Entry  Friday, September 23, 2011, 16:42, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, Target ready to be heated 
Friday, September 23, 2011, 16:4: Target installed and roughing started.
Friday, September 23, 2011, 17:12: Started turbo pumps. 
Monday, September 26, 2011, 09:00: Opened up water flow. Vacuum rose from 3e-6 to 3e-5 torr in 30 s. Closed water flow.
Entry  Wednesday, September 28, 2011, 16:33, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, HV conditioning 
Started the HV conditioning: TSG:BIAS=30kV
Entry  Thursday, September 29, 2011, 09:27, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, Heaters conditioning 
Started the heaters conditioning: TGHT up to 580A and TBHT up to 230A.
Entry  Monday, February 27, 2012, 17:39, Friedhelm Ames, , , , , , , In progress, target and tube heaters ramped up 
ramping up target to 300 A and tube to 270 A
Entry  Tuesday, February 28, 2012, 10:29, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Test FEBIAD at ISAC test statnd 
 
Entry  Friday, March 09, 2012, 08:53, Friedhelm Ames, Nb#6, , , , , , In progress, mass scan started 
mass scan started again. Total current 3.2e-8 A
Entry  Monday, April 16, 2012, 11:16, Anders Mjos, Nb#6, LP-SIS, ITW, TM1, , , In progress, Venting, purging cooling lines 
Venting chamber and purging cooling lines in preparation for target removal
    Reply  Monday, April 16, 2012, 11:56, Anders Mjos, Nb#6, LP-SIS, ITW, TM1, , , In progress, Venting, purging cooling lines 


    
        
            Anders Mjos wrote:
        
        
            
            Venting chamber and purging cooling lines in preparation for target removal
Entry  Wednesday, April 18, 2012, 13:10, Anders Mjos, No target, , , , , , In progress, Pumping down empty vacuum chamber 
Wednesday, April 18, 2012, 13:10: Roughing the vacuum chamber.
Wednesday, April 18, 2012, 13:34 : Turbo pumps started and at speed. Pressure 3.5 E-5 torr
Entry  Tuesday, May 15, 2012, 07:39, Rick Maharaj, Sic #27, HP-SIS, ITE, TM4, , , In progress, Water on at test stand 
The vacuum on TSGIG1 reads 2.85e-07. Turing on water on teststand and observing any changes in vacuum pressure.
    Reply  Tuesday, May 15, 2012, 10:14, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , In progress, target ready to be heated and biased 
 Tuesday, May 15, 2012, 10:13: Turbo pumps at speed. Vacuum at 1.4E-5.
Tuesday, May 15, 2012, 12:03: Cooling lines opened. Vacuum stable at 1.6E-6
Tuesday, May 15, 2012, 12:17: Target ready to be heated and biased.
Entry  Tuesday, May 15, 2012, 16:18, Aurelia Laxdal, SiC#27, HP-SIS, ITE, TM4, , , In progress, Target/Ion source conditioning 
Did the HV conditioning up to 30kV and started to ramp up the heaters to 580A and 230A.
Entry  Thursday, May 31, 2012, 15:43, Anders Mjos, Ta#38, LP-SIS, ITW, TM1, , , In progress, Target ready to be heated 
Thursday, May 31, 2012, 15:42: Roughing
Thursday, May 31, 2012, 16:01 : Starting turbos
Thursday, May 31, 2012, 16:08 : Turbos at speed. Vacuum 1.7 E-5
Entry  Friday, June 01, 2012, 12:23, Aurelia Laxdal, Ta#38, LP-SIS, ITW, TM1, , , In progress, HV & Heaters conditioning. 
Did the HV conditioning.
Heaters conditioning in progress.
The Hall probe is not working: couldn't pass 35.5 units (readback) or 50.16 units (setpoint) at field -3710G.
Entry  Monday, June 04, 2012, 11:40, Anders Mjos, , , , , , , In progress, Empty chamber 
HS water lines blanked.
Monday, June 04, 2012, 11:40: Roughing.
Monday, June 04, 2012, 11:58: Starting turbos. 
Entry  Tuesday, June 26, 2012, 18:04, Anders Mjos, FEBIAD anode end cap test, , , , Tube only, 38307-9, In progress, FEBIAD anode end cap test - ready 
Testing FEBIAD anode end cap as per dwg ITD0304 REV C
Target with TUBE ONLY. Do not use target heater.

Tuesday, June 26, 2012, 18:03: Roughing
Entry  Thursday, June 28, 2012, 11:04, Pierre Bricault, Test FEBIAD, LP-FEBIAD, , , , , In progress, Ready to bias the high voltage. 
 
Entry  Thursday, June 28, 2012, 11:19, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Cathode ramping to 230 A in progress 
 
Entry  Thursday, June 28, 2012, 11:27, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Cathode heating in progress, pressure 8.3e-7 T 
 
Entry  Thursday, June 28, 2012, 11:29, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Lost all cnntrol interface, complete whiteout of the epics system. 
 