Message ID: 473     Entry time: Thursday, October 15, 2015, 11:19
Author: Anders Mjos 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: Right side TGHT connector block removed 

The keensert has been worn out and will be replaced.

The keensert was re-tapped and the block re-installed. New bolts used for TGHT connection (2x). Swagelok T connections shortened (pluged).