190
|
Friday, August 31, 2012, 11:12 |
Aurelia Laxdal | | HP-FEBIAD | ITE | TM4 | | | Done | Finished testing NiO#1 |
Turned off the HV and the optics in the first section. Couldn't turn off the optics in the second section: left a message for Evgeniy.
Also TMS:RP2 is very noisy. Talked to Edi D. from vacuum group. He would work on it this afternoon. E-Fault#6282 |
|
205
|
Friday, September 14, 2012, 16:33 |
Anders Mjos | | | | | | | In progress | Pumping down empty chamber |
Friday, September 14, 2012, 16:33: Roughing
Friday, September 14, 2012, 16:57: Starting turbos
Friday, September 14, 2012, 17:05 : Turbos at speed
Friday, September 14, 2012, 17:07: Vacuum at 8.7E-6
|
|
206
|
Thursday, September 20, 2012, 14:24 |
Anders Mjos | | | | | | | In progress | Venting - installation of FEBIAD test target for operator training |
Thursday, September 20, 2012, 14:24: Turbos off
Thursday, September 20, 2012, 15:20: Venting |
|
209
|
Friday, September 21, 2012, 08:27 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A/B fluctuating |
Backing pressures TSG:CG1A/B are fluctuating between 0.02 and 0.05 since Sept 17th at ~17h. Expected values <0.01. |
|
210
|
Monday, September 24, 2012, 10:31 |
Anders Mjos | | | | | | | Problems/Solutions | EPICS whiteout |
Test stand was off this morning and EPICS controls in "white-out". Controls is looking into it.
Update 13:51:
Controls have reestablished contact with the PLC. |
|
211
|
Monday, September 24, 2012, 13:52 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 will not start without blowing the fuse |
See e-fault 6329
Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow. |
|
212
|
Monday, September 24, 2012, 15:25 |
Anders Mjos | | | | | | | Done | TMS RP and TP started |
|
|
213
|
Tuesday, September 25, 2012, 13:05 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 will not start without blowing the fuse |
Anders Mjos wrote: |
See e-fault 6329
Tried to start the pump from another power outlet with Edi. No luck. Pump will be replaced tomorrow.
|
Pump replaced by vacuum group |
|
214
|
Tuesday, September 25, 2012, 13:25 |
Anders Mjos | | | | | | | Done | Started turbos after replaced roughing pump |
|
|
215
|
Tuesday, September 25, 2012, 16:10 |
Aurelia Laxdal | | | | | | | | Conditioning - SiC-HP-FEBIAD for operator training |
Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A
for TSH:TBHT up to 230A |
|
216
|
Thursday, September 27, 2012, 12:27 |
Aurelia Laxdal | | | | | | | In progress | SiC-HP-FEBIAD for operator training |
The source was used yesterday for operator training.
Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source. |
|
217
|
Friday, September 28, 2012, 09:59 |
Aurelia Laxdal | | | | | | | In progress | SiC-HP-FEBIAD for operator training - Source Off |
Checked with ISAC Ops this morning and they are not available for FEBIAD training. Turned off the source until next week. |
|
218
|
Monday, October 01, 2012, 10:41 |
Aurelia Laxdal | | HP-FEBIAD | | | | | In progress | SiC-HP-FEBIAD for operator training - Source ON |
Turned the source back ON. Heaters are ramping up. |
|
219
|
Wednesday, October 03, 2012, 13:50 |
Aurelia Laxdal | | HP-FEBIAD | | | | | In progress | Training updates |
On Monday October 1, the HP-FEBIAD source was turned ON again, to complete the operator training. The last session was yesterday and for the time being the ISAC operators can play with the source when time allows, and from the ISAC Control room. For this purpose the source will be kept on this week and also over the week-end. |
|
220
|
Wednesday, October 10, 2012, 10:47 |
Friedhelm Ames | | | | | | | Failed | found teststand tripped off |
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown. |
|
221
|
Wednesday, October 10, 2012, 17:35 |
Aurelia Laxdal | | | | | | | Failed | found teststand tripped off |
Friedhelm Ames wrote: |
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.
|
Checked the Archiver and the striptool: TSG:TP1A & TP1B tripped on Oct. 10, at 7:53am. Both pumps showed timeout, but the AC breakers were not tripped. Also, checked with MCR: they were no power bumps or cooling water problems around that time.
Discussed it with Kazuya Negishi from Controls: there were no PLC problems. Kazuya and I would monitor the trips. |
|
227
|
Friday, November 02, 2012, 14:20 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | | Mass scan done |
Mass scan file: plotdump-local-clean.txt Nov2 12 13-15-59.txt
The scan was taken at TGHT=573A (read from the PS panel) .
The TBHT = 230A
|
|
228
|
Friday, November 02, 2012, 15:40 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | SiC#3 cooldown started |
Started the cooldown for SiC#3. |
|
229
|
Monday, November 05, 2012, 09:47 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | TPS optics cannot be turned off. |
All TPS optics, with the exception of TPS:Q4 cannot be turned off. E-Fault#6395 for Controls.
Same for the TSG optics: CB1, VCB1 and CBC.
Talked to Evgeniy and Kazuya. Optics are OFF now. |
|
230
|
Monday, November 05, 2012, 13:26 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | Venting the Test Stand |
Venting the Test Stand.
TiC#3 will be ready to be removed in few minutes.
Please note: water is still ON. |