Wednesday, May 29, 2013, 12:09: Debiased to insert temp logger
Wednesday, May 29, 2013, 14:40: Temp logger installed
CH1 COIL
CH2 CTL Block
Wednesday, May 29, 2013, 14:51: Opening gas lines
Temperatures [deg C]
COIL: 190
CTL: 44
Wednesday, May 29, 2013, 15:31: Coil at 50A
Temperatures [deg C]
COIL: 212
CTL: 45
Thursday, May 30, 2013, 09:18: TGHT was voltage limited at about 570A. Increased voltage limit to 5.5V and raised current to 580A
Thursday, May 30, 2013, 09:20: Ramping TBHT to 280A
Thursday, May 30, 2013, 10:03
Temperatures [deg C]
COIL: 227
CTL: 48
Thursday, May 30, 2013, 10:07: Heard a noise from the vacuum chamber coinciding with a spike in vacuum on both gauges.
Monday, June 03, 2013, 08:54: Target debiased and gases off. Target cooling started in preparation for power outage tomorrow at 9am.
Wednesday, June 05, 2013, 09:57: Purging gas lines to vacuum chamber
Wednesday, June 05, 2013, 10:13: Target biased again. Started target heating.
Thursday, June 06, 2013, 13:23:
Temperatures [deg C]
COIL: 227
CTL: 48
Thursday, June 06, 2013, 16:45: TBHT increased ti 290A
Temperatures [deg C]
COIL: 230
CTL: 50
Friday, June 07, 2013, 08:40: Magnet found off. TPS:Q4 and TPS:Q2 found off.
Temperatures [deg C]
COIL: 227
CTL: 48
Friday, June 07, 2013, 14:21: Anode current limit increased to 500 mA. Adjusted magnet current. Increasing TBHT.
Friday, June 07, 2013, 16:24: TBHT at 296A
Temperatures [deg C]
COIL: 237
CTL: 50
Monday, June 10, 2013, 08:19
Temperatures [deg C]
COIL: 232
CTL: 49
Monday, June 10, 2013, 16:55: COIL at 60A
Temperatures [deg C]
COIL: 244
CTL: 49
Tuesday, June 11, 2013, 08:42: TBHT voltage limited this morning at 291A
Temperatures [deg C]
COIL: 242
CTL: 49
Tuesday, June 11, 2013, 11:02: COIL at 70A
Temperatures [deg C]
COIL: 256
CTL: 49
Tuesday, June 11, 2013, 15:49: COIL at 80A
Temperatures [deg C]
COIL: 272
CTL: 49
Wednesday, June 12, 2013, 08:19:
Short on TBHT - see attached photo.
T/C logger is is off.
Gas lines closed.
Cooling down target.
Target debiased.
Thursday, June 13, 2013, 08:37: Turbos stopped.
Thursday, June 13, 2013, 09:20: Water lines purged.
Thursday, June 13, 2013, 09:41: Venting
Thursday, June 13, 2013, 10:19: Target removed |