Message ID: 449     Entry time: Monday, June 15, 2015, 14:07
Author: Anders Mjos 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: Test Stand Source Tray installed 

Monday, June 15, 2015

Remaining items to do

  • ANODE wire not yet attached
  • FEBIAD COILS not yet reconfigured

Tuesday, June 16, 2015:

Coils reconfigured. See attached photo.

 

Attachment 1: Coils_configuration.jpg  1.617 MB  Uploaded Monday, June 22, 2015, 17:04  | Hide | Hide all
Coils_configuration.jpg