ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
11
|
Friday, September 23, 2011, 16:42 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | Target ready to be heated | Friday, September 23, 2011, 16:4: Target
installed and roughing started.
Friday, September 23, 2011, 17:12: |
|
15
|
Wednesday, September 28, 2011, 16:33 |
Aurelia Laxdal | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | HV conditioning | Started the HV conditioning: TSG:BIAS=30kV |
|
16
|
Thursday, September 29, 2011, 09:27 |
Aurelia Laxdal | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | Heaters conditioning | Started the heaters conditioning: TGHT
up to 580A and TBHT up to 230A. |
|
35
|
Monday, February 27, 2012, 17:39 |
Friedhelm Ames | | | | | | | In progress | target and tube heaters ramped up | ramping up target to 300 A and tube to
270 A |
|
36
|
Tuesday, February 28, 2012, 10:29 |
Pierre Bricault | | LP-FEBIAD | | | | | In progress | Test FEBIAD at ISAC test statnd | |
|
66
|
Friday, March 09, 2012, 08:53 |
Friedhelm Ames | Nb#6 | | | | | | In progress | mass scan started | mass scan started again. Total current
3.2e-8 A |
|
72
|
Monday, April 16, 2012, 11:16 |
Anders Mjos | Nb#6 | LP-SIS | ITW | TM1 | | | In progress | Venting, purging cooling lines | Venting chamber and purging cooling lines
in preparation for target removal |
|
73
|
Monday, April 16, 2012, 11:56 |
Anders Mjos | Nb#6 | LP-SIS | ITW | TM1 | | | In progress | Venting, purging cooling lines |
|
|
76
|
Wednesday, April 18, 2012, 13:10 |
Anders Mjos | No target | | | | | | In progress | Pumping down empty vacuum chamber | Wednesday, April 18, 2012, 13:10: Roughing
the vacuum chamber.
Wednesday, April 18, 2012, 13:34 |
|
85
|
Tuesday, May 15, 2012, 07:39 |
Rick Maharaj | Sic #27 | HP-SIS | ITE | TM4 | | | In progress | Water on at test stand | The vacuum on TSGIG1 reads 2.85e-07. Turing
on water on teststand and observing any changes
in vacuum pressure. |
|
91
|
Tuesday, May 15, 2012, 10:14 |
Anders Mjos | SiC#27 | HP-SIS | ITE | TM4 | | | In progress | target ready to be heated and biased | Tuesday, May 15, 2012, 10:13: Turbo
pumps at speed. Vacuum at 1.4E-5.
Tuesday, May 15, 2012, 12:03: Cooling |
|
92
|
Tuesday, May 15, 2012, 16:18 |
Aurelia Laxdal | SiC#27 | HP-SIS | ITE | TM4 | | | In progress | Target/Ion source conditioning | Did the HV conditioning up to 30kV and
started to ramp up the heaters to 580A and
230A. |
|
101
|
Thursday, May 31, 2012, 15:43 |
Anders Mjos | Ta#38 | LP-SIS | ITW | TM1 | | | In progress | Target ready to be heated | Thursday, May 31, 2012, 15:42: Roughing
Thursday, May 31, 2012, 16:01 : Starting
turbos |
|
102
|
Friday, June 01, 2012, 12:23 |
Aurelia Laxdal | Ta#38 | LP-SIS | ITW | TM1 | | | In progress | HV & Heaters conditioning. | Did the HV conditioning.
Heaters conditioning in progress.
The Hall probe is not working: couldn't |
|
104
|
Monday, June 04, 2012, 11:40 |
Anders Mjos | | | | | | | In progress | Empty chamber | HS water lines blanked.
Monday, June 04, 2012, 11:40: Roughing.
Monday, June 04, 2012, 11:58: Starting |
|
106
|
Tuesday, June 26, 2012, 18:04 |
Anders Mjos | FEBIAD anode end cap test | | | | Tube only | 38307-9 | In progress | FEBIAD anode end cap test - ready | Testing FEBIAD anode end cap as per dwg
ITD0304 REV C
Target with TUBE ONLY. Do not use |
|
108
|
Thursday, June 28, 2012, 11:04 |
Pierre Bricault | Test FEBIAD | LP-FEBIAD | | | | | In progress | Ready to bias the high voltage. | |
|
110
|
Thursday, June 28, 2012, 11:19 |
Pierre Bricault | | LP-FEBIAD | | | | | In progress | Cathode ramping to 230 A in progress | |
|
111
|
Thursday, June 28, 2012, 11:27 |
Pierre Bricault | | LP-FEBIAD | | | | | In progress | Cathode heating in progress, pressure 8.3e-7 T | |
|
112
|
Thursday, June 28, 2012, 11:29 |
Pierre Bricault | | LP-FEBIAD | | | | | In progress | Lost all cnntrol interface, complete whiteout of the epics system. | |
|