSH:TGHT stopped at 263.7A, but the setpoint is still ramping (now at 421A). The voltage is set correctly: have 6.238V setpoint and 4.386V readback. The reading on the Power Supply shows 418A. Through the window the target assembly looks at high temperature. The readback on Epics seems stuck. E-Fault for Controls 6389

  227   Friday, November 02, 2012, 14:20 Aurelia Laxdal LP-SISITWTM1   Mass scan done

Mass scan file: plotdump-local-clean.txt Nov2 12 13-15-59.txt

The scan was taken at TGHT=573A (read from the PS panel) .

The TBHT = 230A

  228   Friday, November 02, 2012, 15:40 Aurelia Laxdal LP-SISITWTM1  DoneSiC#3 cooldown started

Started the cooldown for SiC#3.