Message ID: 337     Entry time: Friday, September 27, 2013, 11:41
Author: Anders Mjos 
Target/No.#: Ta#41 
Source: HP-SIS 
Station: ITW 
Module: TM4 
Target Oven W.O#: 39069-5 
Heat Shield W.O#: 38817-10 
Status: Done 
Subject: Ta#41 Conditioning 

Friday, September 27, 2013, 11:41: Roughing

Friday, September 27, 2013, 12:08: Turbos started

Friday, September 27, 2013, 12:16: Turbos at speed.

Friday, September 27, 2013, 12:18: Vacuum at 1.5E-5 T


Monday, September 30, 2013, 08:41: Opened water supply. Vacuum stable at 1.5E-7 T

TGHT Q=5.5 T=28.0
TBHT Q=5.8 T=28.0

Monday, September 30, 2013, 15:19: Flow sensor moved from TBHT to HS

TGHT Q=5.5 T=27.9
HS      Q=3.6 T=27.8


Tuesday, October 01, 2013, 12:08: Taget Biased to 30kV.


Wednesday, October 02, 2013, 08:50: Started autoramping to 580A/230A

Wednesday, October 02, 2013, 08:50: Opened IV4

Wednesday, October 02, 2013, 10:51 TGHT/TBHT 250A / 239A
TGHT Q=5.5 T=28.5
HS      Q=3.6 T=29.2
SUPPLY (ext)    27.3
RETURN (ext)  27.8

Wednesday, October 02, 2013, 13:28 TGHT/TBHT 250A / 570A
TGHT Q=5.5 T=30.4
HS      Q=3.6 T=33.4
SUPPLY (ext)    27.4
RETURN (ext)  29.3

Wednesday, October 02, 2013, 13:30: TBHT was starting to limit on voltage. Increased voltage limit to 2.4V.


Thursday, October 03, 2013, 08:21: TMS:TP2 timed out over night.

Magnet PS breaker tripped during a mass scan yesterday. Reset breaker and cleared interlocks.

TGHT Q=5.5 T=30.4
HS      Q=3.6 T=34.0
SUPPLY (ext)    27.3
RETURN (ext)  29.3

Thursday, October 03, 2013, 08:28: Started mass scan 200 -> 0 m/q. FC0 7.5E-8 A

Thursday, October 03, 2013, 14:29
TGHT Q=5.5 T=30.6
HS      Q=3.6 T=33.9
SUPPLY (ext)    27.4
RETURN (ext)  29.6

Thursday, October 03, 2013, 15:14: Lowered TBHT:RDCUR  to 230A.

Thursday, October 03, 2013, 15:37: Increased EE to -2000 V

Thursday, October 03, 2013, 16:22
TGHT Q=5.5 T=30.6
HS      Q=3.6 T=33.9
SUPPLY (ext)    27.5
RETURN (ext)  29.6


Friday, October 04, 2013, 08:08
TGHT Q=5.5 T=30.6
HS      Q=3.5 T=33.9
SUPPLY (ext)    27.5
RETURN (ext)  29.3

Mass scan started.

Friday, October 04, 2013, 08:46: Cool down started.

Friday, October 04, 2013, 13:35: TPS:IV4 closed

Friday, October 04, 2013, 13:41: Source debiased.


Tuesday, October 15, 2013, 09:56: Turbos stopped. Vacuum at 1.15 E-7 T

Tuesday, October 15, 2013, 12:44: Venting


After the conditioning, some oxidation (?) from the standards (?) were found on the Plasma Electrode and around the Target Tube. See attachment