Message ID: 118     Entry time: Tuesday, June 21, 2022, 15:34
Author: Matthew Gareau 
Target/No.#: SiC#42, SiC#43 
Source:  
Station:  
Module: TM2 
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: Multipin guide pin issues 

 While removing the SiC#42 it became apparent that the multipin guide pin had become loose again and was not allowing the target to dismount from the module.

The multipin shoulder bolts were removed and then the multipin was able to be pried off.

However the NHC manipulator were not able to reach the guide pin to remove it, which would be required before the SiC#43 could be installed.

The target module was then moved to the SHC where the guide pin could be removed and the installation of SiC#43 took place, along with the transfer of the parasitic attachment onto the SiC#43.

This problem seems to suggest that the multipin could use some redesign to ensure smoother target exchanges.