  135   Friday, July 06, 2012, 15:36 Friedhelm Ames      Doneswitched everything offswitched everything off to prepare for
scheduled power outage on Monday
  
  136   Monday, July 09, 2012, 11:14 Aurelia Laxdal       Test Stand statusRestarted the PC at the Test Stand.
Restarted the Archivers; currently
pumping down the separator area.
  
  137   Monday, July 09, 2012, 12:57 Anders Mjos      DoneVented    
  138   Tuesday, July 10, 2012, 16:01 Anders Mjos      Problems/SolutionsTurbo replaced - cleaning chamber recommendedA new turbo has been
installed. Eddie said the other one had 
     crashed but not catastrophically. He
  
  139   Wednesday, July 11, 2012, 11:16 Anders Mjos      In progressPumping down - with new turbo pump    
  140   Wednesday, July 11, 2012, 15:30 Anders Mjos      Problems/SolutionsRestarting turbos after power bumpWednesday, July 11, 2012, 15:27: Started
TSGTP1A and 1B
Wednesday, July 11, 2012, 15:31:
  
  141   Thursday, July 12, 2012, 09:05 Anders Mjos      Problems/SolutionsShut down TSGTP1A - bearing noiseShut down TSGTP1A due to noise (possibly
from bearings) after consulting Edi.
  
  142   Thursday, July 12, 2012, 09:44 Anders Mjos      In progressVentingSystem will be vented and gas lines purged
with air, then nitrogen.
Thursday, July 12, 2012, 09:43: Shut
  
  143   Thursday, July 12, 2012, 12:23 Anders Mjos      DoneTSH:SV5 bypass onThursday, July 12, 2012, 15:48: bypass
removed
  
  144   Thursday, July 12, 2012, 13:41 Anders Mjos      Donepurging gas lines with air
    gas lines purged with air for
60 min (through TSHUHV1 and TSHSV4).

   gas line allowed to fill with nitrogen
  
  145   Thursday, July 12, 2012, 13:49 Anders Mjos      Problems/SolutionsAluminum oxide found inside TSHSV1Aluminum oxide found inside TSHSV1 and
the copper line to TSHUHV1.
SV1 replaced and copper line cleaned.
  
  146   Thursday, July 12, 2012, 15:49 Anders Mjos       test stand vented for TP1A replacementsee e-fault 6142   
  147   Monday, July 16, 2012, 15:46 Anders Mjos      In progressPumping downMonday, July 16, 2012, 15:11: Roughing.
Monday, July 16, 2012, 15:38: Turbos
started.
  
  148   Tuesday, July 17, 2012, 10:10 Anders Mjos      Problems/SolutionsGas lines leak checked - air supply leak on manifoldLeak found on the Ne supply line. 1E-4
- 1E-5 range. Replaced fittings. Had to use
one brass piece. Leak rate 6E-9 (probably
  
  149   Wednesday, July 18, 2012, 14:08 Anders Mjos      Problems/SolutionsAir supply leak on manifold fixed

    

       
            
  
  150   Thursday, July 19, 2012, 08:42 Anders Mjos      Problems/SolutionsLeak checking source chamber - leak found on front doorDue to high vacuum a leak check will be
done on the system.
Thursday, July 19, 2012, 09:00 :
  
  151   Thursday, July 19, 2012, 09:35 Anders Mjos      DoneVenting to investigate leak on front doorThursday, July 19, 2012, 09:35: Switched
off both turbos.
Thursday, July 19, 2012, 10:23: Venting
  
  152   Thursday, July 19, 2012, 11:31 Anders Mjos      Problems/SolutionsWiped o-rings and sealing faces

    

       
            
  
  153   Thursday, July 19, 2012, 11:32 Anders Mjos      DonePumping downThursday, July 19, 2012, 11:29: roughing
Thursday, July 19, 2012, 11:49: starting
turbos
  
  154   Thursday, July 19, 2012, 12:59 Anders Mjos      Problems/SolutionsLeak checking doors - no responseThursday, July 19, 2012, 12:57: Doors leak
checked. No response. Base rate 1.6E-8 atm-cc/sec.
TP pressuer 0.0E-4 Torr . TSGIG1 4.2E-6 Torr.
  