  ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  997   Wednesday, July 15, 2015, 11:02 chad fisherSouth Hot-CellRepairTM2 TM2 Coil Line Vacuum Leak CheckTM2 coil line R,U has been vacuum leaked
check at the hot cell and has passed with
no response from the leak detector.
  
  1000   Thursday, July 16, 2015, 14:36 chad fisherSouth Hot-CellRepairTM2 TM2 StatusIMG gauge, clip for ground to window lines
and gas line extensions were installed today.
David and I also tried to locate
 20150716_110247.jpg20150716_142818.jpg 
  1001   Friday, July 17, 2015, 13:51 chad fisherSouth Hot-CellRepairTM2 TM2 StatusGas lines extensions installed yesterday
were too long and gas lines touched top inside
of containment box. They have been removed
 20150717_134123.jpg 
  1002   Monday, July 20, 2015, 14:12 chad fisherSouth Hot-CellRepairTM2 TM2 StatusUltem high voltage spacer installed and
9 pin banana plug plugged in. Target has
been inserted into the hot cell and will
 20150720_134819.jpg20150720_135747.jpg20150720_140100.jpg 
  1009   Wednesday, July 22, 2015, 12:13 chad fisherSouth Hot-CellRepairTM2 TM2 Short FindingsPin X was unplugged, short remained, however
any slight pressure on the block towards
the source tray makes the short go away.
 TM2_Short_July_22.jpg 
  1022   Tuesday, July 28, 2015, 14:36 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 AutopsyExtraction electrode was removed from SiC#31
and target inspected.
Pictures of findings can be found
  
  1023   Tuesday, July 28, 2015, 14:40 chad fisherSouth Hot-CellStandard OperationTM4SiC#31 UCx#13SiC#31 removed UCx#13 installedSiC#31 has been removed from TM4 and UCx#13
installed. UCx#13 connection to the 9 pin
connector was VERY VERY tight to the tube
 20150727_115314.jpg 
  1033   Thursday, August 13, 2015, 09:17 chad fisherSouth Hot-CellRepairTM2 TM2 statusTuesday, August 11,  insulator ITA6272
was installed onto the "pin x"
line (unused plasma electrode) and tested;
 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg 
  1035   Thursday, August 13, 2015, 13:46 chad fisherSouth Hot-CellRepairTM2 TM2 StatusAs previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to
  
  1049   Wednesday, August 26, 2015, 10:55 chad fisherSouth Hot-CellRepairTM2ZrC#7New wiring and targetNew wiring was installed yesterday as well
as ZrC#7 which had its high current fasteners
torqued to 130 in lbs.
 20150826_090047.jpg 
  1065   Thursday, September 10, 2015, 08:55 chad fisherSouth Hot-CellRepairTM1 TM1 Window Leak Diag.Vacuum leak check on the window line circuit
of TM1 took place yesterday and again to
confirm this morning. Both days the response
 P0000122.JPG 
  1066   Thursday, September 10, 2015, 08:59 chad fisherSouth Hot-CellRepair  Manipulator Mait. and field check Sept. 4Hot cell was entered for preventative mait.
on left manip. field measurements around
the cell were taken in prep. for window removal
  
  1069   Tuesday, September 15, 2015, 11:06 chad fisherSouth Hot-CellRepairTM1 TM1 Window Gasket ReplacementReplaced the custom silver gaskets on the
entrance window panel of TM1 this morning...this
has eliminated an sign of leak at this joint,
  
  1101   Wednesday, October 14, 2015, 14:03 chad fisherSouth Hot-CellStandard OperationTM2ZrC#7ZrC#7 removedZrC#7 has been removed from TM2. Everything
looks good.
 20151014_134022.jpg20151014_135127.jpg 
  1104   Thursday, October 15, 2015, 14:17 chad fisherSouth Hot-CellRepairTM2 Anode Connector Install and adjustmentThe TM2 containment box was removed this
morning for installation of the 9 pin connector...connection.
The 9 pin connector copper tube connection
 20151015_085914.jpg 
  1105   Monday, October 19, 2015, 11:53 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 installed on TM2SiC#32 has been installed on TM2. High
current fasteners torqued to 130 in lbs.
  
  1109   Tuesday, October 20, 2015, 13:52 chad fisherSouth Hot-CellMaintenance  TM4 Febiad coil line disposalThe febiad coil line removed from TM4 has
been cut into pieces small enough to be disposed
of in a 5 gal pal. The line was cut with
 20151020_133045.jpg20151020_134303.jpg 
  1110   Wednesday, October 21, 2015, 09:49 chad fisherSouth Hot-CellRepair  Manipulator handle repairRebuild handle of manipulator serial 7986
(currently in the east position) and replaced
broken snap ring 5555-18h on west side of
  
  1113   Friday, October 23, 2015, 11:30 chad fisherSouth Hot-CellStandard Operation ZrC#7ZrC#7 Spent Move and Febiad CoilZrC#7 was transfered to a spent target
disposal pail today and removed from the
hot cell. The "hot" end of the
  
  1129   Tuesday, November 24, 2015, 13:54 chad fisherSouth Hot-CellRepair  Cell DeconDecon/removal of large solid waste was
performed on Wednesday November 18th."Hot"
activated items included containment box
  