Message ID: 13     Entry time: Monday, September 26, 2011, 16:14
Author: Anders Mjos 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: Fixed leak on water line for HS, added Kapton insulation 
  • While testing SiC#26 a leak was discovered on the water line to the heat shield. The leak was in the right joint (see attachment). The heat shield water lines were removed from the test stand and repaired in the Machine Shop. 
  • Kapton was added to the FEBIAD coil line to prevent it from shorting to the target heater line (see attachment).
Attachment 1: Water_Leak.pdf  172 kB  | Show | Hide all
Attachment 2: Kapton.pdf  219 kB  | Hide | Hide all