Message ID: 744     Entry time: Monday, July 08, 2019, 09:20
Author: Luca Egoriti 
Target/No.#: p2n1 
Source:  
Station: ITE 
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: In progress 
Subject: p2n heating test 

(see entry 742)

 

p2n target heated over the weekend after the connections between the bottom target legs and the copper connector has been modified from rivets to M3 screws. Target hold current nicely with no major voltage spikes.

The plan now is to cycle the current heating few times to "stress test" the target.