Thursday, March 16, 2017, 12:24, chad fisher, South Hot-Cell, Maintenance, , , West 'Z' motion cable replacement
|
The west 'Z' motion cable on the east manipulator has successfully been replaced. The job took slightly less than an hour (including inspection of the scissor table hoses) and I received 0.075mSv. Scissor table hoses appear to be fine and also didn't "shed" or flake at all when checked by hand. |
Wednesday, March 22, 2017, 14:05, Travis Cave, South Hot-Cell, Standard Operation, TM2, test target, module moved
|
TM#2 has been moved from the east target station to the south hot cell. |
Thursday, March 23, 2017, 09:30, Travis Cave, South Hot-Cell, Standard Operation, TM2, test target, Electrical Check
|
Electrical check of the Ta test target on TM#2 |
Monday, March 27, 2017, 13:40, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical Check 
|
Did the start of the running year electrical checks of both TM#2 and TM#4 with no target attached to either module. TM#2 was in the south hot cell and TM#4 is in the conditioning station under vacuum. |
Tuesday, March 28, 2017, 09:18, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module moved
|
TM#4 has been moved from the conditioning station to the south hot cell. |
Tuesday, March 28, 2017, 10:30, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#19, Electrical Check
|
Electrical check done on TM#4 with UC#19. See attached PDF for results. |
Tuesday, March 28, 2017, 10:44, chad fisher, South Hot-Cell, Standard Operation, TM4, UCx#19, UCx#19 Installed
|
UCx#19 has been installed onto TM4. High current fasteners torqued to 130 in lbs. Has been leak and electrical checked and is ready to leave hot cell. |
Tuesday, April 11, 2017, 11:30, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#51, Electrical Check
|
Electrical check performed on TM#2 with Ta#51, see attached PDF. |
Wednesday, April 12, 2017, 09:20, Travis Cave, South Hot-Cell, Repair, TM3, no target, Module move
|
TM#3 is now in the south hot cell. |
Wednesday, April 12, 2017, 12:51, David Wang, South Hot-Cell, Repair, TM3, , TM3 Ram readings @ SHC
|
We have a ram installed on SHC pole which is 0.5 meter to module shielding block surface. the readings we got today during TM3 move:
at containment box center (highest reading): 3.14 msv/hr.
at bottom of shielding blocks: 960 usv/hr.
at 1/4 of shielding blocks height from bottom :700usv/hr.
at 1/2 of shielding blocks height from bottom: 340usv/hr.
at 3/4 of shielding blocks height from bottom:140u/sv/hr.
The Ram is behind the pole and measured the surface which is 90 degree right side of that opened service tray side. |
Wednesday, April 12, 2017, 13:03, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, Electrical Check
|
Electrical check of TM#3 with no target at the south hot cell |
Wednesday, April 12, 2017, 16:39, Aurelia Laxdal, South Hot-Cell, Repair, TM3, no target, TM3 Inspection at the South Hot Cell 
|
Found spark signs on TM3's containment on the side of the water blocks. They may be OLD or/and NEW sparking signs, but this in not determined at this moment. Please see picture: first attachment. First and second attachment show the profiles of water block and HV lines. |
Thursday, April 13, 2017, 10:32, chad fisher, South Hot-Cell, Repair, TM3, , TM3 Lower Service Tray Video Inspection
|
A video inspection of the lower service tray was performed this morning. Camera was inserted upwards into the service tray/service chase from the containment box. One potential spark mark was identified as well as epoxy not flush with insulator. Fiberglass does not extend into service tray/chase much and does not look, from initial inspection that it will be too difficult to remove.
Video can be found in docushare Document-142295 |
Monday, April 24, 2017, 16:06, David Wang, South Hot-Cell, Repair, TM2, , Crane main hoist strane noise when lifting up TM2
|
When lifting up TM2 (20000lbs) this afternoon, TH crane has a strange noise on main hoist. The module was lift up less than 1 feet.when strange sound was noticed. The module move was stopped right away,and module was lowed back to SHC. The strange noise was confirmed later with SEG block six inches lifting up. Gordon crane technician will be here to tomorrow morning to investigate the problem. |
Wednesday, April 26, 2017, 08:28, chad fisher, South Hot-Cell, Repair, TM3, , TM3 progress and manipulators
|
containment box was re-installed onto TM3 on Monday, Left manipulator may be showing signs of eminent handle or tong cable failure. |
Wednesday, April 26, 2017, 10:40, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, Module move
|
TM#3 has been moved from the north east silo to the south hot cell. |
Wednesday, April 26, 2017, 13:35, chad fisher, South Hot-Cell, Repair, TM3, , TM3 containment box removed
|
the containment box has been removed from TM3. |
Wednesday, April 26, 2017, 16:52, Aurelia Laxdal, South Hot-Cell, Repair, TM3, , TM3 Lower Service Tray Video Inspection
|
chad fisher wrote: |
A video inspection of the lower service tray was performed this morning. Camera was inserted upwards into the service tray/service chase from the containment box. One potential spark mark was identified as well as epoxy not flush with insulator. Fiberglass does not extend into service tray/chase much and does not look, from initial inspection that it will be too difficult to remove.
Video can be found in docushare Document-142295
|
The attached picture is from the video: showing the fiber glass inside the Service Tray. |
Wednesday, April 26, 2017, 17:37, Aurelia Laxdal, South Hot-Cell, Repair, TM3, no target, TM3 HV tests at atmosphere Pictures from April 19-21, 2017  
|
Please see the first two pictures of the HV test at atmosphere done on April 19.
First picture shows a big spark between the Extraction Electrode mounting plate holder (at HV) to the Ground Electrode. Please note minimum gap between these electrodes is 7.8mm.
However the biggest visible spark was noticed at the bottom screw hole. (It is difficult to determine if at the 7.8mm gap were concomitant sparks occurring.)This spark started at 22kV and became stable above 24kV.
On April 20, 2017 Chad inspected this area with the Hot Cell camera and found a spark mark on the Extraction Electrode holder plate at the bottom screw hole. See the third picture.
Again it is very difficult with the existing Hot Cell cameras to inspect the areas where the gap is small (at 7.8mm gap between the conical surfaces of the Ground Electrode and Extraction Electrode holder)
In the second picture there are 2 small sparks: one on the top and another one on the right side at the lines wrapped in Fiber Glass. These sparks started at 20kV.
On April 21 the HV test was repeated with the Containment box ON and the sparks occurred again, at the same locations and at the same voltage. |
Wednesday, April 26, 2017, 17:55, Aurelia Laxdal, South Hot-Cell, Repair, TM3, no target, TM3 Schedule updates at the South Hot Cell and CS 
|
Please see TM3's Updated Schedule (the current schedule) at the SHC and TCS.
For the record I am uploading TM3's Initial Schedule at the SHC and TCS. |
|