Entry  Tuesday, May 15, 2012, 09:46, Rick Maharaj, , , , , , , , target reinstalled pumping started 
 
Entry  Wednesday, May 16, 2012, 16:01, Anders Mjos, , , , , , , Problems/Solutions, Loose chip of insulator material detected Ceramic_Chip.pdf
 A chip of insulator material was detected below the lower target insulator stand-off (attachment - left picture). The chip may come from the tube
heater insulator above (attachment - right picture). The chip will be further investigated when the target is removed.
Entry  Wednesday, May 16, 2012, 18:10, Aurelia Laxdal, , , ITE, TM4, , , , SiC#27 cooling down 
Today: did a mass scan at 580A on TGHT and 230A on TBHT at 30kV. Found some A/q units discrepancies on the mass scan page. It may be a hall probe problem: 
under investigations.
Uploaded the testing file on Docushare: http://documents.triumf.ca/docushare/dsweb/View/Collection-8539/Document-56575
Entry  Wednesday, May 16, 2012, 19:55, Friedhelm Ames, , , , , , , Problems/Solutions, Hall probe reading wrong 
During the mass scan today it was discovered, that the mass calibration was off. Further investigation showed, that the Hall probe readings are a factor
of 1.31 lower than during previous measurements. A fault report has been issued to controls.
Entry  Thursday, May 17, 2012, 15:14, Anders Mjos, , , , , , , , Pumping down empty chamber 
Thursday, May 17, 2012, 15:14: Started roughing. Cooling lines blanked off.
Thursday, May 17, 2012, 16:52: Starting turbos.
Thursday, May 17, 2012, 17:00: Turbos at speed. Vacuum at 1.5E-5.
Entry  Thursday, May 31, 2012, 14:46, Anders Mjos, , , , , , , , Venting in preparation for Ta#38 
Thursday, May 31, 2012, 14:46: Switching off turbos
Thursday, May 31, 2012, 15:05: Venting
Entry  Monday, June 04, 2012, 11:40, Anders Mjos, , , , , , , In progress, Empty chamber 
HS water lines blanked.
Monday, June 04, 2012, 11:40: Roughing.
Monday, June 04, 2012, 11:58: Starting turbos. 
    Reply  Tuesday, June 26, 2012, 16:06, Anders Mjos, , , , , , , Done, Vented 


    
        
            Anders Mjos wrote:
        
        
            
            HS water lines blanked.
Entry  Tuesday, June 26, 2012, 18:04, Anders Mjos, FEBIAD anode end cap test, , , , Tube only, 38307-9, In progress, FEBIAD anode end cap test - ready 
Testing FEBIAD anode end cap as per dwg ITD0304 REV C
Target with TUBE ONLY. Do not use target heater.

Tuesday, June 26, 2012, 18:03: Roughing
Entry  Tuesday, June 26, 2012, 18:30, Anders Mjos, , , , , , , Problems/Solutions, Crack in source tray insulator Cracked_insulator.pdf
 A crack in the insulator ITD0054 was observed while mounting the target assembly. See attachment.
Entry  Friday, June 29, 2012, 13:39, Friedhelm Ames, , , , , , , , start mass scan 
start mass scan to do new mass calibration
Entry  Friday, June 29, 2012, 15:02, Friedhelm Ames, , , , , , , , mass scan finished mass_spectrum_2012_06_29.PNG
mass spectrum saved as
plotdump-local-clean.txt_Jun29_12_14-55-43.txt


Entry  Friday, June 29, 2012, 15:03, Friedhelm Ames, , , , , , , , start ramping down heater 
 
    Reply  Friday, June 29, 2012, 16:39, Friedhelm Ames, , , , , , , , mass scan finished 


    
        
            Friedhelm Ames wrote:
        
        
            
            mass spectrum saved as
Entry  Tuesday, July 03, 2012, 09:23, Friedhelm Ames, , , , , , , In progress, start up again 
purged Ne line and started cathode heater ramp up to 295 A
Entry  Tuesday, July 03, 2012, 19:05, Friedhelm Ames, , , , , , , Problems/Solutions, short in anode 
A short in the anode has developed during the heater ramp up. Increasing the current limit did not cure it. Start heater ramp down to investigate.
Entry  Wednesday, July 04, 2012, 09:22, Friedhelm Ames, , , , , , , Problems/Solutions, turbo pumps stopped 
turbo pumps stopped to prepare for venting for anode short investigation.
    Reply  Wednesday, July 04, 2012, 13:07, Anders Mjos, , , , , , , Problems/Solutions, water lines purged 


    
        
            Friedhelm Ames wrote:
        
        
            
            turbo pumps stopped to prepare for venting for anode short investigation.
    Reply  Wednesday, July 04, 2012, 15:33, Anders Mjos, , , , , , , Problems/Solutions, short in anode photo_1.JPGphoto_3.JPG


    
        
            Friedhelm Ames wrote:
        
        
            
            A short in the anode has developed during the heater ramp up. Increasing the current limit did not cure it. Start heater
Entry  Wednesday, July 04, 2012, 15:37, Anders Mjos, FEBIAD anode end cap test, , , , , , In progress, Pumping down  photo_8.jpg
Replaced grid containing ring (target side) with new ring. No contact between target and anode measured in lab.
NOTE: While closing up the VCR fittings the tube rotated causing the tube to flatten in a bend. This may reduce water flow on the heat shield circuit.
(see attachment)