809
|
Thursday, December 04, 2014, 09:49 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | no target | module move |
TM#2 has been moved from the south hot cell to the conditioning station. |
810
|
Thursday, December 04, 2014, 09:54 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Electrical check |
Results of electrical check of TM#2 with no source tray and no containment box attached. See PDF for results. |
Attachment 1: TM2_elec_check_no_source_traySHC.PDF
|
|
811
|
Thursday, December 04, 2014, 09:57 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent target placed in F-308. |
Spent targets in the mini storage were placed into the F-308s yesterday, all F-308 have been removed from the the target hall and they no reside for the time being in the hallway between the north and south hot cells. |
857
|
Tuesday, March 10, 2015, 09:01 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Module move |
TM#1 has been moved from the west station to the south hot cell had the ThO#1 target removed and then the modules was moved from the south hot cell to the south west silo. Also an electrical check was done on the target before it was removed. |
Attachment 1: TM1_THO_elec_chk_postbeamSHC.PDF
|
|
858
|
Thursday, March 12, 2015, 09:48 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | No target | Module move |
TM#2 with no target and no source tray has been moved from the conditioning station to the north east silo. |
861
|
Friday, March 13, 2015, 13:36 |
Travis Cave | Spent Target Vault | Standard Operation | | ThO#1 | Spent Target Move |
The ThO#1 has been placed in the storage vault placed in pail #122 in spot 2B of the vault. It was 6.2mSv/hr upon removal from the south hot cell. see attached PDF for details. |
Attachment 1: Storage_Vault_March_13_2015.pdf
|
|
862
|
Monday, March 16, 2015, 09:41 |
Travis Cave | ITE | Standard Operation | TM4 | UC#11 | Module move |
TM#4 with UC#11 moved from the east target station to the south hot cell. |
863
|
Monday, March 16, 2015, 14:16 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | No target | Module move |
TM#4 from south hot cell to the conditioning station no target is attached to the module. |
864
|
Tuesday, March 17, 2015, 10:33 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#11 | Spent Target Move |
The spent UC#11 has benn moved from the south hot cell to the spent target vault. See attached PDF for details. |
Attachment 1: Vault_Storage_March_17_2015.pdf
|
|
868
|
Tuesday, March 24, 2015, 08:46 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | No target | Module move |
TM#4 with no target has been moved from conditioning station to the south hot cell. |
870
|
Tuesday, March 24, 2015, 13:57 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#45 | Electrical check |
TM#4 electrical checks with and without the target installed, installed target is Ta#45. |
Attachment 1: TM4_no_tgt_elec_chk_CS.PDF
|
|
Attachment 2: TM4_Ta45_elec_chk_SHC.PDF
|
|
874
|
Thursday, March 26, 2015, 09:20 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Ta#45 | Electrical check |
Electrical check of TM#4 with Ta#45 at the conditioning station, see attached pdf for details. |
Attachment 1: TM4_Ta#45_tgt_elec_chk_CS.PDF
|
|
881
|
Wednesday, April 01, 2015, 10:52 |
Travis Cave | ITE | Standard Operation | TM4 | Ta#45 | Module move |
TM#4 with Ta#45 has been moved from the conditioning station to the east target station. |
887
|
Friday, April 17, 2015, 09:09 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | No target | Module move |
TM#1 with no target has been moved from the south west silo to the south hot cell for the installation of the UCx target. |
888
|
Friday, April 17, 2015, 11:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Electrical check |
Electrical check of TM#1 with UCx#12 attached. See attached PDF for details. |
Attachment 1: TM1_UC#12_tgt_elec_chk_SHC.PDF
|
|
889
|
Friday, April 17, 2015, 14:04 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Module move |
TM#1 with UCx#12 has been moved from the south hot cell to the conditioning station. |
904
|
Tuesday, April 28, 2015, 11:14 |
Travis Cave | ITW | Standard Operation | TM1 | UC#12 | Module move |
TM#1 with UC#12 has been moved from the conditioning station to the west target station. |
906
|
Thursday, April 30, 2015, 08:50 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | No target | Module move |
TM#2 with no source tray has been moved from the north east silo to the south hot cell. |
911
|
Wednesday, May 06, 2015, 14:30 |
Travis Cave | South Hot-Cell | Repair | TM2 | No target | Wiring of TM#2 |
Wires for TM#2 steering elements, and png gauge have been run down to the containment box level. Chad has placed them in the little cable trays. Slack has been pulled back. and termination of the wire will be done on the 7th of May. A modification was done to the signal line of the png gauge wire ultem block, as grounded screw was inserted to allow for strain relief so the end would hopefully quit breaking. See attached pictures for the details. |
Attachment 1: Photo_2015-05-06_8_26_10_AM.JPG
|
|
Attachment 2: Photo_2015-05-06_8_26_17_AM.JPG
|
|
912
|
Thursday, May 07, 2015, 11:02 |
Travis Cave | South Hot-Cell | Repair | TM2 | No target | Wiring of TM#2 |
Wires in TM#2 have been terminated at the top of the module. |